![]() | Public Health Technician (MSF, 1994, 192 p.) |
![]() |
|
Manual intended for the setting up of public health programmes in disavantaged areas, particularly in refugee and displaced people camps
MEDECINS SANS FRONTIERES 1994 - 1st edition
The objective of this section is to suggest some concrete responses to water supply problems faced in camps of displaced people. However, most of the points considered, concern water problems in general, and apply to any deprived situation.
Like any population, displaced people need access to good quality water in sufficient quantity.
This need is that much greater in camps where the population concentration increases the risks of pollution and of epidemics of water-borne diseases.
Quantity
The notion of sufficient quantity is very subjective and depends strongly on the climate and on the habits of the population.
Nevertheless, it may be assumed that ten litres per person per day is a minimum need, while aiming to reach the following targets as soon as possible (UNHCR 1982):
- For domestic consumption: 15 - 20 litres per person per day
(drinking, cooking, hygiene).
- For collective feeding centres: 20 - 30
litres per person per day.
- For hospitals: 40 - 60 litres per person per
day.
In case of severe shortage, a daily ration of 4 to 5 litres may suffice very provisionally. Unless there is a shortage, it is better not to put any limit on consumption as the health status of the population is influenced by the quantity of water used.
It is not enough to supply 10 - 15 litres of water per person per day to a camp; people should actually be able to use this quantity. Therefore water should be reasonably accessible (in terms of distance and of waiting time at the water point), and the means to transport and store it should be available (if the supply is via taps, allow at least one tap per 200 - 250 people and arrange these taps in groups of 6 or 8 maximum). It is important to ensure that the population has enough containers (jerrycans, buckets, etc.) for the collection and storage of water; otherwise a distribution will be necessary.
If a sufficient quantity of water is not available near the site, moving the camp should be considered.
Quality
The water should be harmless to health and have an appearance and taste acceptable to the population.
Ideally the water supplied should meet the water quality standards of the WHO.
However, in practice it is often necessary to supply water which does not conform to these standards, simply because there is no alternative.
COMMENTS
- The quantity of water available has relatively more importance than its quality.
It is preferable to have a lot of water of average quality than little water of very good quality.
The lack of water to ensure a minimum of hygiene entails even more problems than does the consumption of relatively poor quality water.
- Water quality is important for drinking water but is of less importance for other uses (except where there is a risk of schistosomiasis). It is sometimes possible to supply water of two different qualities, but this generally entails more disadvantages than advantages.
Problems due to a lack of water
In extreme cases of lack of water, life is simply not possible (dehydration and death).
Less extreme shortages also have an impact on the health status of a population.
They provoke an increase in the incidence of numerous diseases due to a lack of hygiene. Good personal hygiene requires a sufficient quantity of water.
The diseases linked to a lack of water for personal hygiene, called "water-washed diseases", are:
DERMATOLOGICAL AND OPHTHALMIC DISEASES
Dermatological and ophthalmic diseases directly due to a lack of hygiene such as scabies, trachoma, conjunctivitis, etc.
DISEASES TRANSMITTED BY LICE
Lack of personal hygiene and washing of clothes encourages the proliferation of lice which, in addition to the problems caused by their presence (itching and scratching, skin sores), are disease vectors. They transmit louse-borne typhus and recurrent fever.
FAECO-ORALLY TRANSMITTED DISEASES
A lack of hygiene, particularly of hands and food, allows the transmission of these diseases from infected individuals (sick people or carriers) to uninfected individuals.
These so-called "dirty hands diseases" are: diarrhoeas and dysenteries (bacterial, protozoan, or viral), cholera, typhoid and paratyphoid fevers, hepatitis A, poliomyelitis and various helminth diseases.
Most of these diseases can spread epidemically in concentrated populations.
Problems due to poor chemical water quality
Water may contain numerous dissolved chemical substances which come either from pollution fertilizers insecticides, industrial waste, etc.), or from the composition of the rocks themselves (fluorine, arsenic, iron, etc.).
These substances may give the water such a bad taste that it is undrinkable (for example, if it contains too many salts or too much iron), but it may also, in the long term, cause severe health problems, for example:
- methaemoglobinaemia in babies, due to high nitrate levels,
- arsenic poisoning, etc.
The possible presence of toxic substances in water is something which must be borne in mind, but in the situations considered here, the microbiological quality of the water is a much more important and preoccupying problem.
Problems due to poor biological water quality
Water may contain numerous pathogenic organisms and thereby become a means of transmission for many diseases:
- Typhoid and paratyphoid fevers |
(bacteria) |
- Hepatitis A |
(virus) |
- Cholera |
(bacteria) |
- Poliomyelitis |
(virus) |
- Diarrhoeas (caused by Escherischia Coli, salmonellas and Yersinia Enterocolitica) |
(bacteria) |
- Viral gastroenteritis |
(virus) |
- Bacillary dysentery (caused by various species of shigellas) |
(bacteria) |
- Campylobacter dysentery |
(bacteria) |
- Amoebic dysentery |
(protozoa) |
- Giardia (lambliasis) |
(protozoa) |
- Balantidiasis |
(protozoa) |
- Helminthiasis caused by Ascaris and Trichuris |
(helminths) |
It should be noted that these so-called "water-borne" diseases form part of the group of "water-washed" diseases as well. They may also be transmitted by any of the faeco-oral routes: dirty hands, dirty food, dirty water, etc.
Besides these diseases, water is also involved in the transmission of "water-based" diseases (in other words, those diseases of which the causative agent passes part of its life-cycle in an aquatic plant or animal):
- The different schistosomiases or bilharzias: diseases caused by helminths (worms) which are usually contracted by contact with infested water (washing clothes, bathing, etc.), but sometimes also via the oral route.
- Dracunculiasis (Guinea worm), transmitted only by drinking infested water.
Lastly, water may also transmit:
- Leptospirosis: a bacterial disease which is contracted primarily by contact with water contaminated with the infected urine of various animals (principally the rat), but also by drinking such water.
All the infectious diseases transmitted by water -with the exception of Guinea worm- are linked to the pollution of water by the excreta of humans or other animals (from the sick or from healthy carriers).
Problems due to water-based insect vectors
One last category of water-related diseases is those with an insect vector which develops in or lives near to water, for example malaria, dengue and yellow fevers and onchocerciasis.
The solution to these problems lies among other things with the choice of site for a settlement and with environmental hygiene measures (drainage, elimination of stagnant water, covering reservoirs, etc.). They will not be considered in more detail here.
In terms of health
It is of primary importance that the population should be able to use a sufficient quantity of water to allow a minimum of hygiene, in addition to use for cooking. This means that the water should be available in sufficient quantity and easily accessible, and that people should have enough water containers.
In terms of water quality
The major danger is pollution of water by fl matter. Everything possible should be done to prevent such pollution. Nevertheless, it is preferable to have a lot of water of average quality than a little water of very good quality.
Figure
Different types of water
Potentially, three types of water may be available:
SURFACE WATERS: STREAMS, RIVERS, LAKES, PONDS, RESERVOIRS (DAMS)
- It is generally heavily polluted particularly during the rainy
season.
- Its quantity varies with the season.
- It generally needs
complex treatment before use. Nevertheless, certain catchment methods allow a
significant improvement of water quality: shallow wells dug close to river
banks, river bed filters, infiltration galleries.
GROUNDWATERS: WELLS, BOREHOLES, SPRINGS
- Deep groundwater (boreholes, deep wells, certain springs):
· Generally clear and of good bacteriological quality
(filtered by percolation
through rocks).
· Sometimes containing
substances rendering it undrinkable because of its taste or because of
toxicity.
· Not generally subject to much seasonal variation in quality
or quantity.
- Shallow groundwater (wells a few metres deep, certain springs, groundwater near water courses):
· The higher the water table, the lower the bacteriological
quality tends to be (water from less than 3 metres deep should be treated like
surface water).
· Subject to seasonal variation in quantity.
RAINWATER
- In non-industrialised regions, rainwater is relatively pure and may be consumed without treatment as long as it is collected with certain precautions, ie on a clean surface (tin roof, tent, plastic sheeting) and the first flow of water is rejected.
- Although rainwater rarely provides a regular supply, it may sometimes be a useful temporary or complementary supply (it may be a good alternative to heavily polluted surface water during the rainy season).
Warning !!!
- The exclusive consumption of rainwater without a complementary intake of essential minerals (such as iodine) causes problems in the long term.
- Rainwater dissolves the metal in which it is stored. Do not use containers or pipes made of copper, zinc or lead: clay, cement or plastic containers are suitable.
In practice there is rarely a choice between these different sources of water, particularly in emergency situations.
When settlement begins, surface water (the most polluted or the most easily polluted) is often the only supply available. It is therefore imperative to concentrate on the problem of water as top priority.
Sometimes, at first, supply by water tanker is the only solution. Other solutions should quickly be planned: drilling, digging wells, moving the camp, etc. (specialist advice will usually be needed).
Sometimes a piped supply from an urban area may be possible.
Priorities
What are the priorities in terms of water supply, when dealing with a concentrated population?
Before anything else:
- Find out where and how the people go to collect water and where they defecate.
Then:
- Designate defecation areas far away from water points.
-
Distribute water containers if necessary (very important).
- Take specific
steps to protect water points.
- Determine the amount of water
available.
- If necessary, set up a water rationing system.
Finally:
- If necessary, increase the output of the water points or look
for additional sources of supply.
- Create a reserve water stock.
-
Improve measures to protect water points.
- If possible, set up a system
whereby water is pumped into reservoirs before being distributed.
- Check
water quality if necessary.
- Possibly, install a treatment system.
WATER POINT PROTECTION MEASURES
All the protection measures aim at preventing the introduction of fl genes into the water (either directly, or indirectly by run-off or dirty soil falling into the water, etc.).
- Protection of water courses
Organize the use of the water course according to environmental health considerations. The point used for collecting water should be upstream of all other uses.
Note: surface water is always difficult to protect (there may be a village upstream). As soon as possible, use other sources (wells, springs, boreholes), or at least, pump the water so that people and animals do not have direct access to the water course.
- Well protection
Immediately (and this does not require any particular materials or skills):
· Employ a watchman to monitor access to the
well.
· Surround the well with a fence against animals. If it is used to
water animals, make a channel to take water to a trough situated outside the
protective fence.
· Forbid the use of personal water containers: one
rope with a single container should be provided for this use.
· Install
a winch or similar system so that the bucket and rope are not laid on the ground
and so that people do not lean over the well.
· Keep sources of
pollution such as latrines at least 30 metres away from the well and downhilI
from it if there is a slope (caution: in certain hard and fissured rocks, 30
metres is not enough).
As soon as possible:
· Make the improvements needed to prevent infiltration of
run-off (make the upper part watertight to at least 3 metres depth, install an
apron, a concrete slab on the head wall, and drainage of the surroundings,
etc.).
· Cover the well and install a handpump or a self-priming
motorpump (plan for maintenance and the supply of spare parts).
- Spring protection
Immediately:
· Install a system which prevents water from standing at
the spring (collect the running water with a split bamboo, for
instance).
· Erect a protective barrier around the spring (10 metres
above it).
· Dig a drainage channel 10 metres above the spring to avoid
it being polluted by run-off.
As soon as possible:
· Build a spring box.
Certain measures for the protection of water points can, and should, be taken during the very first days. Others require particular materials, equipment and skills, and should only be envisaged at a later stage, though as quickly as possible.
Do not wait to be able to solve the whole problem before starting work; every step taken is an improvement.
Note:
Fl pollution of water may occur at any stage between its origin and its consumption. For example, for water from a well there may be:
- pollution of the water table,
- pollution of the water
inside the well (from soil, run-off, etc.)
- pollution during transport (from
dirty containers, dirty fingers, etc.),
- pollution during storage in the
home (from insects, dust, people taking water with dirty recipients, etc.).
Consumption of clean water can only be achieved by action at all levels, with a global programme of water point protection, excrete control and health education which is a long term programme).
Pollution at the source or during collective transport is nevertheless more dangerous than pollution in the home, because it affects the whole population at once and consequently encourages large scale epidemics.
CONTAINERS FOR TRANSPORT AND STORAGE
If the displaced people have not been able to bring enough containers with them they cannot use the water which is provided for them.
Each family should have containers with a total capacity of 40 litres as a minimum.
If the people do not have enough containers, it is vital to distribute them as a top priority.
Containers with small openings (like jerrycans) with a cap are the most suitable because they are used by pouring the water and not by dipping into it (which risks contaminating it each time).
Cooking oil is often distributed in such cans, and they can be re-used.
Traditional clay containers may be suitable as long as they are covered to prevent contamination by dust and insects.
Is the water potable or not?
The only criteria really of importance to health are the presence or the absence of pathogenic organisms and of toxic concentrations of certain chemicals.
Unfortunately these two criteria cannot be assessed by simple tests.
For example, there is no direct relation between the appearance of a sample of water and its potability. (A cloudy sample may be safe, whereas a clear sample may be both chemically and biologically dangerous.)
In non-industrialised areas the presence of pathogenic organisms is an infinitely more frequent problem than the presence of chemical substances at toxic concentrations.
ln practice, which analysis should be done and when?
TURBIDITY (CLOUDY APPEARANCE)
The presence of suspended solids is always a problem (the water is unpleasant to drink, there is a sediment, etc.), even if it does not necessarily mean that the water is polluted. But it is particularly important to take the turbidity into account if the water needs treatment.
The measurement of turbidity may be done with special equipment (graduated plastic tubes), but generally simply looking through the water in a transparent container gives enough information.
CHEMICAL ANALYSIS
In emergency situations a blind eye is usually turned to the acceptability of the taste and smell of water.
However, a laboratory chemical analysis may be requested:
- if a long term water supply is being planned,
- if there
are particular reasons to suspect chemical pollution.
BIOLOGICAL ANALYSIS
In other words, how to tell if water contains pathogens.
- Principle
The pathogenic organisms which may be present in water are too numerous and too various to be identified individually in practice (bacteria, protozoa, helminths, etc.).
As their presence is always linked to fl pollution (except for Guinea worm), it is preferable to look for organisms which are "indicators" of this pollution.
The indicator organisms generally looked for are the fl coliforms, principally Escherichia cold (E. Coli).
These germs are always present in large numbers in the faeces of man and other warm blooded animals.
The presence of fl coliforms an water indicates the possible presence of pathogenic organisms.
The absence of fl coliforms in water indicates the probable absence of pathogens, but is no proof of this (certain pathogens are more resistant than fl coliforms).
The count of fl coliforms (or E. Coli) per 100 ml gives an indication of the degree of fl pollution.
Note:
Other bacteria very similar to fl coliforms live more or less everywhere in the environment. They also belong to the coliform group.
Coliform group = |
- Fl coliforms (principally E. Coli) |
(total coliforms) |
- Other coliforms |
In raw water (untreated), only the presence of fl coliforms is significant for health, because they are the only coliforms which prove fl contamination.
Although in certain cases total coliforms are identified, only fl coliforms are used as indicators in the field.
- Method of bacteriological analysis
The membrane filtration method is generally used. This consists of filtering the water through a membrane which retains bacteria.
The membrane is then incubated at 44ºC for 14 - 18 hours on a specific culture medium.
The count of those colonies which develop with a characteristic appearance gives the number of fl coliforms in the sample of water which was filtered.
Note
When incubating at 37 C all the coliforms develop, so the count is of total coliforms.
There are kits available for field analysis (for example the Del Agua/Oxfam kit or the Milliflex kit from Millipore), composed of portable filtration and incubation systems.
However, these kits are expensive and require good training in their operation and in the reading and interpretation of results.
- How to express the results of analyses?
· Number of coliforms/100 ml if it concerns total
coliforms.
· Number of fl coliforms/100 ml or sometimes number of E.
Coli/100 ml (the two may be interchanged, as in human faeces E. Coli represents
more than 90% of fl coliforms).
When to do a bacteriological analysis?
A bacteriological analysis is rarely necessary. It is generally much more important and useful to do a sanitary inspection (the origin of the water, protection of the water point, its siting in relation to defecation areas, protection of the water during storage and transport, etc.). Such an inspection will often make it possible to see that the water is polluted or has strong chances of being polluted at some time or other.
Analysis only gives an indication of pollution at the precise moment of sampling, and not of the potential risk of pollution.
Moreover, a sanitary inspection may be done by anyone, whereas bacteriological analysis needs equipment and proper training in its use and in the interpretation of results.
A bacteriological analysis should only be considered when:
· Deciding whether or not to treat surface water (see the
next section).
· Using properly protected groundwater which, despite
everything, is suspected of being the cause of a high incidence of diarrhoeal
disease, or of being the origin of an epidemic of diarrhoea, cholera or typhoid.
Caution: in no case is the detection of fl coliforms in water proof that the water is the origin of an epidemic. Detection of heavy pollution indicates that it may be the source of the epidemic, but is no proof of this. However, in this case, action must be taken anyway.
The analysis is done:
· Either by a competent local laboratory within 6 hours of
sampling (after this time the samples are no longer representative of the water
to be analysed).
· Or in the field by someone trained in the use of
field testing kits.
As long as the water is chlorinated and the free residual chlorine level is satisfactory (see brief Chlorination), bacteriological analysis is not necessary nor appropriate.
Storage and sedimentation
Storage is the simplest procedure to improve water quality (certain pathogens do not survive beyond several days), but it needs large reservoirs. Storage alone is not always a very effective procedure.
During storage there also occurs purification by sedimentation. Suspended material settles to the bottom of the reservoir with a proportion of the pathogens (mainly the largest: helminth eggs and protozoan cysts).
Sedimentation of turbid water is essential before filtration and disinfection.
If natural sedimentation is too slow, flocculation may be necessary (specialist help is needed for this). In practice, if water in a bottle is still muddy after an hour, then the natural sedimentation will not be enough.
