![]() | Special Public Works Programmes - SPWP - Anti-Erosion Ditches - Training Element and Technical Guide for SPWP Workers, Booklet No. 1 (ILO - UNDP, 84 p.) |
![]() | ![]() | (introduction...) |
![]() | ![]() | 1. What is erosion? |
![]() | ![]() | 2. How to recognise erosion |
![]() | ![]() | 3. Different types of anti-erosion ditches |
![]() | ![]() | (introduction...) |
![]() | ![]() | 3.1 Silt catchment pits |
![]() | ![]() | 3.2 Forest tiering |
![]() | ![]() | 3.3 Forest terracing |
![]() | ![]() | 3.4 Cropping terraces |
![]() | ![]() | 4. Worksite organisation |
![]() | ![]() | (introduction...) |
![]() | ![]() | 4.1 Good management of the workers |
![]() | ![]() | 4.2 Good selection of tools |
![]() | ![]() | (introduction...) |
![]() | ![]() | 4.2.1 Surveying Instruments |
![]() | ![]() | 4.2.2 Tools used in the digging of ditches |
![]() | ![]() | 5. Procedure |
![]() | ![]() | 5.1 Site selection |
![]() | ![]() | 5.2 Siting of the ditches |
![]() | ![]() | 5.3 Plotting the dimensions of the ditch |
![]() | ![]() | 5.4 Preparing the surface soil of the ditch site |
![]() | ![]() | 5.5 Excavating the ditch |
![]() | ![]() | 5.6 Checking the dimensions of the ditch |
![]() | ![]() | 5.7 Constructing the retaining banks |
![]() | ![]() | 5.8 Checking that the retaining banks are horizontal |
![]() | ![]() | 5.9 Improving the waterways |
![]() | ![]() | 5.10 Protecting the slopes |
![]() | ![]() | 6. Maintenance of the retaining banks |