Revised Table of Detailed Project Activities.
|
No. |
Activity |
Time Frame |
Responsibility |
Status |
|
1. |
Appointment of the National Project Director |
March 1997 |
MOFARD/NPD |
Completed |
|
2. |
NARA should identify the officers to be engaged in the project implementation. |
March 1997 |
NPD/NARA |
Completed |
|
3. |
Completion of the MOFARD's proposed Shrimp Farming Training and Extension Centre (SFTEC) at Chilaw |
March 1997 |
NPD |
Completed |
|
4. |
Transfer the MOFARD/AQD's Fish Health Officer (FHO) to the proposed centre at Chilaw |
Mid April 1997 |
NPD |
Completed |
|
5. |
FAO/FIRI Fish Health Specialist will visit the project to finalise/fine tune the project implementation arrangements. Duration two weeks. Terms of Reference annexed |
March 1997 |
FAO |
Completed |
|
6. |
Selection of sites for farmer training and field research programmes. The sites will be selected from private farms and this activity requires discussions between the SFASL, MOFARD/FHO, and NARA. |
April 1997 |
NPD/FAO/Dr Simon Smith |
Completed |
|
7. |
An international consultant on shrimp health management (Consultant 1) to be mobilised for one month. Terms of Reference annexed. Consultant 1 will finalise the selected sites and advise the NPD. FHO, SFASL, and NARA officers on establishing the relevant experiments at the selected experimental sites. The details of the pilot experiments to be conducted will be provided to the Consultant 1 by the FAO/FIRI Fish Health Specialist following his mission in March 1997. Consultant 1 will identify the equipment necessary to upgrade NARA and MOFARD Extension Centre at Chilaw (see Recommendations). |
April to May 1997 |
NPD/FAORAP/ FAO |
Completed |
|
8. |
Appointment and first meeting of the Progress Review Committee (see Recommendations). This meeting should coincide with the visit of the Shrimp Health Consultant, Dr Simon Smith. |
Early May 1997 |
NPD/Dr Smith |
Completed |
|
9. |
First local training workshop aimed at 50-70 farmers in a location/site selected by NPD/SLSFA/Dr Smith and as described. Workshop should coincide with the visit of Consultant 1 (see Recommendations). |
May 1997 |
NPD/SLSFA/Dr Simon Smith |
Completed |
|
10. |
Overseas training at AAHRI/Bangkok on shrimp health management for two officers (MOFARD/AQD and NARA) and PCR technology training for one technician from NARA (see Recommendations). |
Mid May 1997 |
FAORAP/NPD FAO/HQ |
Completed |
|
11. |
Second local training programme |
Early June 1997 |
NPD/SLSFA |
Completed |
|
12. |
Purchase of equipment including PCR equipment |
End June 1997 |
NPD/FAORAP |
Ordered; awaiting arrival |
|
13. |
Identification and recruitment of a national legal consultant (Consultant 2) for one month to collect and study the national regulations and legislation on aquaculture and to work together with international legal consultant during her mission (see Recommendations and new TOR) |
December 1997* |
NPD/FAORAP |
To be done |
|
14. |
Third local training programme |
Early July 1997 |
NPD/SLSFA |
Completed |
|
15. |
An international legal consultant (Consultant 3) to be identified and recruited. Consultant 3 will visit the project for a period of three weeks to review the aquaculture legislation, assess requirements, and present options. Consultant 3 will communicate and work with Consultant 2 before and during her visit to the project to maximise the efficiency. Terms of Reference are attached. Duration: 3 weeks + 1 week report writing (see Recommendations). |
March 1988; to be done in conjunction with #25* |
NPD/FAORAP |
To be done |
|
16. |
At the end of the consultancy. Consultant 3 will hold a short (half a days) seminar/workshop with the concerned senior government officials, together with the relevant MOFARD and NARA officials. |
March 1998; to be done in conjunction with #25* |
NPD/FAOLEGN |
To be done |
|
17. |
Third local training programme |
End July 1997 |
NPD/SLSFA |
Completed |
|
18. |
NARA research programme on PCR screening for SEMBV to be operational and activities to be continued until October 1998.* |
End July 1997; collections begun in August 1997; analyses to begin in January 1998* |
NPD/NARA |
Active |
|
19. |
Second Progress Review Committee |
Early August 1997 |
NPD |
Completed; September 1997* |
|
20. |
Fourth local training workshop |
17 October 1997* |
NPD/SLSFA |
To be done |
|
21. |
An international consultant on aquatic animal quarantine and health certification (Consultant 4) will visit the project for a period of three weeks. Consultant 4 will work closely with the MOFARD/FHO, NARA staff, and the SFASL in reviewing and developing the appropriate practical guidelines on aquatic animal quarantine and health certification. Terms of Reference annexed. |
Late August 1997 |
FAORAP/NPD FAOHQ |
Completed; September/ October 1997* |
|
22. |
Fifth local training workshop to coincide with the visit of Consultant 4. |
31 October 1997* |
NPD/SLSFA |
To be done |
|
23. |
FAO/FIRI environmental officer (Consultant 5) will visit the project for a period of three weeks to conduct an investigation to study the environmental problems with respect to shrimp farming in Sri Lanka with a view to providing advice and develop necessary guidelines to ensure the sector sustainability. The environmental officer will work with the NPD. FHO, and the relevant MOFARD/NARA officials. Terms of Reference annexed. Duration 3 weeks plus 1 week report writing. |