Filtration
Passing water through a permeable bed eliminates a proportion of the pathogens by retaining them mechanically on the surface or within the filter.
Ceramic candle filters and certain sand filters (known as rapid sand filters) work on this principle.
SLOW SAND FILTRATION
Under certain conditions, in passing water through a bed of sand, particularly effective filtration is achieved by biological purification in addition to the mechanical action of the filter. For this to occur, the filtration must be relatively slow.
A deposit is formed at the surface and in the top few centimetres of sand, in which breeds a whole range of bacteria and microscopic plants, forming a skin (called the Schmutzdecke, biological membrane or bacterial film), which works both biologically and mechanically. It acts as a very fine filter which retains or kills most pathogenic organisms: it eliminates eggs, cysts, nearly all pathogenic bacteria and a proportion of viruses.
Slow sand filtration is the only procedure which achieves such an improvement of water quality in a single operation.
A slow sand filter can operate for weeks or even months without maintenance (which consists of the removing of a thin layer of sand when the filtration rate becomes too low).
In practice
At the collective scale, the construction of this type of filter needs the input of a specialist, and then the maintenance is relatively simple.
At a smaller scale, for example in a feeding centre, a small filter may be made with local materials.
Whatever the size of the filter, the operating principle remains the same.
Important
The bacterial layer is fragile and certain precautions should be taken to preserve it: never let it dry out, and never pass chlorinated water through it.
Disinfection with chlorine
Chlorine is a suitable disinfectant for water because it is very powerful without being toxic. It allows the destruction of all viral and bacterial pathogens in water.
Chlorine can also be used to disinfect surfaces in contact with water: the insides of wells, pumps, pipes, spring boxes, reservoirs, etc., (when putting into service, after repairs or after accidental pollution).
For this purpose it is used at much higher concentrations than for the disinfection of drinking water because the pollution may be much greater (see technical briefs Chlorine-generating products and Chlorination).
In the situations considered here, gas chlorination is not recommended because it can be dangerous and is not practical on a small scale. Chlorine-generating products are preferred: calcium hypochlorite, chloride of lime, sodium hypochlorite solution (see technical brief Chlorine-generating products).
All these chemicals release chlorine when they are dissolved in water.
Chlorine reacts immediately with all the oxidizable substances which may be present in the water (organic matter and certain mineral substances as well as pathogens and other organisms).
These substances consume chlorine. For the chlorination to be effective, sufficient chlorine must be added to meet this initial chlorine demand. This is confirmed by checking that an excess of unconsumed chlorine remains in the water (residual free chlorine: see technical brief Monitoring chlorination).
EFFECTIVENESS
At the doses normally used, chlorine destroys all pathogenic viruses and bacteria in water, but it is ineffective against:
- protozoan cysts and helminth eggs or larvae,
- pathogens
within suspended particles (as they are thus not in contact with the chlorine),
so it is advisable to filter water prior to chlorination, to remove eggs, cysts,
larvae and suspended particles.
PRACTICAL USE
Chlorination is a very suitable treatment method for emergency situations (e.g. typhoid or cholera epidemics), because it is very effective, but it is relatively tricky to set up and needs constant attention.
If water has to be treated, which method should be used?
The choice of treatment method will depend on the appearance of the water, the supposed degree of pollution, or that measured by bacteriological analysis, and the technical options. See the following table.
In an emergency, chlorination is often the best technique, but in the long term, slow sand filtration is generally the most appropriate solution. However, it is always better to use water which does not need treatment.
Table
Digging a well
Protecting a well
Protecting a
spring
Washing area
Ferrocement tank
Fabricating concrete
rings
Choosing a motorpump
Ceramic candle filters
Slow sand
filter
Chlorine-generating products
Monitoring chlorination
Water
sampling
Water storage kit: 2,000 l
Water storage kit: 15,000
l
Distribution tapstand kit
Motorpump kit
DIGGING A WELL
Method
The aim of this brief is not to look at all the types of wells there are, but to explain a technique which should be useful in the absence of other technical skills.
Numerous techniques exist for finding water. Good field observation, particularly of the vegetation at the end of the dry season, and above all, the advice of local well diggers will help to decide where and how to dig.
Construction
- Identify a suitable site (vegetation, etc).
- Mark out a
circle about 1.2m diameter.
- Dig to about 1m deep.
- Erect a tripod with
a pulley over the hole (the legs of the tripod must be firmly anchored).
-
Continue digging, taking out all the soil as the work proceeds, using a bucket
and the tripod.
- At regular intervals as the hole deepens, line the sides
with wire mesh and
plaster it with cement mortar.
- When the water table
is reached, lower porous or perforated concrete rings, using the tripod, and
continue to dig inside the rings: these will descend into the water as digging
proceeds. The water which accumulates in the rings should be taken out as the
work continues.
- Place a layer of gravel between the sides of the well and
the rings.
- The capacity of the well should be considered sufficient when
there is always water remaining at the bottom of the well after drawing water by
bucket over a period of 4 to 5 hours continuously.
- Place a layer of gravel
at the bottom of the well (see technical brief Protecting a well).
- Cement
the joint between the top edge of the highest ring and the cement-plastered
section of the well.
- Install a system to draw water from the well, and the
protection (see technical brief Protecting a well).
- Before use, the well
should be disinfected using chlorine solution (see technical brief Protecting a
well).
Key
1. Tripod
2. Pulley
3. Rope
4.
5.Sections of wire
mesh with cement coating
6.
7. Bucket
8. Bottom section of reinforced
cement lining (just above the water level)
9. First concrete ring
10.
Joint between reinforced cement lining and concrete rings
11. Gravel
Inputs
- 1 shovel, 1 pick, 1 miner's bar
- 3 beams (about 2 m long)
and 1 pulley
- 3 builder's buckets
- Mason's tools
- Rope (diem. over
10 mm), about 60 m
- Cement (about 1 bag per 3 m of well depth)
- Wire
mesh ("chicken mesh" type)
- Sand (0.15 m3 per 3 m of well depth)
-
Perforated or porous concrete rings: 3 or 4
- Material and tools for well
protection (see technical brief)
- Mechanical pumping system (if the flow of
water is too great to keep the well empty by bucket during the work).
Important
- Well digging should only be done at the end of the dry season
(except in an emergency), when the water table is at its lowest, to avoid the
nasty experience of finding the well dry after just a few months of use.
-
Hand-digging a well without supporting the sides should only be considered in
soils which are stable enough to be safe for the diggers.
- If other wells in
the area show the water table to be more than 30m deep, or if there are good
reasons to suspect the presence of a rocky formation between the surface and the
water level, then another technique (e.g. drilling) should be considered.
-
It is important to use local skills and knowledge when deciding where to site a
well and which technique to use. Skilled well diggers may often be found
locally.
- The technique described here (based broadly on the GRET technical
briefs) is one of the simplest. However, it is not suitable for all soil types
(e.g. sands).
- Take care when siting a well to avoid possible sources of
pollution (see technical brief Protecting a well).
PROTECTING A WELL
Method
A well should be protected as soon as it is dug. This protection consists of preventing anything from getting into the well, and preventing the infiltration of run-off and wastewater which could carry contaminating material. Lastly, protection strengthens the structure of the well.
What to do
1. Line the whole well with concrete rings (bought locally or fabricated - see technical brief Fabricating concrete rings); the lowest ring should be porous or perforated. The uppermost ring should extend above ground level. Pack gravel between the rings and the sides of the well.
2. Place a layer of gravel about 10 cm deep at the bottom of the well (in order to avoid the resuspension of settled particles).
3. Excavate the earth around the well head to a depth of about 30 cm, to a radius of about 2 m. Dispose of all the material removed and cast a concrete apron, surrounded by a drainage channel confined by a low wall about 5 cm high, at a radius of at least 1.5 m around the well head.
4. The slope of the apron (1%) should fall to a drainage channel leading to a soakaway pit, an irrigated garden or a cattle drinking trough (see corresponding briefs).
5. Install a pumping system (follow pump manufacturer's instructions).
6. Fix a cover (either removable or fitted with an inspection hole), on which to mount the pump body. (The pump makes work easier for users, but is also useful because it prevents potentially contaminated objects like buckets from falling into the well).
Key
I/ 1. Possible entry of pollution
2. The well
3. Water
surface
II/ 4. The well
5. Concrete rings
6. Concrete apron
7.
Drainage channel
8. Channel to soakaway pit
9. Soakaway pit
III/ 10.
Pump
11. Cover
12. Impermeable concrete rings
13. Anchoring collar on
concrete ring
14. Apron
15. Permeable concrete ring
16. Gravel layer
(about 10 cm)
Inputs
- Cement: about 4 bags of 50 kg
- Sand: about 400 kg
-
Gravel: about 800kg
- Reinforcing steel: about 20 m, or steel mesh, to
reinforce the apron (optional).
- Bricks or large stones for the base of the
apron: enough to fill underneath the apron.
- Concrete rings, inside diameter
about 1 m, height about 80 cm: allow 10 rings for 7 m of well depth.
- Porous
or perforated concrete rings: 1 or 2
- Cover which fits on the top ring
-
Handpump with fixtures and fittings
- Construction materials for the drainage
system (see technical brief Soakaway pit).
Important
- Respect safe minimum distances: no latrines closer than 30 m
from a well.
- Latrines should absolutely be downhill from the well.
-
Maintenance should be done carefully: the pump, the apron (repair possible
-
Before the first use, or after accidental pollution, disinfect the well with a
chlorine solution as described below. (For the preparation of 1% chlorine
solution, see technical brief Chlorine-generating products.)
- If it is
possible to empty the well: Empty the well, brush the sides above the water
level with a solution of 200 mg of chlorine per litre (20 ml of 1% solution/1),
leave for half an hour and let the well refill.
- If it is not possible to
empty the well:
1. Brush the walls above the water level with a solution of
200mg of chlorine per litre.
2. Determine the volume of water in the well
(vol = PI x r2 x h; PI = 3.14, r = radius of well, h = depth of water or height
of water column).
3. Add 10 litres of 1% chlorine solution (see technical
brief Chlorine-generating products) per m3 of water, mix and leave the well
dosed for 12 hours.
4. After this time, pump out the water until there
remains just a faint smell of chlorine.
PROTECTING A SPRING
Method
A spring should be captured and protected in such a way as to maximise the quantify and qualify of water supplied.
- If the spring serves few people, the spring box acts as a
storage reservoir before distribution.
- If the spring serves many people,
the spring box is connected to a larger reservoir
- If the spring box is used
for storage, its capacity should be at least equivalent to a 12 hours period
demand.
Construction
- Dig out and clean the area around the spring to uncover all
resurgences and so obtain the maximum yield.
- Calculate the quantities of
materials needed (concrete, stone, bricks etc), according to the size of the
spring box and the local means of construction.
- Construct the spring box
according to the plan. Its base should be on the impermeable layer (1).
-
Build the back wall (4) of stone without mortar, and fill the space between the
wall and the earth with gravel (3). Cover with a layer of compacted clay (10),
to prevent infiltration from the surface.
- Backfill the upper part with soil
and dig a drainage ditch about 10m above the spring box to divert run-off.
-
Erect a fence or hedge around the site at a radius of 10 m to keep out animals
which could damage or pollute the spring, and to limit erosion of the drainage
ditch.
- Fix an overflow pipe at the height of the top of the spring's
flow.
- Lay a surface of stone or concrete under the overflow and a drainage
channel to avoid erosion and mud around the spring box.
- Install the
delivery pipe connected to the distribution system about 10 cm above the bottom
of the spring box.
Key
1. Impermeable layer
2. Emergence of spring
3. Gravel
backfill
4. Stone wall with open joints
5. Drainage channel
6.
Desludging pipe
7. Delivery pipe to distribution system
8. Overflow
9.
Cover with lock
10. Layer of clay
11. Soil
12. Protective fence or
hedge
13. Run-off drainage ditch
Inputs
- Detailed plan of spring box
- 2 masons, 2 labourers
-
Mason's tools
- Construction materials, according to local availability,
quantities calculated from the size of the spring box
- Concrete (1: 2: 3
cement: sand: gravel)
- Calculate the volume of concrete needed and multiply
by 15 to obtain the volume of dry mix (The volume of a 50kg bag of cement is
0.033 m3)
Important
- The aim of protecting a spring is to increase its useful yield
and reliability, and to protect it from surface pollution
- It is important
at the outset to carry out a sanitary inspection so as to identify the risks of
pollution and to do yield tests to be sure that the supply can meet users'
needs.
- Never try to make the water rise above the highest point of
resurgence as this could produce a backpressure which would make the flow emerge
elsewhere. The water should be captured on the impermeable layer.
- Be
careful not to divert the spring in another direction or into another fissure
when digging around it. Terracing should start at the point where the water
comes out of the earth. Continue to dig working back up the water-bearing layer,
while ensuring that the water flows away.
- A good spring should have a
constant temperature. If this is not the case, check above the spring to see if
the water comes from a surface water source which runs underground. The yield of
a spring with such a surface source will rise immediately if it rains.
- It
may be considered that for a reliable spring:
the yield in the rainy
season
= 3 to 5 maximum
the yield in the dry season
- The distribution and overflow pipes should be fitted with a screen (e.g. metal mosquito netting) in order to avoid the passage of insects and/or large particles.
WASHING AREA
Method
As its name suggests, a washing area should provide a hygiene
facility for a population in an emergency situation, without creating
environmental health risks
(stagnant water etc).
It is built close to a water point and its design should be adapted to the habits of the population (particularly concerning the position generally used by women to wash clothes).
The washing area described here is about the simplest it is possible to be build. It can be made of local bricks and mortar or of stone masonry.
Construction
- Choose a space down the slope from the apron of the water point. Lay out the area using a string line. Its size will depend on the number of people likely to use it at one time.
- Excavate about 30 cm of soil from this area to create a slope of at least 1% along its length, with a "V" profile across its width (see section AA); spread a 5 cm layer of sand and gravel on the bottom and compact it well.
- Dig a channel to take water from the water point to the washing area. This channel should have a slope of at least 1% and should join the highest end of the washing area.
- Lay bricks on the washing area, using a string line and a spirit level, cementing the joints (be careful to keep to the same slope and the same cross-section).
- When the cement has set, plaster the surface with a strong cement mortar (1 part cement to 2 parts sand), and smooth it well.
- Powder the surface of the plaster with cement when it is still wet and smooth it again to waterproof the surface.
- Cover the slab with plastic sheeting or thick sacking which is regularly wetted, and let it cure for 5 to 6 days before using.
- Dispose of wastewater in a soakaway pit, an evapotranspiration area or an irrigated garden (see relevent technical briefs).
- Fence off the area to protect it from animals.
Key
1. Well head
2. Drainage channel
3. Washing slab (sloping
towards drainage channel to disposal)
4. Drainage channel
5. Drainage
towards disposal
6. Stones
Inputs
- Shovel and pick
- String line and tape measure
- Spirit
level
- Sand and gravel
- Cement (about 50 kg)
- Bricks or stones
-
Trowel, float, cement-mixing trough
- Plastic sheeting, jute sacking, leaves,
etc.
Important
In all cases the dimensions of the washing area should be adapted to the habits and the average height of its users. The model illustrated here is suitable for people used to washing clothes in a crouching position. If people prefer to wash clothes standing up, a raised washing slab (table height), or an emptyable, raised concrete washtub is better.
During the early days of a camp, it is possible to make washing areas using only plastic sheeting (of the sort used for temporary shelters). The ground surface must be carefully prepared, removing all sharp objects (stones, roots, etc).
Drainage channels may be dug and lined with a double thickness of plastic sheeting, following the above guidelines for the slope. The edges of the plastic should be anchored to the ground with stones covered with well compacted earth.
This technique only lasts a few days because:
1) the plastic sheeting gets damaged very quickly,
2) and it
will probably be stolen.
FERROCEMENT TANK
Method
The construction of a ferrocement water tank may be considered when planning to collect rainwater etc. Its watertightness and strength are directly related to the quality of materials used and the care taken in its construction.
A shape in ferrocement is created using a removable mould to which wire mesh is attached and to which a cement coating is applied.
It is equally possible to build a framework of reinforcing steel which avoids having to use a mould. The steel is thus embedded in the cement coating and reinforces the structure.
Technique using wooden stakes (for a tank of 1,500 l)
1. Drive stakes into the ground, leaving at least 1.5 m above ground level with centres spaced at 20 cm, to form a circle 1.2 m in diameter.
2. Wind three thicknessess of wire mesh around the circle of stakes. Stretch and flatten the layers of mesh well against each other and fix them to the stakes and to each other with fine wire.
3. Reinforce the structure by winding round it three turns of thick wire at the top, in the middle and at the bottom.
4. Push a length of pipe with a valve attached through the mesh near the bottom (for emptying), and another one several centimetres higher with a tap for the outlet. A third pipe for the overflow is fixed near the top of the tank.
5. Apply a 15 mm first coat of cement plaster to the outside. One person should be on the inside to retain the mortar with a float as it is applied. Leave it to harden for 12 to 24 hours, keeping it damp.
6. Pull out the stakes and cut off the wires which stick out.
7. Apply a coat of cement plaster to the inside so as to cover the mesh completely. Leave it to harden for 12 to 24 hours.
8. Apply finishing coat to the inside and the outside and smooth well.
9. Cover the bottom of the tank with wire mesh and curve it up at the corners where the walls meet the bottom. Plaster the base, forming a slope towards the emptying pipe.
Key
1. Wooden stakes
2. Wire mesh
3. Overflow pipe
4.
Tap
5. Emptying pipe
6. Galvanised steel wire, 2 - 2.5 mm dia.
7.
