Concrete mixes are designated by three numbers, in some cases there are only two numbers. The ratio describes the quantity relationship which is determined by the architect or engineer.
a) The ratio 1:2:4
- The ratio 1 : 2 : 4 is defined
:- 1 part cement
- 2
parts fine aggregate/sand
- 4 parts rough aggregate/stone or
gravel
- For one cubic
metre of 1 : 2 : 4 concrete uses the
following:- 8 Bags of
cement
- 0.5m/3 of fine aggregate/ sand
- 1.0m/3 of coarse
aggregate/gravel
- 200 litre of water
b) Different ratios
- 1:2:4 is used for foundations, footing, footpath, troughs, slab, wall, bottom of the septic tank, etc.
- 1:2:3 is used for the walls of a septic tank,
- 1:2:2 is used for the top of a septic tank,
- 1:4 is used for concrete blocks.