March 1998; to be done in conjunction with #25* |
NPD/FAORAP |
To be done |
|
24. |
Mid-term evaluation/second technical backstopping mission by the FAO/FIRI Fish Health Specialist. The specialist will review the progress of the project, with special reference to the research programme, and help the NARA and MOFARD officers to analyse the data. Terms of Reference will be developed by the FAO/FIRI Fish Health Specialist by August 1997. Duration two weeks. |
March 1998; to be done in conjunction with #25* |
NPD/FAORAP |
To be done |
|
25. |
Public Seminar Workshop on shrimp culture, the environment and health management. The workshop will be sponsored by DFCC and EDB with some financial inputs from FAO under training budget. Number of international experts including Consultants 4 and 5, FAO/FIRI fish health specialist will also act as resource persons. Duration 2 days. Terms of Reference for the Public Seminar will be developed by FAO/FIRI Fish Health Specialist, in consultation with NPD, DFCC, EDB, etc., by the end of May 1997. |
March 1998* |
NPD/FAOHQ |
To be done |
|
26. |
Sixth local training workshop to coincide with the visit of Consultant 5. |
7 November 1997* |
NPD/SLSFA |
To be done |
|
27. |
Third Progress Review Committee to coincide with the FAO Mid-term Review Mission |
December 1997* |
NPD |
To be done |
|
28. |
NARA Research continues |
October 1997 |
NPD/FHO/NARA |
To be done |
|
29. |
Seventh local training workshop |
21 November 1997* |
NPD/SLSFA |
To be done |
|
30. |
Eighth local training workshop |
5 December 1997* |
NPD/SLSFA |
To be done |
|
31. |
Ninth local training workshop |
19 December 1997* |
NPD/SLSFA |
To be done |
|
32. |
Fourth Progress Review Committee Meeting |
March 1998; to be done in conjunction with #25* |
NPD |
To be done |
|
33. |
Initiation of the split-centre PhD research/training programme with NARA and Mahidol University in Thailand. The candidate will travel to Thailand for a period of three months and return to Sri Lanka to conduct research at NARA. The completion of the research work is the responsibility of NARA and the candidate concerned (See Recommendations). The Government of Sri Lanka and MOFARD will secure funds from another source to provide travel and stipend for the candidate to travel to Bangkok for writing up the thesis. |
January 1998 |
NPD/NARA |
Cancelled |
|
34. |
A consultant (Consultant 6) on aquaculture product quality control and inspection (an officer from the FIIU) will visit the project for a period of two weeks to evaluate the actual status of the implementation of inspection and quality assurance of aquaculture products in Sri Lanka with a view to providing recommendations for corrections and improvements, if needed, and also to training a group of core personnel from the government and industry in the field of the design and application of the HACCP concept to aquaculture products. Consultant 6 will conduct a 3-4 day training programme on HACCP procedures. Duration 2 weeks. Terms of Reference annexed. |
February 1998 |
NPD/FAORAP |
To be done |
|
35. |
Special training workshop on HACCP will be conducted by Consultant 6 during his visit to the project. Duration one day. |
Mid February 1998 |
NPD/SECO |
To be done |
|
36. |
Tenth local training workshop |
9 January 1998* |
NPD/SLSFA |
To be done |
|
37. |
Short-term visit (two weeks) by Consultant 1 to the project to provide further advice. Consultant 1 will examine the research progress made by the NARA team. He will also study the necessity of further support for the sector and will advise the Government of Sri Lanka and FAO on formulating a project proposal for donor funding. Duration 2 weeks. |
March 1998 |
NPD/FAORAP |
To be done |
|
38. |
Eleventh local training workshop |
23 January 1998 |
NPD/SLSFA |
To be done |
|
39. |
Fifth Progress Review Committee |
March 1998* |
NPD |
To be done |
|
40. |
Twelfth local training workshop |
6 February 1998* |
NPD/SLSFA |
To be done |
|
41. |
Thirteenth local training workshop |
27 February 1998* |
NPD/SLSFA |
To be done |
|
42. |
Fourteenth local training workshop |
6 March 1998* |
NPD/SLSFA |
To be done |
|
43. |
Second Public Seminar/Workshop on shrimp farming in Sri Lanka: past, present, and future, on the basis of the findings of the project. Duration 2 days. This workshop is to be coupled with the project terminal workshop to wrap up the project. Two officers from FAO/HQ will act as resource persons and DFCC and EDB will provide assistance to bring 2-3 resource persons from overseas. Regional Aquaculture Officer from FAO/RAP (Bangkok) will also join the workshop as a resource person. This final workshop will partly be sponsored by the EDB and DFCC and will discuss the alternate production strategies, environmental friendly shrimp culture and the future of shrimp health management in Sri Lanka. Duration 2 days. Terms of Reference will be developed towards the end of the project. |
November 1998* |
NPD/FAOHQ |
To be done |
|
44. |
Sixth and final Progress Review Committee Meeting to coincide with the Project Terminal Workshop. |
November 1998* |
NPD |
To be done |
|
45. |
Project termination |
December 1998* |
NPD/FAORAP |
To be done |
* indicates activity which has been rescheduled.