Exterior coat of cement mortar
8. Interior coat of cement mortar
Inputs
- 20 sharpened wooden stakes (50 x 50 x 1,750 mm)
- 25 m of
fine wire mesh (12 mm mesh, 1.5 mm wire)
- 2 - 3 bags of cement
- 500 kg
of building sand
- 3 x 30cm lengths of metal pipe, one fitted with a tap and
one with a valve
- 1 roll of fine wire (0.5 mm)
- 1 roll of thick wire (2
mm)
- Mason's tools
- 2 people for 3 days
- 1 sledgehammer
Important
- Preparation of cement mortar: 1 part cement to 2 or 3 parts
dean, sieved sand.
- Final thickness of tank walls: 30 to 40 mm.
- A metal
cross piece is welded on the pipes to anchor them in the mesh before
plastering.
- To make a cover on the tank it is possible to extend the mesh
with its shuttering or reinforcing steel framework. An inspection hole with a
cover should then be made at the top of the tank
- Otherwise, the tank should
be fitted with a cover to protect the stored water.
- Once the coats have
been applied it is important to cover the tank with damp jute sacking or plastic
sheeting for at least one week for good curing of the cement. This allows the
cement to develop its full strength and avoids the risk of cracks appearing.
FABRICATING CONCRETE RINGS
Method
Concrete rings are needed to line and protect hand-dug wells. They may have other uses, such as making a spring box, a rainwater collection tank etc.
Concrete rings for infiltration at the bottom of a well may be perforated during fabrication, or made of porous concrete. Porous concrete rings are preferred for use in decomposed rock, sand or gravel.
Concrete rings used for the main part of a well or for water storage should obviously not be porous or perforated.
- The internal diameter of the rings should be at least 0.8 m so
that a person can work inside the ring if necessary.
- The mould is of steel
plate, at least 3 mm thick, reinforced with angle steel. It is composed of two
parts: the internal and external rings. Each of these parts is made of three
sections which bolt together.
- The mould is generally 1m high (less if
necessary).
- The bottoms and tops of the rings are stepped so that they fit
together well. The groove may be formed using a template or a plastic tubing
against the internal face at the bottom of the mould, and against the external
face at the top when the mould is almost full of concrete.
- The mould
sections are removed about 24 hours after casting. The rings should be cured in
the shade for at least 1 week, during which they should be kept damp (wetted
jute sacking or plastic sheeting).
- For perforated rings, the moulds are
made with holes every 15 cm. Greased pegs are inserted when the concrete is
cast; they are withdrawn before the concrete sets completely.
- After each
use the mould sections should be scraped and brushed and the contact surfaces
coated with used engine oil or diesel to prevent concrete sticking to them.
Key
1. External mould, diameter 1.15 m
2. Internal mould,
diameter 1 m
3. Concrete ring
4. Bolts
5. Wooden or metal pegs (for
perforated rings)
6. Reinforcing angle steel
Inputs
- 2 workers
- Cement, sand and gravel (about 0.25 m3 of
concrete per ring)
- 1 ring mould
- 2 shovels, 2 buckets, 2 trowels
- 1
wire brush
- Used engine oil
- 1 spanner, 1 lump hammer
- Plastic
sheeting or jute sacking
Important
- Concrete mix for ordinary or perforated ring is 1: 2: 4
cement: sand: gravel. Compact the concrete well during casting to drive out air
bubbles.
- Concrete mix for porous rings is 1:1: 4 cement: sand: gravel. The
concrete should not be too wet. Instead of compacting, vibrate it by hitting the
mould with a wooden stick. Porous rings should cure for longer than ordinary
ones. They are more fragile and should be handled with care.
- When the rings
are produced in series for a programme of well protection, it is recommended to
use a sheltered area for curing and storing the rings.
- A tripod and pulley
should be used to lower the rings safely into the well.
CHOOSING A MOTORPUMP
Method
A motorpump is composed of a pumping mechanism and a driving mechanism (electric motor or combustion engine).
The choice of a motorpump depends on the type of water source and the work to be done.
The water source:
A study of the type of water source (river, lake, well, deep or shallow borehole) and its situation allows the choice of a surface pump or a submersible pump.
For a suction height of up to 7 metres, any type of surface pump may be used.(The pump body is at the surface: it sucks and delivers.)
For greater lifting heights (deep wells and boreholes), a submersible pump is suitable (an electric pump, completely immersed: delivery only).
The work to be done:
The following information is needed when specifying a pump for a specific use:
- The discharge, Q. expressed in litres per second or cubic metres per hour, or the demand in cubic metres per day.
- The vertical distance in metres between the lowest water level and the highest level to which water must be pumped (suction height and delivery height), or the total geometric head.
- The variation of the water level in metres.
- Physical information on the site: depth of water, diameter and depth of well or borehole, sketch with dimensions of river bank, lake or channel.
- The height of the site above sea level.
- The energy source for pumping: human, animal, wind, electric motor, combustion engine, solar, etc.
- The average weight which can be easily transported and handled on site.
Key
1. Suction head
2. Delivery head
3. Level of pump
axis
4. Lowest water level
5. Highest water level
6. Internal diameter
of suction pipe
7. Internal diameter of delivery pipe
8. Length of suction
pipe
9. Length of delivery pipe
10. Atmospheric pressure
11. Motorpump
unit
12. Non-retum valve
13. Suction strainer with foot valve
14.
Storage reservoir
Inputs
- Measuring equipment (rope, tape measure, level, etc)
-
Sketch and description of site
Important
The following factors must also be considered:
- The possible presence of large quantities of sand in the water
which may damage the moving parts of the pump.
- The presence of salty or
brackish water which could produce rapid pump corrosion.
- The ease of
maintenance and robustness of the pump, the availability of fuel (what type of
fuel) or electricity, the availability of tools, spare parts and maintenance
skills.
- The pumping schedule: a few hours per day, or 24 hours per
day?
- Calculation and comparison of the costs of different options.
Note:
The suction ability of a surface pump is limited to 7m head at sea level, whatever its power. It diminishes as the altitude increases (see table opposite).
On the other hand, its discharge capacity is directly related to its power.
The discharge of a pump can be regulated by means of a valve at the discharge outlet.
CERAMIC CANDLE FILTERS
Method
Ceramic candle filters can remove practically an bacteria, some viruses and all suspended material from water.
Important: this technique is not effective for dissolved substances (salts, chemical pollutants, etc.).
Water is passed through microporous ceramic walls with a pore diameter of about0.45
Siphon filter
- Place the water to be filtered in a container, immerse the candle, place another container underneath and let the filtered water siphon through, drop by drop (the siphon is primed automatically).
Gravity filter
- The same principle as above, but one container stacks on top of the other.
This method produces a greater flow than the siphon as it uses several candles (provided they are not clogged).
Pump filter (also called "Katadyn")
Here, the water is forced through the filter under pressure using a small integral handpump, thus improving the flow.
- Put the end of the plastic pipe into the water to be filtered,
and pump.
- Inside the candle there is activated carbon which adsorbs
dissolved substances and takes away any possible taste from the water.
Tap filter
- In this unit the candle is mounted inside a cylinder. (It is
like the siphon filter candle, but filled with activated carbon.) A plastic hose
is connected to the tap.
- When the tap is turned on, water fills the
transparent filter body, passes through the candle and comes out of the
spout.
- Important: this filter can only be used where there is enough
pressure in the piped water supply.
Key
1. Water to be filtered
2. Ceramic candles
3. Siphon
tube
4. Collecting filtered water
5. Container of water to be
filtered
6. Ceramic candle fastening and rubber washer
7. Tap
8.
Cover
9. Transparent filter body
10. Outlet for filtered water
11.
Handpump
12. Fastening collars
13. Flexible tube (raw water)
14.
Strainer (to prefilter raw water)
15. Universal tap fitting
Inputs
Siphon filter
- Ceramic candle with flexible siphon tube
Gravity filter
- 2 containers (metal or plastic)
- Ceramic candles (2 or 4)
with rubber washers and wing nuts
- Tap
Katadyn
· Kit containing:
- 1 pump filter with flexible tube attached
- 1 brush to
clean ceramic candle
- 1 gauge to measure thickness of candle
Tap filter
- Filter body with flexible hose and universal rubber tap
adaptor
- Ceramic candle (delivered together)
Important
- Siphon filter: ensure that the flexible tube is firmly attached to the ceramic candle so that no water is siphoned directly without filtration.
- Gravity filter: assemble the candles correctly with their rubber washers to ensure that no water passes without filtration.
- Katadyn filter: change the candle as soon as the measuring gauge passes freely around it (see maker's instructions).
- Teams in the field should always drink filtered water because they can never be sure of the quality of local water supplies.
- Never let the candles come into contact with boiling water as there is a risk of cracks forming.
- Maintenance of ceramic candles: when the flow becomes too weak, brush the candles (e.g. with a toothbrush) under clean running water, rinse and reassemble. The candles are fragile, handle them with care.
- The tap filter is ideal for washing hands etc. in an operating theatre, if the hospital has running water. Be careful not to loose the little rubber rings on the tap adaptor.
SLOW SAND FILTER
Method
Slow sand filtration a highly effective microbiological purification of water in addition to mechanical purificationby the sand.
This microbiological treatment is due to the action of a biological layer (called the Schmutzdecke), which develops at thesurface of the filter. This layer actively retains and destroys helminth eggs, bacteria and some viruses.
Construction
1. Paint the insides of two 200 l drums. Fix an inlet pipe about 5 cm from the bottom of one drum which which be used for the prefilter (as shown in the sketch).
2. Place a layer of large stones on the bottom of this drum (4), making sure there is a plug-hole at the bottom. If there is not, then make one.
3. Place a perforated plate (e.g. the top cut off the drum) on top of the stones (2), to act as a support for a layer of coarse sand.
4. Place a 30 cm layer of coarse washed sand (1 - 2 mm dia) on top of the metal plate.
5. Fix a pipe connecting the two drums near the top, to take water from the prefilter to the filter.
6. Make sure the second drum has a plug-hole in the bottom. Make a hole about 5 cm from the bottom and insert a perforated pipe (9). A length of PVC pipe with many slots cut with a saw is suitable.
7. Bury the perforated pipe in a bed of gravel (8), which covers it by at least 5 cm.
8.Then add a layer of at least 70 cm of washed, sieved, fine sand (7). The ideal diameter is 0.2 to 0.5 mm, or in any case, less than 1.5 mm. The Schmutzdecke will develop at the surface of this sand.
9. Place a flat stone (10) where the water flows onto the filter so it will not to disturb the Schmutzdecke by its turbulence.
10. Insert and fix the pipework (outlet and overflow). Important: the outlet pipe must rise above the level of the top of the sand, so that the filter surface is always under water, even if the water supply is cut.
Key
1. Raw water inlet valve
2. Perforated plate (holes about 2
mm die every 5cm)
3. Coarse sand (1-2 mm dia)
4. Large stone (e.g.
cobbles)
5. Plug-holes with plugs
6. Prefilter overflow (towards
filter)
7. Fine sand (0.2-0.5 mm dia)
8. Gravel
9. Perforated pipe (for
collecting filtered water)
10. Flat stone
11. Outlet valve
12. Outlet
pipe to distribution
13. Overflow
A. Minimum water level in filter
B. Maximum water level in
filter
Inputs
- Two 200 l drums
- Metal saw, hammer, cold chisel, tape
measure
- Drill and bits
- Round and half-round files
- Pipe (PVC or
galvanised), 1/2" or 3/4"
- Pipe threader (for galvanised pipe) or solvent
and PVC glue
- Teflon tape or mastic and tow (for making joints)
- Elbows
and nipples (for fixing pipes)
- Anticorrosion and household paints
-
Paintbrush and thinners
- Cobbles (stones)
- Coarse sand (about 1 mm dia):
about 0.12 m3
- Fine sand (0.2 - 0.5mm dia): about 0.3 m3
- Gravel: about
0.03 m3 important
- The filter sand should be of uniform size. Sieve it, using mosquito netting for instance.
- Before the first use, fill the prefilter and the filter with a solution of 100 mg/l chlorine (10 ml of 1% solution per litre); leave it for 12 hours and empty it through the plug-holes. Never chlorinate after this: it would destroy the biological layer. Cover the drums to prevent the growth of algae.
- It is vital that the Schmutzdecke at the surface of the sand
is always covered with water; again, make sure that the outlet pipe rises above
the level of the
Schmutzdecke.
- Flow setting: close the outlet valve. Open the inlet valve (not too much, to avoid putting the prefilter sand into suspension); when the filter is full, open the outlet valve so as to have an outflow of about 1 l/min.
- The Schmutzdecke is only effective after about 2 weeks, so for the first 2 weeks of service the water is not safe.
- Such a filter can treat 1,000 to 1,400 l/24 h. If the needs are greater, several filters may be built in parallel (this also avoids having to cut the supply during maintenance).
- Maintenance: when the yield drops significantly, cut the inflow and undo the plugs of the two drums. Let the water empty completely from the prefilter. Let the water level in the filter fall to 15 - 20cm below the filter surface; rake the top 1 - 2 cm of sand from the Schmutzdecke. Replace the plugs and put back into service. After this has been done several times, remove about 10 cm of sand and put it to one side. Place a layer of clean sand and then replace the 10 cm, to bring the total thickness of fine sand back to 70 cm.
- If the water is not very turbid (<30 NTU), the prefilter will not be necessary.
Chlorine-generating products
CHLORINATION
Method
Chlorination is one of the best methods of treating drinking water (relatively simple, effective and easy to measure). In spite of this relative simplicity, it should not be forgotten that in an emergency situation it is always preferable to use a groundwater source which can be protected and monitored in terms of environmental hygiene (see technical brief Protecting a well).
Chlorination demands staff trained in the technique and in its monitoring as well as good logistics (supply of chlorine product storage, etc.).
In practice
Only the chlorination of a known volume of water in a reservoir is discussed here.
- The principle is to add enough chlorine^generating product to destroy all the organic matter contained in the water and to leave a small fraction of chlorine available for dealing with any possible reintroduction of organic matter. To determine how much chlorine product to add, the chlorine demand is measured.
1. Prepare a 1% chlorine solution (see technical brief Chlorine-generating products).
2. Take 3 or 4 non-metallic containers of known volume (e.g. 20 l buckets).
3. Fill the containers with some of the water to be treated.
4. Add to each bucket a progressively greater dose of 1% solution with a syringe:
1st container: 1 ml
2nd container:1.5 ml
3rd container: 2
ml
4th container: 2.5 ml
5. Wait 30 minutes (essential: this is the minimum contact time for the chlorine to react).
6. Measure the free chlorine residual in each bucket (see technical brief Monitoring chlorination).
7. Choose the sample which shows a free residual chlorine level between 0.2 and 0.5mg/l.
8. Extrapolate the 1% dose to the volume of water to be treated.
9. Pour the solution into the reservoir, mix well (during filling) and wait 30 minutes before distributing.
Example
Chlorination of water in a 2,000 l reservoir
- Follow steps 1 - 5 above.
- The free residual chlorine
levels of the water in the buckets, measured half an hour after adding 1, 1.5, 2
and 2.5 ml of 1% chlorine solution respectively are as follows:
1:0 mg/l
2:0.1 mg/l
3:0.4 mg/l
4:1 mg/l
- The dosing rate chosen therefore will be that for bucket number 3 (result between 0.2 and 0.5 mg/l
- If it needs 2 ml of 1% solution to chlorinate 20 l of water at the correct dosage, then it needs 100 times as much to chlorinate 2,0001, e.g.: 100 x 2 ml = 200 ml of 1% chlorine solution
Inputs
- 1% solution
- Several containers of the same known volume
(buckets, jerrycans, etc.).
- 5 ml syringe
- Measuring equipment
(comparator and DPD1 tablets)
- Watch to measure the 30 minutes
The MSF "chlorination" kit, available through MSF logistics, contains all the material needed for chlorination and dosing.
Important
- Never chlorinate turbid water because the suspended particles can protect micro-organisms. The measurement of free residual chlorine may indicate a satisfactory result (between 0,2 and 0,5 mg/l), but there is no way of knowing if the chlorine actuary comes into contact with all the pathogens. Water to be chlorinated must contain as little visible suspended material as possible. If it is turbid, a pretreatment such as sedimentation and/or filtration should be done before chlorination.
- Chlorination is effective against practically all pathogenic micro-organisms in water. The only way to be sure of this effectiveness is to dose the free residual chlorine. Important: even if the dosage rate is correctly determined, the chlorine demand may vary over time with unexpected changes in the amount of organic material in the water. It is thus important to measure the free residual chlorine frequency in order to be able to adjust the dosage rate to the situation.
- Metal consumes chlorine, so never prepare strong solutions in metal containers (unless they are enamelled or painted).
- Concentrated chlorine products should be kept in a dry, shaded place, and guarded. (Chlorine is dangerous, particularly for children). When in contact with air, chlorine produces a corrosive and toxic gas heavier than air. The ventilation of chlorine stores should therefore be by means of vents at the bottom of the walls.
- The doses of 1% chlorine solution given here for the example of calculating chlorine demand are only an indication. It may be that the chlorine demand of water to be treated in the field is very different from this example.
- The taste of chlorine in water is no proof of the presence of free residual chlorine (it could be combined residual chlorine).
Monitoring chlorination
Method
The simplest and surest way of motoring effectiveness of chlorination of drinking water is to measure Free Residual Chlorine (FRC).
The presence of FRC in water (after a contact time of 30 mins) proves that enough chlorine has been added to oxidise all organic matter in the water, plus leaving an excess of chlorine available to deal with possible recontamination (in the distribution system, during handling etc.).
The objective of chlorination (see technical brief Chlorination) is thus to add enough chlorine to leave between 0.2 and 0.5 mg/l of FRC after the contact time.
The measurement is most easily done using a "Pooltester"
1.Rinse the Pooltester 3 times with the water to be
tested.
