3.7 Management considerations
Water and sanitation infrastructure installed during an
emergency will always need maintenance. The requirement will be determined by
how well the system has been designed and constructed, and how well it is
managed. Technically complicated systems will require a high degree of
maintenance.
Pumped water systems are always problematic. A regular supply of
diesel or petrol must be secured. Mechanics need to be trained and workshop
facilities established. Standby capability is a necessity, and reserve pumps,
generators and spare parts must be budgeted for and made available.
If water is being chemically treated, stock levels need to be
maintained to provide at least sufficient capacity to guarantee the provision of
water until replacement orders arrive. Planned procurement and replacement of
hardware must be organised. Similarly, stock levels of water fittings such as
valves have to be maintained. This implies a high degree of management and a
good level of stock control, and all this becomes doubly important, as donors
are increasingly demanding greater accountability for the funds they make
available in emergencies.
Staff employed to operate the system must be well trained not
only to perform their daily tasks, but also to understand why they are doing so.
This, if something goes wrong, they will be better equipped to correct it. Until
this level of training has been reached, the systems will need a high level of
technical supervision and staffing. All too often water systems costing
considerable sums of money are installed, and the 'experts', who have usually
been flown in to supervise the installation, leave the project to be run by
semi-trained local staff, who, through no fault of their own, have difficulty
providing the service expected. Training of staff plays a vital part in the
long-term success or failure of a programme.
Water and sanitation programmes use large amounts of manual
labour, whether for digging pits for latrines or trenches for pipelines, for
mixing concrete for water point or washing areas, for constructing storage
reservoirs, for guarding installations and stock, or for operating pumps. A
labour force of this size requires a great deal of management. Accurate records
have to be kept of daily attendance; tools have to be provided; work needs to be
supervised to ensure quality; and people have to be paid regularly. From the
outset, a clear policy must be decided. How often and at what rate will people
be paid? And on a daily or piece rate? Will some of the work e.g. constructing
latrines be on a contract basis? What are the daily working hours? Will refugees
or residents be used? Will people be working on religious days?
Box 4
As a result of inexperience, an expatriate engineer found
himself threatened by a group of labourers who had been laughing and joking with
him only the previous day. Local people had been employed to construct latrines
on a greenfield site to which refugees were to be transferred. After the
refugees arrived be continued to use local labour. It was then suggested that
refugee labour might now be used. He agreed and without any warning, when the
locals arrived for work the next day, they were told there was no more work.
From the outset, the labour force should have been kept informed about the
amount of work they would be receiving. Difficult situations can be avoided if
consideration is given to actions beforehand. |
Such issues need to be clear to the programme co-ordinator and
to the people who are employed. It is worthwhile taking time to resolve these
issues at the outset. If other agencies are working in the area, it is a good
idea to have an agreed rate of pay and agreed working hours so that there is
unanimity of conditions between agencies. If these issues are not resolved a
great deal of time and energy can be taken up on an almost daily basis resolving
personnel issues - time that should be spent elsewhere. It can also lead to
problems of security for local and international, staff as was recently the case
in
Rwanda.