2.Fill the 3 compartments completely with water.
3.Put 1 phenol
red tablet in the left hand compartment (measurement of pH).
4.Put 1 DPD1
tablet in the right hand compartment (measurement of Free Residual
Chlorine).
5.Replace the cover.
6.Shake until the tablets are completely
dissolved (about 20 sees).
7.Read the results in the light, comparing the
colours in the outside compartments (samples) with those in the central
compartment (reference).
Key
1. Cover
2. Central compartment
3. pH compartment (phenol
red tablet)
4. FRC compartment (DPD1 tablet)
5. pH reading scale
6. pH
reference scale
7. FRC reading scale
8. FRC reference scale
Inputs
(for 1 measurement)
-1 pooltester with cover
-1 phenol red tablet
-1 DPD1
tablet ("DPD1" is marked in green on the packet)
- Water to be tested
Important
- Never touch the tablets with the fingers: this could affect
the results.
- The printing "DPD1" must be in GREEN on the packaging. There
are other DPD1 tablets with the printing in black. They should not be used in
this pooltester.
- Read the results within 60 seconds of the tablets
dissolving to be sure of a reliable measurement.
- Read the results in good
light (daylight is best).
- The pH need not be measured every time. It is
used for determining the amount of chlorine product to add to the water.
-
Comments on the pH of water:
pH = 7: neutral
pH < 7: acidic
pH > 7: alkaline (or
= basic)
· Important: chlorination is less effective if the pH is above 8. In this case, the FRC level after the contact time should be double the normal (between 0.4 and 1.0 mg/l instead of 0.2 - 0.5 mg/l) for chlorination to be considered effective.
· Important: if chlorine is overdosed, the measurement of FRC may give a false negative result.
WATER SAMPLING
Method
Important: the sampling technique differs according to whether it is for bacteriological or chemical analysis.
The results are in the section "Assessment of water quality".
Chemical analysis
- Collect at least 2 x 11 in plastic bottles (e.g. mineral water bottles), which must be clean and airtight.
- Rinse the bottles 3 times with the water to be analysed, fill them right to the top, label them and send them to the analytical laboratory.
Bacteriological analysis
- Collect at least 100ml in a sterile bottle.
- To sterilize
bottles, place the cap loosely on each one so that steam can circulate
inside.
- Wrap each bottle in tissue paper, newspaper or wrapping paper.
-
Sterilize in an autoclave for 15 minutes at 121°C (a small autoclave like
the "Prestoclav" is quite suitable).
- If there is no autoclave, the bottles
may be sterilized by boiling: place each bottle and cap in the water and let it
boil for 20 minutes.
- After 20 mins boiling, take out of the water, and let
it cool protecting the opening with flamed aluminium foil or a sterilized
compress.
- Use as soon as possible.
- For the bacteriological analysis of
water that has been chlorinated, add 0.15ml of 1% sodium thiosulphate solution
per 100ml of sample to each bottle before sterilizing, in order to neutralize
the chlorine which would otherwise affect the results.
Key
(1 - 8: water sampling from a tap for bacteriological analysis)
1. Clean the tap (alcohol or soap)
2. Let the tap run fully
for about 30 seconds
3. Flame it with a pad soaked in alcohol
4. Let it
run fully again for 30 seconds
5. Take off the cap and its protection from
the bottle
6. Take the sample
7. Replace the cap
8. Label the sample
and record it in a notebook
9. Sampling from a water course
10. Sampling
from a well
Inputs
Chemical
- Glass or plastic bottles, 1 or 1.51: 2 per sample
- Marker
pen for labelling
- Thermometer
Bacteriological
- 2 sterile 100 ml bottles
- String and weighting stone (for
sampling from a well or other inaccessible place.
- Cloth
- Alcohol and
tighter
- Cotton wool and forceps (e.g. hair tweezers)
- Thermometer
-
Cool box
Important
- The 8 steps described here for sampling from a tap are not necessary for chemical analysis, but are absolutely necessary for bacteriological analysis. They are the only way to be sure that the results of the analysis reflect the quality of the water and are not affected by possible contamination on the tap, during handling.
- Always work with clean hands (washed with soap). Any contamination by dirty hands will distort the results.
- Never touch the inside of the sterilized bottle or its cap. When sampling, hold the cap by the outside; never put it down unless it is upside down. It is better, for security and reliability, to double each sample.
- Mark the following on each sample (and keep a copy):
- an identification number, the place and the type of water
sampled, as accurately as possible;
- the date and time of sampling and
dispatch;
- the substance(s) or organism(s) to be identified; techniques
-
treatment, if any, of the water (product and dose);
- water temperature at
the time of sampling (if possible).
- Certain chemical tests require special sampling. Enquire about
these.
- For bacteriological analysis, it is often simpler to use field
testing kits (e.g. De lAgua or Millipore); in fact, samples should reach the
analytical laboratory within an hour of sampling if they are kept at ambient
temperature, or within 6 hours if they are kept at between 4 and 6°C (but
not frozen).
2,000 litres water storage kit
Method
This kit is for the supply of water to a health structure (dispensary, small hospital, feeding centre, etc.).
Once the base has been prepared (a raised earth platform), the bladder tank can be in operation in a few minutes.
Installation
- Choose the site for installing the tank, close to the centre to be served.
Important: make sure that the site is accessible at all times for filling the tank (e.g. by lorry tanker).
- Prepare a flat platform, about 15 m high so that the water may be distributed by gravity. The higher the platform the better the distribution.
- The surface of the platform should be cleared of all objects (stones, sticks, etc.) which could puncture the tank. If possible, cover the surface with a layer of sand.
Important: the area of the platform should be larger than that of the tank (3 m x 1.7 m). Note also that this platform should be strong enough to support 390 kg/m3.
The platform may be made of compacted earth, or oil drums filled with stones or earth with earth packed between them, or a flat roof may be used, etc.
- Spread the groundsheet on the platform.
- Lay the tank out
on the groundsheet.
- Tighten the outlet valve; it is not completely screwed
on by the manufacturer.
- Attach the pipe to the outlet.
- Organise the
distribution system in the health centre (or right next to it), using either the
1/4 turn valve supplied with the Wt. or a distribution tapstand (there are 2
stands, each with 6 taps in the MSF "Distribution tapstand" kit).
- Install a
drainage system around the platform and around the distribution point to avoid
rapid deterioration of the site.
Key
1. Reservoir (bladder tank)
2. Filling opening with cap
3.
Outlet valve
4. One half of a DN50 connection, Guillemin system
5.
Groundsheet
6. 6m of 2" reinforced hose, DN50, suitable for carrying drinking
water
7. Harness for transport by car or lorry
8. Serflex collars for grip
and watertightness
9. Spanner for loosening and tightening the hose
connections
10. 1/4 turn distribution valve
11. Corner protection plate
Inputs
- 2 people per kit for installation
- Means of firing:
motorpump, lorry tanker, etc.
- Distribution points, e.g. MSF tapstand kits
with 6 taps
Important
- Site the distribution point as far away as possible from the
tank.
- Do not lose the connection spanner: if it does get lost, there are
some in the
MSF water supply tool kit (white bucket).
- After use, it is
essential to dean and dry the inside of the tank before repacking, to extend its
life:
· open the valve and the firing cap,
· unscrew the
plastic corner reinforcing plates on one side of the tank, push a piece of
string or wire,
· between the plates and retighten them,
· hang
up the tank by the string or wire,
· slip a piece of wood (for example)
between the filling opening and the tank bottom to keep the inner surfaces apart
and let air circulate inside.
- Do not fold up the tank until the inside is completely dry (2
- 3 days at least).
- To repair the tank, use the repair kit supplied and
follow the instructions carefully.
15,000 litres water storage kit
Method
This kit is designed to supply water in a camp. Once the base has been prepared (a raised earth platform), the bladder tank can be operational in a few minutes.
Installation
- Choose the site for installing the tank, ensuring that it is accessible at all times for filling the tank (e.g. by lorry tanker).
- Prepare a flat platform, about 1.5 m high so that the water may be distributed by gravity. The higher the platform the better the distribution.
- The surface of the platform should be cleared of all objects (stones, sticks, etc.) which could puncture the tank. If possible, cover the surface with a layer of sand.
Important: the area of the platform should be larger than that of the tank (6.4 m x 3.2 m). Note also that this platform should be strong enough to support 730 kg/m3.
The platform may be made of compacted earth, or oil drums filled with stones or earth with earth packed between them, or a flat roof may be used, etc.
- Spread the groundsheet on the platform.
- Lay the tank out
on the groundsheet.
- Tighten the outlet valves; they are not completely
screwed on by the manufacturer.
- Attach one of the three lengths of pipe to
one of the outlets; fit the tee and the two other lengths of pipe to the other
outlet.
- Organise the distribution points, using either the 1/4 turn valves
supplied with the kit, or distribution tapstands (there are 2 stands, each with
6 taps in the MSF "Distribution tapstand" kit).
- Install a drainage system
around the platform and around the distribution point(s) to avoid rapid
deterioration of site.
Key
1. Reservoir (bladder tank)
2. Filling opening with cap
3.
Outlet valves (2)
4. Half of a DN50 connection, Guillemin system
5.
Groundsheet
6. 6 m of 2" reinforced hoses, DN50 (3), suitable for use with
drinking water
7. Serflex collars for grip and watertightness
8. Spanner
for loosening and tightening the hose connections
9. 1/4 turn distribution
valves (3)
10. 2" tee connection, DN50
11. 2 shovels, 2 picks
12.
Handles for shovels and picks
13. Roll of rope
Inputs
- 2 persons per kit for installation
- Unpack the shovels and
picks first of ale to prepare the platform. If mechanical equipment (e.g. a
bulldozer) can be used it is much quicker and easier.
- Means of filling:
motorpump, lorry tanker, etc.
- Distribution points, e.g. MSF tapstand kits
with 6 taps.
Important
- Site the distribution point as far away as possible from the tank Use the rope in the kit for fencing.
- Do not lose the connection spanner: if it does get lost, there are some in the MSF water supply tool kit (white bucket). When rationing water, the gate valves on the outlets may be closed and the knobs taken off. Be careful not to lose the knobs.
- After use, it is essential to clean and dry the inside of the tank before repacking, to extend its life:
· open the valve and the filling cap,
· unscrew the
plastic corner reinforcing plates on one side of the tank, push a piece of
string or wire between the plates and retighten them,
· hang up the tank
by the string or wire,
· slip a piece of wood (for example) between the
filling opening and the tank bottom to keep the inner surfaces apart, and let
air circulate inside.
- Do not fold up the tank until the inside is completely dry
(2-3 days at least).
- To repair the tank, use the repair kit supplied and
follow the instructions carefully.
Distribution tapstand kit
Method
The distribution tapstands are pre-assembled and quick to install, allowing rapid provision of water distribution points in emergency situations. The kit is composed of 2 tapstands, each with 6 self-closing taps. The tapstands are designed to be used with the water storage kits (or any other system fitted with DN50 connections).
Installation
- Unpack the two tapstands from the box and identify the various parts (frame, taps, nuts and bolts, etc.).
- Unfold the legs and assemble the frame with the 4 steel braces. Use the bolts and the Nylostop M10 nuts with the 10mm spanner in the kit.
- Secure the reducing tee with its vertical pipe for incoming water. Use Teflon tape (PTFE) on the thread before screwing on the elbow to ensure a watertight joint. Tighten the nuts fixing the pipe to the frame with the 13mm spanner supplied.
- Wind teflon tape onto the threaded ends of the pipes on the
tapstand.
- Attach the 6 Taflo taps, tighten them well (use a wrench supplied
in the water supply tool kit). Make sure all 6 taps are vertically aligned.
-
Choose the site to install the tapstand(s): the site should be well drained (for
rainwater and wastewater) and accessible for users.
- Position the
tapstand(s). Fix them to the ground using the short stakes in hard earth and the
long stakes in soft earth.
- Connect &e tapstand(s) to the tank using 2"
Heliflex pipe. Tighten the DN50 connections well using the spanner. Bury the
pipe if possible.
- To connect 2 tapstands in series, undo the stopper from
the reducing tee on the first tapstand and attach one end of a 2" Heliflex pipe.
Connect the other end to the reducing tee of the second tapstand.
- Pave the
area with stones and dig a drain for wastewater.
Key
1. Frame and bolted legs (angle steel)
2. Galvanised steel
pipe, 3/4'
3. 1 tee, 2 crosses, 1 elbow for connections
4. 6 Taflo
(Talbot) taps
5. Steel braces
6. 4 short stakes or 4 long stakes for
anchorage
7. 2" to 3/4" reducing tee for connecting the tapstand
8.
Stopper and chain, DN50 connection fitting
9. 15 m3 or 2 m3 bladder
tank
10. 2" outlet valve and tee
11. 2" Heliflex pipe
12. Fence (posts
and ropes)
13. Paved and drained area
14. Distribution tapstands
15.
Drain for wastewater
Inputs
- 2 people for assembly and installation
- Bladder tank for
supply
- 2" Heliflex pipe
- 1 pipe wrench
- 1 connection spanner
-1
large hammer or mallet for driving in the stakes
- Enough stones to complete
the drainage works
Important
- It is important to arrange the area around the taptstands well (access, drainage), to avoid mud and stagnant water.
- If several tapstands are to be installed at the same place, separate them enough to avoid pushing and shoving at busy times.
- The 15 m3 tank has 2 outlet valves, so it is possible to install a tapstand at each end to have two distinct distribution points.
- The Taflo self-closing taps are designed to work at very low pressures. A flow of about 10 l per min at each tap may be obtained with a fall of between 1 and 1.5 m between the tank and the taps. In any case this difference in height is recommended as a minimum.
- To have a good flow to all taps, do not place more than 2
tapstands in series.
- Check from time to time that the taps close properly.
Solid particles in the water or objects inserted by users may obstruct or
prevent closure.
Motorpump kit
Method
The diesel and petrol motorpump kits are packages designed for providing water in emergency situations. They permit water to be pumped from a water source (well, river, etc.), to a water tanker or a reservoir.
Installation
- Choose the pumping site: it should be easily accessible in all seasons and not liable to flooding, particularly where the pump is to be used for filling water tankers.
- Prepare the site so as to install the pump as close to the source as possible, to reduce the suction head.
- Lay the suction pipe on a rising slope (avoid dips), making sure the connections are well tightened. An air leak through the connections could mean losing the priming of the pump. The total suction head should be limited to 7 m.
- Fit the strainer and footvalve at the lower end of the suction pipe. Attach a float so as to hold the strainer 30 cm below the water surface (to avoid creating eddies and sucking air) and at least 50 cm above the bottom (to avoid sucking in mud).
- Lay the delivery pipe(s) up the slope towards the reservoir or tanker filling point.
- Fill the pump engine with oil. New motor pumps are delivered without engine oil in the engine.
- Check the general condition of the motorpump. Fill up with fuel. The air filter of the diesel motorpump is an oil bath type; fill it according to the instructions provided
- Fill the pump body with water. The motorpumps in the kits are self-priming so there is no need to fill the suction pipe to encourage priming.
- Start up the pump, following the user's manual
- Record pumping times in the maintenance book to keep a count of pumping hours and plan the engine maintenance schedule.
Key
1. Float
2. Strainer with non-return foot valve (to exclude
large impurities and keep the suction pipe full of water when pumping
stops)
3. Water source (river, well, etc.)
4. Heliflex suction pipe, 2"
(do not use ordinary flexible hose for the suction pipe)
5. Petrol or diesel
motorpump
6. Non-return valve (protects against water hammer from
backflow)
7. Heliflex delivery pipe, 2"
· Hs: suction head / Hd: delivery head
Inputs
- 2 people to install the kit
- 1 operator for operation and
maintenance
- Shovels and picks for preparing the site
- Fuel (petrol or
diesel) and motor oil
- Reservoirs or water tankers for filling
Important
- The petrol motorpump kit is light, and suitable for mobile use for limited pumping times (e.g. on a pickup or a water tanker). Maximum delivery: 30m3/hour.
Total pumping head (suction + delivery): 28 m. Fuel capacity:2.5 l giving 3 hours running.The motorpump is mounted on a frame and weighs 28 kg. The 4-stroke engine is fitted with a low-oil security system.
- The diesel motorpump kit is suitable for fixed installations and for long pumping hours. The maximum delivery is 40 m3/hour. The total pumping head is 28 m.
The fuel capacity is 4.3 l which gives 4 hours running. The motorpump is mounted on a trolley and weighs 58 kg.
Warning: the diesel engine does not have an oil level security system; check the oil level every day before starting up.
- Every motorpump kit is supplied with 4 lengths of 2" Heliflex pipe, 1 strainer, 1 non-return valve, 1 float for the strainer, 1 20 l jerrycan for fuel, 1 can of engine oil, 1 funnel, 1 tool kit with spare parts for normal survives, a user's manual and a maintenance logbook.
- The recommended conditions of use and the maintenance practices should be followed (pumping hours, frequency of oil changes, etc.), so as to avoid breakdowns which might interrupt an emergency water supply.
- Where the motorpump is to be used for long periods in a fixed position, shelter it from the weather.
- The kit is a complete unit. Its component parts should not be separated. The whole kit should be repacked in its original case if it is to be stored again or sent elsewhere.
This chapter describes the health risks created by inadequate sanitation. It suggests some simple techniques for disposal of excreta, wastewater and refuse, which improve environmental sanitation and thus create "sanitary barriers".
Introduction
The term "excrete" includes urine and faeces.
The main objective of excrete disposal is to reduce the transmission of diseases due to environmental contamination by fl matter or the proliferation of vectors.
In an emergency situation, steps must be taken immediately, particularly where there is a large concentration of displaced people.
The methods of excrete disposal which apply to refugee camps as well as rural situations are generally simple and cheap. The choice of method will be decided more by local practices and socio-cultural factors than by technical considerations.
Excreta-related health risks
Many infectious diseases are transmitted by human excrete. The pathogens leave the body of the infected person in the excrete and contaminate one or more healthy individuals.
Urine is less dangerous than faeces, except in the case of one type of schistosomiasis (Schistosoma haematobium), typhoid, paratyphoid and leptospirosis (e.g. where water is contaminated by rat urine).
Five types of excrete-related diseases or transmission routes may be identified:
1.Faeco-oral transmission
Pathogens are transmitted by direct and domestic contamination (hands, water, food and objects contaminated by excrete).
The pathogens may be viruses, bacteria, protozoa and certain helminths. The list of faeco-orally transmitted diseases is long and includes diarrhoeas, typhoid fever, cholera, amoebic dysentery, giardia, hepatitis A, etc.
Control measures:
- providing toilets,
- improvement of water supply,
-
improvement of shelter conditions,
- improvement of hygiene practices.
2.Helminths (worms) transmitted by soil
Helminth eggs have a latent period, or period between the moment they are excreted and the moment they become potentially infecting. The transmission of these "geohelminths" takes place through the contamination of soil or crops.
It mainly concerns ascaris, trichuris, ankylostoma and strongyloides. Infection by these helminths is very frequent and prevalences may be greater than 90% in certain populations.
Control measures:
- general excrete control,
- and/or treatment of excrete
before use for fertilizing crops.
3.Beef and pork tapeworms (taenia)
Cattle and pigs are intermediate hosts of taenia The transmission cycle involves the contamination of soil and forage by human excrete, then the ingestion of undercooked meat by humans.
Control measures:
- excreta disposal,
- and/or treatment before use as a
fertilizer,
- inspection and thorough cooking of meat.
4.Water-based helminths
The excreted eggs of this category of helminths pass part of their life-cycle in one or several intermediate aquatic hosts (snails, crustacea, fish), before becoming infectious to man. Examples are schistosomiasis and flukes.
Control measures:
- excreta disposal,
- treatment before disposal in the
aquatic environment,
- control of intermediate hosts (e.g. snails in
irrigation canals),
- reduction of contact with potentially contaminated
water,
- correct cooking of fish and aquatic plants.
5. Excreta-related diseases transmitted by insect vectors
This includes all the diseases in the previous category which can be transmitted by insects (flies, cockroaches, etc.), and diseases transmitted by mosquitoes breeding in polluted water (Culex quinquefasciatus which transmits bancroftian filariasis).
Control measures:
- excreta disposal coupled with control of certain vectors.
The impact of an excrete disposal programme on health is difficult to evaluate.
It is generally agreed that a health impact will only be achieved if such a programme is linked to improving water supplies and individual and collective hygiene.
Choice of disposal technique
There are many excrete disposal techniques. In each situation the technique chosen should be adapted to the site conditions and the population concerned.
If this rule is ignored, the system may quickly become unused and damaged and may even create a health risk in itself.
In general the choice of an excrete disposal technique depends on:
- cultural factors, particularly local altitudes and practices
concerning defecation;
- the physical nature of the site (soil type, natural
drainage, rainfall patterns, water resources);
- the space available and
locally available materials and skills.
A distinction may be made between emergency situations, where immediate action should be taken, and chronic or long term situations, where other factors dictating the choice of technique should be given more consideration.
EMERGENCY SITUATIONS
When there is a large collection of people (e.g. a refugee camp), or where the normal sanitation structures are destroyed in a disaster, it is essential to provide defecation facilities immediately. These facilities are usually provisional and are progressively improved or replaced by more suitable structures as the situation develops.
A defecation field or area may provide an emergency solution, particularly in hot dry climates and where there is enough space available. Defecation fields should be clearly marked, fenced if possible, and protected against flooding.
They should be located downwind and away from living areas, avoiding water courses and at a reasonable distance from water points (minimum 50 m).
If a bulldozer is available locally it is recommended that the ground is cleaned regularly and the fl material is buried in a trench so that the area may be reused.
The use of collective trench latrines may also be an adequate solution for emergency situations (see brief Trench latrines).
If a high water table, rock or sandy soil prevent the digging and use of trenches, elevated platforms may be built. It is also possible to use 200 litres drums, partially buried in the ground with an opening at the top, or to use concrete slabs which can be set on the top of opened drums.
If augers or drilling equipment are available, drilled latrines covered with simple slabs may be installed rapidly.
Whatever the emergency solution chosen, it is important to take steps to ensure that the facilities work well, are maintained properly and are used.
CHRONIC SITUATIONS
Different disposal techniques may be used in refugee camps and in emergency situations (simple pit latrines, VIP latrines, pour-flush latrines). There is no formula to suit all circumstances. For each situation some basic questions must be asked; the answers should help in the choice of technique:
- What are the traditional methods and habits concerning
defecation?
- What method of anal cleansing is used?
- What position is
used (sitting or squatting)?
- What are the cultural, social or religious
habits which affect the technique of excrete disposal (separation of the sexes,
of groups or of individuals, particular orientation of latrines, taboo places,
the need to be alone, the acceptability of emptying a latrine pit, etc.)?
-
What is the level of the water table? What seasonal variations are there?
-
What is the rainfall pattern? What is the soil type?
- What other physical
characteristics of the site may influence the choice of system (density of
settlement, proximity of water sources, availability and type of building
materials)?
The system should be chosen with the answers to these questions in mind, whilst remaining simple, cheap and above all easy to install and maintain.
As a general rule, individual family latrines are prefered. In most cases, individual family latrines are socially more acceptable and pose fewer problems maintenance than collective systems. If individual latrines are not possible because of population density, centralised units may be built at the edge of a living quarter or camp section where each family has access to its own latrine.
The area allowed for latrines should be big enough to dig new pits when the first ones are full.
Collective latrines usually pose maintenance problems. When this system is adopted for a population or for a central service (e.g. a hospital), it is indispensable to appoint someone to be responsible and possibly to pay them to ensure good maintenance.
An exereta disposal programme
Eight successive phases may be considered:
1. Identify the problem: site survey, questions, medical data,
etc.
2. Initiate and organise participation of the population: consult local
leaders, etc.
3. Collect information: geographic, climatic, demographic,
socio-cultural technical and material.
4. Propose alternatives: analysis of
data and technical options.
5. Choose a method: needs, social suitability,
resources (financial, material and human), geography (soils, water, climate),
space (family or collective systems).
6. Implement the system chosen: involve
the population, control the costs, plan the construction.
7. Use and maintain
the system: inform, educate. Take special care with collective systems.
8.
Evaluate the system: sanitary inspection and monitoring system.
Calculation of the effective volume of a latrine pit
The pit latrine is the most common system of excrete control in the world.
To calculate the effective volume of a pit, proceed as follows:
V = N x S x Y
where |
V = effective volume in m3, |
|
N = number of users, |
|
S = solids accumulation rate in m3/person/year, |
|
Y = lifetime of latrine in years. |
For dry pits, use a solids accumulation rate of 0.04m3 per person per year. For wet pits, use 0.02m3 per person per year.
When calculating the total pit volume a free space of 0.5m at the top of the pit is added to the effective pit volume.
The volume may also be increased by 30 to 50% if bulky anal cleansing material is used (e.g. stones, maize cobs, etc.).
The suggested design life of a non-emptyable simple pit latrine is 5 to 10 years.
That of an emptyable latrine (simple or alternating twin pit) is at least two years.
Conclusion
The designs shown in the technical briefs which follow represent the most simple and common techniques of excrete disposal:
- trench latrines, suitable for emergency situations;
-
simple pit latrines, ventilated or not, the most frequently used;
- twin pit
emptyable latrines, suitable for public facilities;
- pour-flush latrines,
more sophisticated, suitable where there is plenty of water and where the
population is familiar with this technology;
- flushing toilets with septic
tanks, sometimes seen in hospitals, but which need constant running water.
This is just a quick review of disposal techniques. There are variations which allow adaptation to local conditions.
In general terms, an excrete disposal technique may be considered acceptable when:
- it contains the excrete in one place;
- it does not create
an attraction for insects;
- it is not a source of pollution of water
points;
- it is accessible to users;
- it gives a minimum of privacy;
-
it is adapted to local
habits.
Introduction
"Nothing is lost, nothing is created, everything is transformed.." This principal applies equally to water: it is the source of life, much effort is spent to get it; but it also is a source of death, and it is essential for health that the same effort is made to remove it after use.
Health risks and nuisance
These risks are due to organic and biological pollution carried by wastewater as well as the presence of stagnant water:
- breeding of insect vectors (anopheles, culex);
- spread and
multiplication of pathogenic agents such as cholera vibrios and schistosomonas,
etc.;
- chemical contamination of water (nitrates, detergents) and ecological
disturbance of aquatic environments;
- production of noxious and corrosive
gases.
Definition of wastewater
The risks associated with wastewater depends on its origin, and it is useful to classify the important sources:
- Domestic wastewater
· Sewage: water carrying excrete in suspension, thus
containing bacteria, viruses and fl parasites and also nitrogen.
·
Sullage: water from the bathroom, the kitchen, laundry, etc., containing
detergents and fats as well as micro-organisms of fl origin.
- Agricultural wastewater
· Stockraising effluent: slurry and manure.
· Crop
growing activities: fertilizers and pesticides.
It is usual to measure the degree of pollution by the following parameters:
- Daily volume of effluent.
- Chemical Oxygen Demand (COD): a
measure of the total organic content.
- Five day Biological Oxygen Demand
(BOD5): the organic content biodegradable within 5 days.
- Total Suspended
Solids (TSS).
- Nitrogen content (ammonia and organic nitrogen).
-
Phosphorous content
General principles
For every place supplied with water there should be a removal system which prevents stagnant water and local pollution.
Treatment methods aim to fix the chemical and biological pollution (by sedimentation, filtration, etc.), and/or to destroy it by biological, chemical or physical processes and then to dispose of the treated water by infiltration into the ground, or into surface water (river, lake sea, etc.).
This field may become very technical and involves special expertise which is beyond our capabilities.
In practice, the problems faced in the field are few and generally simple to solve; for instance:
- stagnant water around a water point: well, tap, etc.,
-
washing areas: bathing, cooking, laundry, etc.,
- laboratory and health
centre wastes, etc.
More rarely:
- flushing toilets,
- house or hospital
sewers.
Removal
A removal system should be able to remove wastewater, so as to avoid stagnant water, and to channel it to the disposal or treatment site without contaminating the local environment.
The collection surface should be gently sloped (1%) and cemented. Before removal, it may be necessary to pretreat the water to remove solid or dissolved matter which could hamper the removal and final treatment (see technical briefs):
- Grease-trap to eliminate fatty material which might block
channels.
- Screen to remove floating objects.
- Sedimenter or sand trap
to separate sand, soil, etc.
These structures become ideal vector breeding sites if they are not well maintained.
The removal system design may be based on different techniques:
- Open channel
This is the most simple and least costly technique but it entails maintenance problems: blockages, stagnant water, damage to the sides, etc.
This technique should be used only for drainage of rainwater or of wastewater over short distances; the channel should be cement-lined if possible and with enough slope to be self-cleansing
- Gravel drain
The open channel may be improved by lining it with plastic sheeting, filling it with coarse gravel, covering it with more plastic sheeting and then with earth.
The wastewater should never contain suspended material capable of blocking this type of drain which is impossible to unblock. This technique may be used in an emergency, for example at a dispensary or a laboratory.
- Pipe drain
This is the most effective way of removing wastewater but also the most costly.
Various types of pipe may be used (PVC, polythene, cement, fibrocement, etc.), with a minimum diameter of 100 mm.
The slope and the pipe diameter should be adequate for the flow, and the pipes should be buried correctly so as not to be destroyed by the passage of heavy vehicles (20cm of compacted earth minimum).
Check regularly in order to spot and deal with blockages.
Treatment
Wastewater treatment techniques mostly need specialised skills and technologies.
For this reason, these sophisticated techniques will not be studied in this guide. Information will be limited to infiltration systems and the basic principles of waste stabilization ponds.
INFILTRATION
Infiltration uses the natural capacity of the soil to fix particles present in water by filtration, and to purify the water by a process of biological decomposition capable of destroying micro-organisms and chemical pollution.
This natural capacity is always extremely variable, depending on the soil type:
- A mature organic-rich soil is host to intense biological
activity favouring purification, but it blocks rapidly and so has a reduced
infiltration potential;
- Conversely, a sandy soil may have an infiltration
rate which is too rapid and which does not allow sufficient time for
purification if the water table is too close to the surface;
- For the same
reasons, a fissured rock would have only a small purifying capacity.
In practice, the two following parameters should be studied:
- The slope of the ground: a slope too steep may encourage water
to reappear and so contaminate the ground.
- The infiltration rate:
determined by percolation tests with clean water (see technical brief Soil
permeability).
The principle of infiltration is used in the following techniques:
· soakaway pit,
· infiltration trench,
·
evapotranspiration area,
· irrigated garden.
WASTE STABILIZATION PONDS
Waste stabilization is a biological process which takes place in ponds arranged in series.
It is an effective technique for the elimination of pathogens and is relatively easy to maintain, but the design and implementation should be left to specialists, or the result may be an almost insoluble problem.
It may be assumed that with a series of three ponds and a retention time in the ponds of 11 days, a reduction of 99.9% in the number of fl germs may be achieved.
The reuse of wastewater for irrigation after treatment in ponds may be useful, provided that the following rules are followed:
- ensure that irrigation is not likely to create areas of
stagnant water;
- irrigate crops which are not in contact with the soil (e.g.
fruit tree), or which are cooked before
eating.
Introduction
The accumulation of household waste creates a public health refuse as well as a pollution problem.
The health risks are essentially to do with the encouragement of insect vectors and rodents:
- the breeding of flies which play a major part in the
transmission of f-oral diseases;
- mosquitoes of the Aedes genus which lay
eggs in water lying in empty tins, drums, tyres, etc., and which are responsible
for the transmission of dengue, yellow fevers and other arboviruses;
-
mosquitoes of the Culex genus which breed in stagnant water heavily loaded with
organic matter, and which are liable to transmit microfilariases;
- rodents
which are directly or indirectly responsible for the transmission of various
diseases such as plague, leptospirosis and salmonella, and whose presence
attracts snakes.
In addition to these health risks, poor management of the collection and disposal of refuse may involve the pollution of surface water or groundwater and increase the risk of fire. Lastly, the aesthetic aspects (sight and smell) are far from negligible.
These risks and nuisances are all the more serious at high population densities.
Certain types of refuse (from medical activities) represent a particular risk and so need special attention.
Type and quantity of refuse
The type and quantity of refuse produced by a community are extremely variable.
The main factors affecting the composition of refuse are:
- geographic region;
- sociocultural, cultural and material
levels, which may produce great variations even within the same community;
-
seasonal variations;
- the importance and diversity of refuse-generating
activities (workshops, dispensaries, etc.);
- packaging of food ration.
The density of refuse is in the order of 100 to 200 kg/person/day and the volume varies between 0.5 and 101/person/day; an average value of 0.5 litre/person/day may be taken.
The percentage of putrescible matter may range from 20 to 70%.
These few figures simply present orders of magnitude, and in practice the quantity and density (or volume) of refuse should be determined for each situation. Its composition is only really important when disposal is by means of incineration or composting.
In general terms it may be assumed that the volume of refuse will be small when dealing with a population of rural origin and where the basic ration is in the form of dry foodstuffs (as is often the case during the initial phases of an emergency operation).
Refuse containers
The objectives are:
- to gather the refuse to facilitate the collection;
- to
avoid dispersion by wind and animals.
Metal drums are generally used. The bottoms should be pierced so that they do not retain liquids from decomposition (and to avoid the drums being used for other purposes), and they should be provided with covers and with handles for easy lifting. In the first instance one drum per ten families may be provided, placed at a reasonable distance from the dwellings.
Certain structures need particular storage systems, either because of the specific nature of the refuse produced (hospitals), or because of the large volumes produced (market, slautghterhouse, various workshops). In these cases, solid, covered and easily cleaned bins may be built. In health centres, refuse is collected in separate containers: some dustbins are available for ordinary refuse and others, clearly marked, are used only for medical waste.
Collection
Collection should be done at least once per week to avoid the hatching of flies and odour problems. In practise the use of a whole chain of different resources need to be optimised, but a daily collection is the ideal.
The collection of the contents of dustbins (without forgetting the surroundings) may be done with vehicles. But it may be more reliable logistically to use hand carts or animal carts. Moreover, it is difficult in emergency situations to commit a vehicle exclusively to this task.
The collection should be organised:
- establishment of circuits,
- constitution of teams,
-
allocation of a circuit to each team.
After its introduction the collection system should be supervised and evaluated periodically. (Is the circuit appropriate? Are the resources enough?)
These two steps of storage and collection require the co-operation of the population, which should be involved regularly (once or twice per month) in a general clean-up of the camp.
Disposal
Three techniques are used
- burying,
- incineration,
- composting.
BURIAL
Burial is done in trenches. Controlled tipping (see brief Controlled tip) is only used where there is sufficient space and access to mechanical equipment.
Access to the site should be restricted (a fence). If good drainage is not ensured, there is a great risk of the trenches turning into sickening quagmires.
The siting of the trenches should follow the same rules as for siting latrines, as the risk of polluting the water table is the same.
INCINERATION
Medical waste should be incinerated as it is potentially contaminated.
This method is not generally suitable for household wastes as it is costly and may be dangerous when it is done on a large scale (atmospheric pollution).
COMPOSTING
Composting is biological decomposition in the presence of air, as opposed to anaerobic decomposition which takes place in septic tanks for instance.
It is a technique which needs special care and which may cause major health risks if not mastered correctly. For this reason it should not be used in emergency situations.
Trench latrine
Simple pit latrine
Ventilated improved pit
latrine
Twin pit latrine
Latrine slab
Pour-flush latrine
Septic
tank
Refuse pit
Controlled tip
Dustbin
Temporary
incinerator
Permanent incinerator
Soakaway pit
Infiltration
trench
Soil permeability
Grease trap
Irrigated
garden
Evapotranspiration area
Sterilization by autoclave
Sterilization
by hot air
Sanitary surveillance
Trench latrine
Method
Trench latrines represent a method of excreta disposal which is simple and rapid to implement, but temporary. They are only justified in emergency situations, until more permanent solutions are implemented.
Installation
- Choose a site away from water points (>= 30 m), and downhill from them.
- Dig trenches about 30 cm wide and 90 to 150 cm deep. Allow about 35 m per 100 users.Place the excavated soil near the side of each trench so that the users can cover their excrete with soil after each use, to reduce the attraction of flies.
- Lay planks down the two sides in order to ensure a good foothold and to limit erosion of the trench edges.
(When the excrete reaches about 30 cm from the surface, fill in the trench with compacted earth. Mark the spot and dig another trench.)
- Fence the area (for example with plastic sheeting), and put up a zigzag entrance in order to limit the risk of straying of animals and to keep as much privacy as possible for users.
- Put a water container with a tap and soap in an obvious place (near the exit) to allow the washing of hands after defecation.
Key
1. Fence (plastic sheeting)
2. Water container with tap and
soap
3. Stones for drainage
4. Zigzag entrance
5. Planks
6. Trenches
(width: 30 cm; depth: 90 to 150 cm)
7. Soil for burying excrete
Inputs
- Shovels, picks
- Planks (or wooden poles)
- Stakes (for
the fence)
- Plastic sheeting (or local material)
- Empty cans (to handle
soil for burying excrete)
- Water container (e.g. 200 l drum) with tap
-
Soap
Important
- The planks may be replaced by wooden poles (which should be buried several centimetres).
- Ensure that living areas are not downwind of the trench latrines.
- It is usually necessary to build separate trench latrine areas for men and women. Simply separating the male and female sections with plastic sheeting and providing two separate entrances may not be enough from the point of view of acceptability to the population.
- The objective should be to replace the trench latrines as quickly as possible with a more hygienic system (e.g. ventilated pit latrines; see the other Latrines technical briefs).
Simple pit latrine
The simple pit latrine is one of the simplest and cheapest means of disposing of human wastes. If well designed and built, correctly sited and well maintained, it contributes significantly to the prevention of fcoorally transmitted diseases.
Construction
1. Choose a site downhill from groundwater abstraction points and at least 30 m away; the latrine (or group of latrines) should be not less than 5 m and not more than 50 m from the dwellings.
2. Dig a pit, assuming that the solids accumulation rate will be about 0.04 m3 per person per year. Thus, for a group of 25 people (the maximum number per latrine recommended by WHO), it needs a pit of at least 0.04 x 25 = 1 m3 per year of use.
3. If a cement slab is to be used, it should extend at least 15 cm beyond each side of the pit to ensure a secure seating.
4. Make a slab (see technical brief Latrine slab), and place it over the pit.
If the soil is unstable it may be necessary to build a foundation to strengthen the pit walls before placing the slab.
5. Construct the superstructure. It may be built with bricks, earth, wood, plastic sheeting, etc., but preferably local materials. The superstructure should have a door if local habits dictate. Otherwise a spiral form may be used.
6. Fix a roof with the slope towards the back of the structure.
7. Dig a drainage channel around the latrine to prevent run-off entering and to protect the walls of the pit.
Key
1. Effective volume of pit
2. Defecation hole
3.
Slab
4. Cover
5. Superstructure
6. Roof
7. Slab seating
8.
Drainage channel
9. Water table
10. Example of a concrete slab (see
brief)
11. Possible alternative: slab of logs (covered with soil to make
maintenance easier; quality of wood is important: aging + termites = danger)
Inputs
- Shovel, pick, miner's bar
- Slab (see technical brief)
-
Cover (wood, metal or concrete)
- Material for superstructure and door
Important
- Try to ensure that the cover is always replaced to avoid
breeding of flies and bad smells around and inside the latrine.
- The slab
and surroundings should be cleaned every day.
- If possible, provide lighting
for use at night.
- Never put disinfectants (chlorine products, Iysol, etc.)
in the pit: this only serves to inhibit the natural decomposition of fl
material. The only situation in which it is recommended to pour disinfectants
into a latrine pit is during a cholera epidemic.
- On the other hand it is
recommended that fire ashes are put into the pit after each use. This gives a
perceptible reduction of odours and accelerates decomposition.
- When the pit
is nearly full (50cm from the surface), demolish it, or move the superstructure
and slab to a neighbouring place and fill the pit with soil. Do not dig this
place again for at least two years.
- Important: allow for the spare 50 cm of
depth in the calculation of pit size. It is not part of the effective pit
volume.
- Alternative method: if the subsoil is very rocky or the water table
is very high and it is not possible to leave 1.5 m between the bottom of the pit
and the groundwater level, the pit may be partially dug in a very very compacted
earth mound. In this case the above-ground part should be lined with bricks or
stones.
- Improvements: ventilated improved pit (VIP) latrine, twin pit
latrine (see corresponding technical briefs).
Ventilated improved pit latrine
(VIP)
Method
The VIP uses the movement of air across the top of a ventilation pipe to draw odours up the pipe and out of the latrine. Flies entering the pit are attracted to the light at the top of the pipe and die trying to escape through the mosquito netting.
Construction
1. Choose a site downhill and at least 30 m distant from groundwater points; the latrine (or group of latrines) should be not less than 5 m and not more than 50 m from the dwellings.
2. Dig a pit, assuming that the solids accumulation rate will be about 0.04 m3 per person per year. Thus, for a group a 25 people (maximum number per latrine recommended by WHO), it needs a pit of at least 0.04 x 25 = 1 m3 per year. If possible make the pit big enough to last 5 years.
3. If it is planned to use a concrete slab, it may be necessary to build a foundation on the upper part of the pit to support it.
4. Cast a slab (see technical brief Concrete slab) and place it over the pit. The slab should have a second hole behind the defecation hole with a diameter of about 150 mm to fix the ventilation pipe.
5. Construct a superstructure of brick, stone, wood, plastic sheeting etc, but preferably using local materials. A spiral form may be suitable, if it is acceptable to the population; this saves having to fit a door. The superstructure should provide a minimum of darkness so that when flies leave the pit they are attracted to the light coming from the ventilation pipe and not that coming from inside the superstructure.
6. Fix the ventilation pipe at the back of the latrine. It may be round or square, made of PVC, metal, bricks, reeds with earth plaster, etch It should be vertical, with an internal diameter of about 150 mm. A screen of mosquito netting is fixed at the top of the pipe to prevent the entry and exit of flies. Fit a roof to the superstructure with the slope carrying rainwater towards the back.
Important: the ventilation pipe should extend 50cm above the highest part of the roof.
7. Dig a drainage channel around the latrine to prevent erosion of the pit walls.
Key
1. Effective pit volume
2. Defecation or squatting hole
3.
Slab
4. Absence of cover
5. Superstructure
6. Roof
7. Ventilation
pipe (internal diameter: 150 mm)
8. Mosquito netting
9. Drainage
channel
10. Water table
Inputs
- Shovel, pick, miner's bar
- Special VIP slab
- Mosquito
netting (preferably nylon)
- Pipe of PVC or building material
- Material
for superstructure and door
Important
The slab and surroundings should be cleaned every day.
If possible, provide lighting for night use.
Never put disinfectants (chlorine products, Iysol, etc.) in the pit: this only serves to inhibit the natural decomposition of fl material. The only situation in which it is recommended to pour disinfectants in a latrine is during a cholera epidemic.
On the other hand, it is recommended that fire ashes are put into the pit after each use. This gives a perceptible reduction of odours and accelerates decomposition.
When the pit is nearly full (50 cm from the top), demolish it or move the superstructure and the slab to a neighbouring place and fill the pit with soil. Do not dig this place again for at least two years.
Alterative method: if the subsoil is very rocky or if the water table is very high and it is not possible to leave 1.5 m between the bottom of the pit and the groundwater level, it is possible to dig the pit partially in a very well compacted earth mound. In this case the above-ground part should be lined with bricks or stones.
Do not use a cover on the defecation hole: this prevents the circulation of air.
Do not forget the mosquito netting which traps flies at the top of the pipe where they die. Use a synthetic or painted metal mesh because the gases which escape via the pipe are corrosive to metal.
The VIP latrine should be built in a dear space, away from trees which impede air movement. Pay attention to the wind direction so as not to cause an odour nuisance.
Twin pit latrin
Method
Twin pit latrines may be used in places where toilets have to last for a long time, so as to economise space (public places, health structures, etc.) and, as a bonus, to produce good quality organic manure.
The latrine is built on a lined pit divided in two by a watertight partition wall. Both pits are used alternately and are emptyable. As they are reusable the system is thus permanent. For collective facilities, several pits may be constructed in series.
Construction
1. Choose the site (see technical brief Simple pit latrine).
2. Dig the double pit large enough so that each half-pit has a 2 year accumulation capacity (see the chapter Calculation of the effective volume of a latrine pit).
3. Line the pit (brick, stone, etc.), leaving regular gaps in the construction to allow liquids to infiltrate, and build up the watertight partition wall between the two equal parts.
4. Place slabs with a defecation hole over each twin-pit.
These slabs should not cover the pits completely: one or more removable slabs should cover the back of each pit so that it can be emptied.
5. Construct the superstructure which should include both defecation holes in the same cubicle. Only one hole is used at a time, while the other is blocked.
6. After a period of 1 to 3 years the first pit is full:
- block the first hole and unblock the second.
After a further 1 to 3 years the second pit is full in turn:
- take out the contents of the first pit, which has formed
compost, and reuse the pit;
- in this way the alternation between pits may be
repeated indefinitely.
The material taken out is inoffensive and does not resemble excrete at ale
It is an excellent fertiliser.
Key
1. Defecation hole in service
2. Defecation hole on standby
(blocked)
3. Slabs
4. Superstructure (spiral, or with a door)
5.
Removable slabs (for emptying pits)
6. Ventilation pipe
7-8.
Twin-pits
9. Mosquito netting
10. Gaps for the passage of liquids
Inputs
- Shovel, pick, miner's bar
- Mason's tools
- Bricks
-
Cement
- Sand, gravel
- Material for superstructure and door
-
Ventilation pipe and mosquito netting if latrine is to be VIP type
- 1
experienced builders and 1 or 2 labourers.
Important
The correct size of each pit is essential: each one should permit the storage of fl material for about 2 years, during which period possible pathogens contained in it are destroyed (biodegradation). Certain authors recommend one year only, although it is known that Ascaris worm eggs need more than one year to be destroyed.
As this technique demands the handling of fl material during pit emptying (even if the material is so decomposed that it is neither offensive nor dangerous), it is important to know before choosing such a system if it can be acceptable to the population to do this work. Social, religious and/or cultural factors may forbid it and demand the use of another method.
The compost taken out may be used to fertilize crops or if not, should be buried.
It is perfectly possible to build ventilated latrines on twin pits. Important: each pit must have its own ventilation pipe.
Remember to provide workers emptying the pits with protective clothing: at least boots and gloves (household glove type).
Latrine slab
Method
A latrine slab may be made of local material (e.g. Iogs covered with earth), but for more durable latrines a reinforced concrete slab is easy and relatively cheap.
Construction
- Make a mould of metal or wood with internal dimensions the
same as the slab. Coat the inside with an oily product such as used engine oil,
to avoid the concrete sticking to it.
- Place the mould on a flat surface
which is covered by a layer of sand, plastic sheeting, paper, etc.
- Cut the
steel bars to length and join them together with wire.
- Make a wooden or
metal template for the defecation hole, oil its surface and place it in the
mould.
- Mix the concrete: 1 volume of cement to 2 volumes of sand and 4
volumes of gravel.
- Cast a thickness of about 25 mm of concrete in the mould
and level the surface without smoothing.
- Place the reinforcing steel on the
surface.
- Cast the rest of the concrete and smooth the surface, making a
curve round the defecation hole (useful when cleaning the slab).
- Position
the footrests (e.g. bricks. Optional).
- If possible, attach handles of bent
steel bar to several parts of the slab to aid carrying.
- Cover the slab with
jute sacking or plastic sheeting and sprinkle regularly with water to keep it
damp during curing.
- After 24 hours, remove the template from the defecation
hole and recover.
- Take out of the mould and install after 4 to 6 days
curing in the shade.
Key
1. Defecation hole
2. Footrests (optional)
3. Ventilation
pipe hole (only for VlPs)
4. 8 mm reinforcing steel bars
5. Template for
forming defecation hole
Inputs
- Cement: 1/3 of a bag
- Sand
- Gravel
- Shuttering
timber, 70 mm: about 5 m
- Nails
- Reinforcing steel, 8 mm: 8 m
-
Measure
- Shovel
- Bucket
- Trough or board for mixing concrete
-
Trowel, float
- Saw
- Hammer, pincers
- Steel bar cutters
- Wire for
joining reinforcing bars
Important
- If possible, make a gentle slope towards the defecation hole;
this will ease cleaning.
- Don't forget the handles. It is very difficult to
move the slab without them.
- If the slab is for a VIP latrine, don't forget
the hole for the ventilation pipe (150 mm dia).
- Take care over the curing
(4 to 6 days in the shade): it greatly affects the strength of the slab.
-
The template for the defecation hole should be tapered to ease its withdrawal
from the concrete.
- If embarking on a programme of latrine construction, it
is well worth the trouble to build a workshop for continuous production. This
workshop should have a water point, storage for tools and a covered area for
casting and curing slabs.
Pour-flush latrine
Method
Pour-flush latrines are relatively simple in design, but should only be considered where there is abundant water for flushing.
The latrine is fitted with a pan and a water trap which stops odours from coming out and prevents flies from reaching the excreta.
Construction
- The siting and construction steps are the same as for the simple pit latrine (see the corresponding technical brief).
- The simple pit latrine slab is replaced by one fitted with a pan and water trap. In mady places such slabs can be found ready made. Otherwise it is possible to make a trap out of 75 mm PVC pipe, and fit it to an ordinary slab.
Connection
- If the pour-flush latrine is not connected to a sewer or on-site treatment system (e.g. septic tank), the pit should be masonry lined as the heavy water flow would erode the walls of an unlined pit. The lower half of the pit should be lined with open brickwork to let the water infiltrate into the soil.
- It is possible to construct this type of latrine with an emptyable twin pit if the infiltration rate is too low or if there is a risk of polluting groundwater points. (In this case the pit should be airtight: see technical brief Twin pit latrine.)
- To calculate the effective pit volume, use a solids accumulation rate of 0.02 m3/ person/ year.
- Preferably, connect the pour-flush latrine to a septic tank (see technical brief Septic tank).
Key
1. Slab
2. Pan
3. Water trap
4. 75 mm drainage
pipe
5. Simple pit or alternating twin pit
6. Open joints in lower pit
lining, to allow passage of liquids
7. Removable slab
8. Foundation
9.
Backfill and sand
10. Superstructure
11. Septic tank
12.
Inspection/emptying hole with cover
13. Outlet pipe towards an underground
soakaway system
Inputs
- Materials for superstructure
- Excavation tools (shovels,
picks, etc.)
- Slab with pan and water trap, or simple slab fitted with a 75
mm PVC water trap
- Building materials and tools (for pit or septic
tank)
- 75 mm pipe for connections
Important
- As a general rule, the pour-flush latrine is suitable for regions where water is habitually used for anal cleansing. In other cases it is preferable to use dry pit latrines.
- It is essential to have a water point close by so that the toilet may be flushed after each defecation. If the water supply fails, closure of these latrines and temporary replacement by a system not using water should be considered.
- Maintenance should be frequent: if these toilets block they should be unblocked quickly, or material will solidify and plug the water trap.
Septic tank
Method
A septic tank receives and treats wastewater before disposal (underground dispersal by infiltration trenches). The septic tank receives all domestic wastewater (sewage and sullage), and is suitable for wastewater from schools, hospitals,etc.
Operating Principles
A septic tank is a container, usually rectangular in shape, built just underground, in which wastewater is retained for 1 to 3 days.
During this period, solid material settles and is decomposed by bacteriological action. Although this biodegradation is reasonably active, the accumulation of solids means that the tank needs emptying at regular intervals, generally every 1 to 5 years.
The effluent from a septic tank needs secondary treatment before final disposal in the environment. It is purified and disposed of by underground dispersal via infiltration trenches positioned after the septic tank (see technical brief Infiltration trench).
Design principles
- In order to reduce the concentration of suspended material in the effluent, the tank has a partition separating it into 2 compartments, the first having double the volume of the second. The depth of the liquid zone is 1 to 2 m. The length of the tank is usualy 2 to 3 times its width.
- The volume of the tank is calculated on the basis of a 3 day retention time of the quantity of water entering in the tank each day.The effective depth of water should not be less than 1m.
Frequency of emplying
- The tank should be emptied when it is 1/3 full of solids. The
frequency of emptying is given by:
[1/3(volume of tank in m3)]/[(solids
accumulation, m3/ pers./ year) x (number of pers.)] = n years
The solids accumulation rate depends on temperature. A figure of 0.03 m3/pers/year is considered a reasonable average. After emptying, it is advisable to fill the tank with clean water.
Key
1. Floating material (oils, fats)
2. Clarified liquid
3.
Settled solids
4. Inlet tee
5. Outlet tee
6. Partition to retain solids
and floating material
7. Access holes with covers
8. Ventilation
a: 20% of effective depth
b: 40% of effective depth
c: 20%
of effective depth
d: 40% of effective depth
e: at least 75 cm
f:
effective depth of water (minimum 1 m)
Inputs
- Plans
- Shovels, picks, etc.
- Builder's tools
- Sand
for sub-base
- Shuttering timber
- Concrete (quantity calculated according
to tank volume), concrete blocks or prefabricated elements
- Pipes and inlet
and outlet tees (minimum die 100 mm)
- Ventilation pipe
Important
- A septic tank may be built in situ, in concrete or concrete
blocks, or alternatively, with prefabricated panels in concrete, fibre or
plastic.
- Whatever the construction method, the tank must be water-tight and
strong enough to resist soil and possible groundwater pressures. It should rest
on a sub-base of sand several centimetres thick.
- The minimum diameter of
the inlet and outlet pipes should be 100 mm and their minimum slope 2%.
- The
siting of a septic tank is dictated partly by the placing of the dispersal area
(infiltration trench). The tank should be away from vehicular passage,
accessible for maintenance, and as near as possible to the building served.
-
Make sure that there is enough land available for the underground dispersal
system and that the soil allows a sufficient rate of infiltration.
- The
gases resulting from anaerobic digestion in the septic tank should be evacuated
without nuisance. This is done by means of a ventilation pipe which extends
above roof height, taking into account the wind direction.
- The quantities
of chlorine and detergent products used in normal household and hospital
activities should not affect the tank's functioning
- It is not necessary to
use special additives in the tank to activate it. The materials collected in the
tank are rich enough in micro-organisms to start biodegradation.
- Take care
if the water table is not deep.
Example of design calculation for a septic tank
- Design calculation for a septic tank for a health centre of 20
beds and a water consumption of 50 litres/bed/day. The effluent from the septic
tank is to be disposed of in an infiltration trench.
- It is estimated that
80% of the water consumed enters the septic tank
Assumming a 3 days retention time, the volume of the tank will be:
(0.04 m3/bed/day) x (20 beds) x (3 days retention time) = 2.4 m3 or 2.4 m long, 1 m wide and 1 m deep.
- The frequency of emptying accumulated solids if one assumes that the accumulation rate is:
[1/3 (2.4 m3)]/[(0.03 m3/bed/year x (20 beds)] = 1.4 year
- For designing an underground infiltration system, see technical brief Infiltration trench.
Refuse pit
Method
In an emergency situation, the best way to dispose of household refuse (not medical waste) is burial in a controlled tip if possible (see technical brief Controlled tip), or in collective or family refuse pits if there is not enough land or the transport for controlled tipping.
The high water content of this type of refuse does not allow it to be burned in the pits; apart from using a lot of fuel, the incomplete combustion obtained by this gives a false sense of security.
- It is important to respect minimum distances to avoid the danger of contaminating water points.
· Distance from water points:
>15m if the pit serves fewer than 10 families,
> 30m if
it is a collective pit.
· Distance from dwellings:
>10m if the pit serves fewer than 10 families,
> 30m if
it is a collective pit.
- Dig a hole, leaving the earth to one side (to be used for
daily covering of refuse).
- Check that the bottom is more than 1.5m from the
water table. (It is possible to drive in a metal bar such as a reinforcing rod
to a depth of 1.5m and see if it is wet when pulled out.)
- Surround the hole
with a fence to avoid accidents and prevent the entry of animals etc.
-
Dispose of refuse in the pit each day, covering it with a layer of earth to
avoid attracting flies and rodents.
(Ashes or a mixture of ashes and earth
may be used for this covering.)
- Refill the hole completely and compact the
earth when the level of refuse reaches from the surface.
Key
1. Pit
2. Refuse, day 1
3. Earth, day 1
4. Refuse, day
2
5. Earth, day 2
6. Fence
7. Excavated earth
8. Water table
A. Dwellings
B. Refuse pit
C. Latrine
D. Well
Inputs
- 1 pick, 1 shovel
- 2 buckets (to lift out the earth)
- 1
miner's bar
- 2m length of reinforcing rod
- Stakes and fencing
material
- 2 people for 1 day (depending on size of pit)
Important
- Only throw household refuse in the pit. Do not throw in
medical (waste potentially contaminated) before incineration.
- If the soil
is too unstable it may be useful to support the walls with uncemented
bricks.
- It is not efficient (it is expensive) to burn household refuse.
This technique (described in technical briefs Temporary incinerator and
Permanent incinerator) should be reserved for medical wastes.
- It is
essential that refuse is covered with earth or ashes immediately after disposal
to avoid attracting flies and rodents and to accelerate decomposition.
- In
certain cases (hospital, feeding centre), when the quantities of non-medical
waste to be disposed of need a very deep pit, it may be covered by a slab (for
safety) with a covered opening. The cover should be heavy and fitted tightly to
the opening to prevent the entry of flies. Make sure that the cover is replaced
after each use.
Controlled tip
Method
This technique is used to eliminate a community's waste. Its feasibility is essentially dependent on the land surface available and the availability of collection and transport equipment (animal carts, lorries, etc.).
- Calculate the length of trenches needed using the following
formula: for a width of 1.5m arid a depth of 2m, dig 1 linear metre of trench
per 200 people per week
- Choose an area at least 800m from dwellings; living
areas should not be downwind from the tip.
- Take care about the distance
from water points, which should never be less than 50m away and which should be
uphill from the tip.
- Fence the area well.
- Dig a surface water drainage
ditch around the whole area. The lowest corner of this ditch should lead to a
soakaway pit.
- Dig the trenches with a mechanical shovel if possible,
placing the earth beside the trenches; this earth is used as tipping proceeds.
Operation
- The refuse is collected and taken to the tip, then dumped at
one end of the trench and covered immediately with earth. The following load is
dumped next to the first, and so on until the trench is full.
- After 6
months the trenches may safely be redug to make a new tip, or to use the
contents as a fertilizer.
Key
1. Fence
2. Trench waiting for use
3. Part of trench
already full
4. Alley (wide enough for the passage of the refuse collection
vehicle)
5. Drainage ditch
6. Crossing point of ditch
7. Lowest corner:
towards soakaway pit
8. Lorry bringing refuse
9. Excavated earth used
progressively for covering
10. Refuse
11. Layer of backfilled earth
Inputs
(construction)
- Land
- Mechanical shovel or numerous workers
- Stakes
and fencing material
- Poles or tree trunks to build the bridge crossing the
drainage ditch
(operation)
- Lorry or cart for transporting refuse
- Trained personnel,
permanently at the tip
- Shovels for covering refuse
- Boots and gloves
for personnel
- Broom and 0.05% chlorine solution (or Iysol) for daily
cleaning of the cart or lorry.
Important
- This technique needs a lot of land and sophisticated equipment
for its implementation, which can entail heavy costs.
- Important: the bottom
of the trenches must be more than 1.5m from the water table to avoid pollution
by leachates.
- The compulsory distance from dwellings demands the use of a
lorry or cart.
- The staff should be trained for their task and should wear
protective clothes; washing facilities (water and soap at least) should be
available at the site.
- If the tip is designed to have a lifespan of more
than 6 months, it is possible, when the end is reached, to redig the start of
the first trench fired, to reopen the tip. Otherwise it is necessary to open a
second tip during the time it takes for the first one to stabilize.
- The
fence is essential to avoid scavenging and accidents at the tip.
Dustbin
Method
The dustbins may be used along paths and roads in a refugee camp or in the courtyard of a hospital.
- Cut a 200 litres oil drum in two.
- Hammer the cut edges to
avoid injuries.
- Fix a cover on the open end with hinges.
- Pierce about
20 holes in the bottom with a large nail to let decomposition liquids drain
out.
- Fix a handle on the cover for opening, and two on the sides for
carrying.
- Paint the inside of the dustbin with anti-corrosion paint.
-
Paint the outside in a bright and attractive colour to make it clearly
visible.
- Make a support, in metal or wood, for example, to raise the bottom
of the dustbin from the floor.
- Dig a hole where the dustbin will be placed,
50cm deep, the same diameter as the dustbin, and fill it with stones to drain
leachates.
- Place the support on the stones and the dustbin on the support.
Key
1. Cover
2. Handles
3. Hinge
4. 1/2 metal drum
5.
Pierced bottom
6. Support
7. Stones (drainage)
8. Hammered edges
Inputs
- 1 drum, 200l
- 1 cold chisel or metal saw
- Wire, nuts
and bolts, or pop rivets for fixing handles
- 1 hinge (or piece of rubber or
leather) for attaching cover
- Wood or metal and stones for support
-
Anti-corrosion and coloured paints
Important
- Attach the cover in such a way that it falls shut every time
it is let go.
This is the only way to be sure that the dustbin is always
covered.
- Allow one dustbin for every 10-15 houses, and others along roads
and in public places (schools, markets, etc.).
- Organise refuse collection
and diposal.
- Organise regular cleaning and disinfection of the
dustbins.
- Hammer the cut edges to avoid injuries.
Temporary incinerator
Method
This incinerator serves a temporary purpose in a dispensary or health centre.
If the health structure becomes permanent, it should be replaced by a permanent incinerator.
- Cut the top cleanly off a 200 l metal drum, around 2/3 of its
perimeter (see fig. 1). Cut a hole the diameter of the chimney in the remaining
part of the cover.
- Perforate a metal plate (length = internal height of
drum, width = diameter of drum at the place the cover was cut), all over its
surface with holes about 1 - 2 cm diameter. Slide it into the alum and fix it so
as to divide the inside into two chambers of unequal volume.
- Fix the cut
part of the cover to the top edge of the plate with hinges.
Attach a handle
so that this cover may be opened and closed.
- Cut some rigid metal grating,
or make some with the same cross section as the large chamber of the drum (in
front of the metal plate), and fix it horizontally about 20 cm from the bottom
of the drum.
- Cut out a panel 40 x 40 cm at the bottom of the drum and
remount it as a door using hinges.
- Fit a chimney (about 2 m high) on the
hole made in the fixed part of the cover.
Operation
- Fill with refuse from the top.
- Fill the bottom with
firewood through the door (6).
- Light the fire and give it time to take
well.
- Monitor the combustion, turning over the refuse frequently.
- Once
incineration is complete, empty the ashes and &pose of them like domestic
refuse (refuse pit or controlled tip).
Key
A. Top of drum (part not cut)
B. Hole cut for chimney
C.
Large chamber (for refuse)
D. Cut-out of cover
1. Metal drum, 2001
2. Perforated metal plate
3.
Perforations in the metal plate for draught
4. Movable cover
5.
Chimney
6. Fire chamber door (used to regulate the draught)
7. Metal
grating (or heavy mesh) to separate the refuse from the fire chamber
Inputs
- 1 drum, 200l (e.g. fuel drum)
- 1 cold chisel and
1 hammer
- 1 metal saw
- 1 pair of pincers and wire
- 1 metal plate
(same thickness as drum, same height; width: about 2/3 of drum diameter)
-
Large nail or punch (for making perforations)
- System to fix the plate in
the drum (e.g. angle steel and nuts and bolts)
- Tin chimney pipe
- Heavy
mesh or grating
- Metal hinges (4)
Important
- Never over-fill with refuse: as the draught comes from the
fire, the pile of refuse should not be too compact.
- Do not empty the
incinerator from the top; only take out the ashes which fall.
- Clean out the
fire chamber frequently.
- Do not try to economise on firewood: always keep a
good fire going to guarantee complete combustion.
- Turn over the refuse
frequently during combustion to make the ashes fall and to expose all the refuse
to the flames.
- Never put explosive objects (e.g. aerosol cans) in the
incinerator, or materials which give off toxic fumes on combustion (certain
medicines for example). Always seek advice before in case of doubt.
- Situate
the incinerator where the smoke will not bother people, and place it under a
shelter if possible to avoid corrosion being worsened by rain.
- The door (6)
may be adjusted to regulate the draught. However, if the draught is enough,
incineration with the door closed is the most economical on firewood.
- If it
is used frequently, such an incinerator will not last more than a few months
(less than a year because of corrosion due to the great heat generated).
Permanent incinerator
Method
This incinerator is useful for a dispensary, a hospital or a health centre, for disposing of refuse generated by medical activities. Domestic refuse should not be incinerated, but buried (see technical brief Controlled tip).
1. Draw a detailed plan of the structure.
2. Build brick
foundations 100 x 70 x 20 cm (overall dimensions).
3. Shutter and cast the
base slab, fire chamber slab, upper slab and chimney-top slab.
4. Lay the
base slab on the foundations.
5. Build the refractory brick walls up to the
height of the fire bars. Lay the fire chamber slab and cement the fire bars in
place.
6. Continue the walls up to the chimney. If possible, plaster the
inside of the fire chamber with a heat-resistant mixture.
7. Lay the upper
slab which acts as a base for the chimney.
8. Build the chimney at least 1.5
m high (be sure to use a plumb line; the chimney should be perfectly
vertical).
9. Fit the fire chamber and refuse-loading doors.
10. Let the
structure cure for 2 to 3 weeks, covered in wet jute sacking or plastic sheeting
before using it.
Key
1. Brick walls (7 x 14 x 28 cm)
2. Fire bars (3 cm
spacings)
3. Door of fire chamber
4. Door for loading refuse
5.
Chimney
6. Base (reinforced concrete: 130 x 70 x 8 cm)
7. Fire chamber
slab (reinforced concrete:70 x 60 x 3 cm)
8. Top slab (reinforced concrete:
100 x 70 x 7 cm)
Pay attention to the opening left for the chimney (25 x 45 cm)
Inputs
- Detailed plans
- About 300 refractory bricks (7 x 14 x 28
cm)
- 4 bags of cement
- Sand (270 litres)
- Gravel (125 litres)
-
Refractory plaster mix (earth, lime or cement)
- 2 metal doors
- 15 metal
bars (8 mm dia, 650 mm long)
- Reinforcing steel, 6 mm: 18 m
- Shuttering
timber for the slabs
- Builder's tools
- About 3 days work for one
experienced builder and one labourer.
Important
- The combustion capacity of such an incinerator is about 100 kg
of refuse per hour.
- The incinerator should function with the loading door
shut to encourage the draught.
- The same remarks on operation apply as those
for the temporary incinerator (see corresponding technical brief).
- It is
important that one or two people are responsible for the operation and
maintenance of this type of equipment.
Soakaway pit
Method
A soakaway pit allows the disposal of wastewater from a water point, kitchen, shower etc by infiltration into permeable soil.
Construction
1. Choose the site: at least 6 m from dwellings, 3 m from trees or hedges, 30 m from groundwater points if it is a domestic soakaway pit.
2. Determine the dimensions of the soakaway pit according to the quantity of wastewater to be infiltrated and the permeability of the soil.
3. Dig the trench for the inlet pipe (diameter 50 to 100 mm), with a slope of 1%, 300 mm wide and 300 mm deep.
4. Dig the pit to the required dimensions. Measure the depth from the bottom of the incoming trench. If the pit is deep and/or the soil is unstable, support the sides during digging.
5. Fill the soakaway pit with stones up to the level of the trench bottom. The stones should be clean, with a diameter of 5 to 15 cm.
6. Lay the incoming pipe (1% slope). Clear the stones around its end to create an empty space to aid dispersal of the flow.
7. Place a large flat stone over the pipe and add a 10 cm layer of stones.
8. Cover the stones with straw or a plastic sheet and fill in the hole with earth.
Key
1. Permeable soil
2. Pipe (diameter 50-100 mm)
3.
Compacted earth
4. Cleared space at the end of the pipe
5. Straw or
plastic sheet
6. Stones
7. Flat stone
Inputs
- 1 tape measure
- Shovels, picks
- 1 wheelbarrow
- 1
pipe, 50-100 mm diameter, in PVC or cement
- Stones: enough to fill the
soakaway pit
- Straw or plastic sheet
Important
- To determine the dimensions of the pit, it is important to evaluate the infiltration capacity of the soil and to allow for a possible increase in the amount of wastewater to be disposed of.
- Install a grease trap before the soakaway pit if it is meant to take wastewater from kitchens, in order to avoid clogging by fats (see technical brief Grease trap).
- The straw or plastic sheet over the stones prevents soil from getting between the stones and blocking the system.
- The bottom of the soakaway pit should be at least 1m above the water table during the wettest period, and 1m above any impermeable layers. If this is not possible, opt for a system of infiltration trenches (see technical brief Infiltration trench).
- Plant the area of the soakaway pit with grass if water or wind erosion are severe.
Infiltraton trench
Method
Infiltratiom trenches may be used for the underground dipersal of wastewater from kitchens, health centres, etc. They may equally well be used for disposing of water from septic tanks.
Construction
1. Choose a site at least 30 m from groundwater points, 6 m from
dwellings and 3 m from trees or hedges and 3 m from possible property
boundaries.
2. Determine the dimensions of the trench or trenches according
to the permeability of the soil and the quantity of wastewater to be infiltrated
(see technical brief Soil permeability).
3. Dig the trench for the incoming
pipe (300 mm wide, 1% slope).
4. Lay the pipe (100 mm), and cover with
earth.
5. Dig the infiltration trench to the required dimensions (with a
slope of 0.5 to 1%).
6. Rake the sides and bottom of the trench. Do not walk
in the trench after this step.
7. Fill the trench with gravel up to the level
of the inlet pipe (minimum thickness 100 - 150 mm).
8. Extend the inlet pipe
about 0.5 m into the infiltration trench.
9. Lay the drain (perforated pipe,
or pipe sections with loose joints). Plug the far end.
10. Fill the
infiltration trench with gravel to a thickness of 50 mm over the drain.
11.
Cover the gravel with straw or a plastic sheet.
12. Fill the trench to the
top with earth and compact it lightly.
13. After one or two weeks, plant
grass on the top to limit erosion.
Key
1. Permeable soil
2. Gravel
3. Incoming channel
4.
Drain (perforated pipe)
5. Straw or plastic sheet
6. Earth
7. Plug at
the end of drain
8. Distribution box
Inputs
- 1 tape measure
- Shovels, picks
- 1 wheelbarrow
- 1
pipe, 100mm die in PVC, cement or clay
- 1 drain (perforated pipe or pipe
sections with loose joints)
- Gravel
- Straw or plastic sheeting
Important
- Dispersal systems using simple or multiple trenches are an alternative to soakaway pits for less permeable soils, where there are large quantities of effluent, in the case of a high water table or where there are rocky layers near the surface.
- To estimate the dimensions of the trench, evaluate the infiltration capacity of the soil and allow for a possible increase in the amount of wastewater to be disposed of.
- For a system with several trenches, a distribution box is installed at the beginning of the drains to ensure that the effluent flow is well divided. The box should have an inspection cover and may be designed like a grease trap (see technical brief Grease trap).
- The straw or plastic sheet over the gravel bed prevents the entry of soil which would block the system.
- The bottom of the infiltration trench should be at least 1 m above the level of the water table during its highest period and 1m above any impermeable layer.
Soil permeability
Technique
The measurement of soil permeability by means of percolation tests allows:
1. Judgement of the infiltration capacity of a soil to be used for the dispersal of effluents;
2. Determination, using the results, of the dimensions of a dispersal system.
Method
- Dig at least 3 test holes, each one 150 mm wide and 500 mm
deep on the proposed site.
- Fill the holes with clean water and leave
overnight or at least for several hours to bring the soil to a saturated
state.
- The next day, fill the test holes with 300 mm of water.
- After
30 minutes and then 90 minutes, measure the water levels in the holes.
-
Calculate the difference in level corresponding to this period of 60
minutes.
The soil may be considered as having an infiltration rate sufficient
for a dispersal system if the level in each hole falls by at least 150 mm during
this60 minute period.
Key
Percolation test
1. Permeable soil, proposed for a dispersal system
2. Test
holes: diameter = 150 mm, depth = 300 mm
3. Test hole filled with 300 mm of
water to measure the infiltration rate
Inputs
- 1 operator
- 1 hand auger or 1 pick and shovel
- 1 watch
or stopwatch
- 1 tape measure
Important
- The percolation test is done with clean water, so does not
allow for the clogging effect of the discharge of effluents carrying
solids.
- It has been found that the infiltration rate for different soil
types is more or less the same once the soil surface is partially clogged. The
infiltration rate is thus usually found to be between 10 and 30 l/m3/day.
-
For safety, it is better to work on the basis of 10 l/m3/day for the
infiltration of effluents and 20 l/m3/day for clean water (e.g. from a water
point).
- The following formula is used to calculate the length of trench
needed (see also the example opposite):
Effective infiltration surface (square metres) = Volume of effluent to be infiltrated (litre per day)/(Infiltration rate of soil (litre per square metre per day))
Length of trench in metres = Effective infiltration surface (square metres)/(2 x depth of trench (metres))
APPROXIMATIVE ESTIMATION OF INFILTRATION RATE ACCORDING TO SOIL NATURE
Soil nature Infiltrationrate (litre/m2/day)
Sand 50
Sandy
soil, earth soil 30
Porous limestone soil 20
Porous clayey limestone
soil
Compact limestone soil 10
Compact clayey limestone soil
Example of dimensions determination of a d dispersal system
The effluent of the septic tank of a health centre must be eliminated with infiltration trenches.
- The effluent volume to infiltrate is 500 litres per day.
-
The infiltration rate of the soil is estimated at 10 litres/m2/day.
- The
trenches will be 0.7 m depth.
· The effective infiltration surface is calculated the following way:
Volume of the effluent(l/day)/Infiltration rate(l/m2/day)= 500/10 = 50 m2
· A trench is made of two vertical walls; the total lenght of the trench is obtained by:
Infiltration surface(m2)/(2 x trench's depth (metre))=50 m2/(2x0.7)= 36 metres
· Notice that only the vertical surfaces of the trench are taken into account when calculating the infiltration surface.
Grease trap
Method
A grease trap is used for separating solid materials, oils and fats contained in wastewater before its disposal in the ground. If oils and fats are left in the effluent they very quickly clog an infiltration system. Two simple types of grease trap may be distinguished (the choice of one or another type will be decided by the resources and skills available): a) With an elbow at the inlet and a "T" at the outlet. b) with separating partitions.
Principle
In both cases the trap operates with three zones:
1. 1nlet zone which slows down and distributes the effluent in
the trap;
2. Middle zone where fatty material floats and accumulates at the
surface and where heavier solids settle to the bottom;
3. Outlet zone where
grease-free water flows out towards the underground dipersal system.
Construction
- Choose a place with easy access, above the dispersal system
(soakaway pit, infiltration trench).
- Design the grease trap and draw a
detailed plan (see effective volume).
- Excavate at the chosen place, to
dimensions greater than the trap to be built.
- Build the grease trap using
locally available means and materials, e.g. cast concrete, bricks or concrete
blocks, with an internal cement plaster.
- Position the inlet and outlet
pipes carefully to facilitate the flow and the operation of the trap. The
removable cover should fit well on the trap and be sufficiently heavy to avoid
unauthorised opening (children).
Key
1. Watertight casing
2. Removable cover
3. Inlet elbow,
904. Outlet tee
5. Inlet
6. Outlet
7. Separating partitions
8.
Middle zone (separation of fats)
9. Settled solids
Resources
- Detailed construction plans
- Casing in bricks or
cement
- Cement, sand, gravel
- Shuttering timber
- 6 mm reinforcing
steel
- Shovel and pick
- Bricklayer's tools
- 10 mm PVC pipe, elbow
and tee
Important
Effective volume
- The effective volume of the grease trap should be enough to
allow a retention time of the wastewater sufficient for the separation of oils
and fats and the settlement of solids.
- As a general rule, it may be
considered that the effective volume should be double the hourly flow entering
the trap.
Maintenance
- Good maintenance is the key to the efficiency of the grease trap. Weekly cleaning is recommended to limit odours. Material removed by the trap should be buried.
Irrigated garden
Method
Wastewater from water points may be used to irrigate vegetable gardens. The most common method is flood or basin irrigation.
The basins are periodically flooded and the water stays until it infiltrates into the soil.
Furrow or channel irrigation is also practiced. The water is distributed in a system of channels between rows of plants and infiltrates vertically and horizontally (e.g. for potatoes, beans, bananas, paw paws, etc.).
Construction
- Choose a site for the garden about 15m from the water
point.
- Dig a channel or drain to collect the wastewater.
- Prepare the
garden in basins or furrows, depending on the crops grown and the space
available.
- The passage of water from the channels into the basins may be
regulated using sluices or earth.
- Continue the main channel to the end of
the garden to dispose of excess water in a soakaway pit or infiltration
trench.
- Erect a fence to keep animals out.
Key
1. Basins
2. Ridges
3. Sluices
4. Channel
5.
Flooding
6. Fence
Inputs
- Gardening tools
- Tools and materials for construction of
final disposal system (see technical briefs Soakaway pit and Infiltration
trench)
- Fence (local materials)
- Sluices (e.g. short planks)
- Seeds
Important
- In refugee camps, where space is limited, an irrigated garden
is preferable to infiltration disposal systems. It provides a nutritional
supplement for the refugees and a source of activity and possible revenue.
-
Water containing detergents may be toxic to some plants.
- Install a grease
trap (see corresponding brief) if the water comes from the washing area.
-
Take local advice on the choice of irrigation method and the watering
frequency.
- Wash vegetables (even root vegetables) before cooking and
eating.
Evapotranspiration area
Method
This is useful where a soakaway pit or infiltration trench cannot be used because of impermeable soils (e.g. clay or rock).
Evapotranspiration combines evaporation of water from the soil and transpiration by vegetation.
Siting: at least 30 m from groundwater points, 5 m from dwellings, property boundaries, trees and bushes.
Evapotranspiration is a complex phenomenon which varies with latitude, season and time of day. An acceptable approximation is given by:
Evapotranspiration rate (mm of water per day) = 0.8 x Evaporation rate
- The dimensions of an evapotranspiration area may be calculated on this basis, in the absence of other data. If the evaporation rate is not known, it may be roughly measured using a square basin of water placed on the ground. Take measurements over several days and take an average.
Construction
- Prepare and mark out the area on the ground.
- Dig the
trench for the wastewater inlet pipe and the trenches of the evapotranspiration
area.
- Spread 5 cm of sand on the bottom of the trenches.
- Install the
dispersal drains (100 mm perforated pipe) on a bed of gravel.
- Fill the
trenches with a 50cm layer of sand and gravel mixture.
- Cover everything
with 10 cm of soil.
- Plant a quick-growing local grass (for high water
consumption).
- Build an embankment around the area to protect it from
run-off.
Key
1. Impermeable soil
2. Sand and gravel
3. Drains (10 mm
perforated pipe)
4. Soil
5. Quick-growing vegetation
6. Run-off
protection embankment
Inputs
- 2 wheelbarrows
- 4 shovels, 2 picks
- Inlet pipe (100 mm
PVC)
- Dispersal drains (perforated 100 mm PVC)
- Tee for inlet pipe to
drains
- Sand and gravel
- Soil
- Quick-growing grass: sown or planted
out
Important
- The evapotranspiration area is most suitable for hot, arid or
semi-arid climates.
- Choose a short-rooted grass which needs a lot of water
for growth.
- Cut the grass regularly.
- Use a grease trap (see
corresponding brief) when the wastewater originates from a kitchen or washing
area.
Design calculation example
- A dispensary in a hot, dry tropical zone generates 300 l of wastewater per day.
The rocky soil will not allow underground dispersal. The evapotranspiration rate is 10mm/day.
Evapotranspiration rate = 10 x 0.8 = 8 mm or 0.008 m of
water/day
Effective area = volume of wastewater (m3/day)/evapotranspiration
rate (mm/day)
Effective area = (0.3 m3/d)/(0.008 m/d)=37.5 m2
Sterilisation by autoclave
Method
There are many types of autoclave on the market. They work on the same principle (water vapour under pressure, like a pressure cookery, but are operated in different ways.
The mixed energy autoclave described here (Daguerre type) is particularly suitable for emergency situations, as it can be heated by electricity, kerosene stove, gas or charcoal.
Procedure for use
1. Put water in the autoclave (8 litres if heating by kerosene,
gas or charcoal, 16 litres if heating by electricity).
2. Load the boxes
(with covers open) into the autoclave.
3. Close the autoclave, tightening
diametrically opposite clamps.
4. Choose the pressure required by moving the
weights: 1st notch = 1 bar (121°C), 2nd notch = 2 bars (134°C)
5.
Close the Yellow, Red and Blue valves, leaving the Green bleed valve open.
6.
Put on full heat. As soon as a continuous jet of steam comes out of the Green
valve, close it until the pressure reaches 1 bar; then open it and let the
pressure fall to 0.2 bar. Repeat this operation at least once in order to
eliminate all air pockets.
7. Let the pressure rise until the desired
pressure/temperature is reached (121°C or 134°C).
8. As soon as
that pressure is reached the regulating valve releases steam. Count the
sterilization time from this moment and start the timer.
9. Reduce the heat
(position 1 or 2 on the electric heater, or reduce the kerosene or gas flame) to
keep just a light jet of steam coming out.
10. When the sterilization time is
finished, cut the heat and open the Yellow valve. (Be careful of the jet
ofboiling steam: use a flexible tube to vent the steam into cold water.) Close
the valve again when the pressure drops to 0.1 bar.
11. Fill the outer tank
with cold water (16l).
12. Open the Blue valve, (the pressure reading falls
because a vacuum is created inside).
13. Wait for 10 mins and dose the Blue
valve. Open the Red valve.
14. Open the autoclave. Wait for 15 to 30 mins
with the cover half open to allow the material to dry completely.
15. Take
out the boxes and close the covers immediately.
Key
1. Chimney
2. Graduated water tank (81 and 161)
3. Blue
valve
4. Condensation coil
5. Removable collection tank
6. Air filter
(filled with cotton wool)
7. Red valve
8. Electric heater indicator
(optional)
9. Electric control (1,500/3,000/4,500W)
10. Timer
11.
Pressure gauge
12. Isolation valve, not used
13. Safety valve
14.
Weights (left:1 bar, right: 2 bars)
15. Green valve (bleeding)
16. Yellow
valve (for emptying at the end of sterilization)
17. Electric overheating
safety cut-out (optional)
18. Electric elements
19. Door for
kerosene/gas/charcoal stove
Inputs
- 1 autoclave and detailed instructions
- Boxes with
covers
- Water: 8 or 161 for sterilization plus 161 for drying
- Flexible
pipe and container of cold water (for venting steam at the end of the
cycle)
- Indicator tape (if available)
Important
- For more complete instructions, refer to the user's guide for
each model
- The timer acts only as a reminder. It does not control the
electricity supply.
- Air bleeding (step 6) must absolutely be done at least
twice, or sterilization is not complete.
- The heating time is longer when
not using electricity. The sterilization time is the same, whatever heating
method is used.
- Only start counting the sterilization time from the moment
the temperature (pressure) is reached, after air bleeding.
- If adhesive
indicator tape is available (do not confuse this with the tape used for hot air
sterilization), stick small pieces to the outside of the boxes; the indicator
tape turns brown if the sterilization time and temperature have been
achieved.
- NEVER operate the autoclave without water (the heating elements
will be destroyed).
- NEVER try to open the autoclave before the end of the
cycle.
Sterilization by hot air
Method
The "Poupinel" oven is used for sterilizing medical and surgical equipment with hot air.
- Place the hermetically sealed boxes of instruments in the
Poupinel loosely packed and not stacked, so that air can circulate between
them.
- Set the thermostat (3) at the desired temperature (see below).
-
Set the timer (5) at the desired time (see below).
- Close the door.
-
Monitor the temperature (4). Timing starts only when the thermometer shows the
sterilization temperature is reached. Adjust the setting of the timer at that
moment.
Times/temperatures
- There is a choice of 2 sterilization protocols, depending on
the type of equipment and the degree of urgency: - Either 160°C for 120
minutes; - Or 170°C for 60 minutes.
- Avoid exceeding 170°C because
you risk to damage the instruments.
Key
1. Oven
2. Door
3. Temperature control
4.
Thermometer
5. Heating time control
6. Circulating fan
7. Shelf
8.
Electricity supply
Inputs
- Electricity
- Poupinel
- Metal instrument boxes
-
Indicator tape (if available)
Important
- Ensure that timing starts only once the sterilization
temperature (160°C or 170°C) has been reached.
- If "Poupinel"
adhesive sterilization indicator tape is available (do not confuse it with the
tape used for autoclave sterilization which is very similar), stick small pieces
on the outside of the boxes; the indicator tape turns brown if the correct
temperature and time have been achieved.
- Only sterilize metal instruments
(without any plastic or rubber parts), heat-proof glass ("Pyrex" type) or
vaseline in the poupinel. Any other type of material will burn.
- Anything
which can not be sterilized in the Poupinel may be sterilized in an autoclave
(see Sterelisation by autoclave).
- This method of sterilization consumes a
lot of electricity. Although there are charcoal or kerosene-heated Poupinels
available, only the electric models are considered reliable.
Sanitary surveillance
Method
The aim of sanitary surveillance is to perform a regular and continuous evaluation of the performance of a water supply and sanitation programme. The analysis of its results should reveal both technical and operational problems in such a way as to highlight trends and promote immediate action and, if necessary, a reorientation of the programme by a revision of the objectives and resources deployed.
Sanitary surveillance is done above all through field observation (or sanitary inspection), and by establishing indicators which allow specific objectives set for the programme to be quantified (e.g. quantity of water per person per day).
- The frequency of surveillance activities depends firstly on
the situation and the results obtained Monthly inspections should be considered
a minimum. When there are particular problems (e.g. a sudden influx of people,
the rainy season, epidemics, evaluation of a programme's impact), this frequency
is increased.
- To carry out the sanitary surveillance correctly, a
standardized form is used to collect essential information (see opposite page).
This form should be adapted to each situation and should always be designed for
use and interpretation by local staff, who should eventually be able to carry
out this surveillance themselves.
- Sanitary inspections develop field
knowledge, an understanding of how well the water and sanitation installations
function and are maintained, and of the habits and practices of the population
and general hygiene conditions. It is preferable to carry out inspections
accompanied by local staff responsible for the area, and by one or more
representatives of the population and anyone else who is influential and who has
a good knowledge of the place and the people.
- The indicators to be
monitored are most commonly chosen according to specific objectives and
standards set by the programme. These indicators may be:
- water quantity: the number of people /water point,
litres/person/day, number of containers/family;
- water quality: free
chlorine residual, bacteriological quality, turbidity, taste and odour;
-
disposal of excrete and refuse: number of people/latrine, refuse pits/family or
section, etc.
Key
- Example of a sanitary surveillance form
Inputs
- 1 sanitary surveillance form, adapted to the particular
situation.
- 1 bucket, 10 or 201 and a watch for measuring water flow.
- 1
Pooltester (if chlorination is done, to measure free chlorine residual; see
brief Monitoring chlorination).
-1 portable bacteriological analysis kit (if
the programme demands, see brief Water sampling).
Important
- The analysis of epidemiological data collected in curative
health structures (morbidity due to diarrhoeal, dermatological and ophthalmic
diseases, and diseases transmitted by insect vectors) is complementary to the
sanitary surveillance carried out on the ground. It allows a relationship to be
established between the health status of the population and its general living
conditions and hygiene. It also allows better targeting of action to take and of
the health messages to spread.
- The information gathered during a sanitary
survey should be interpreted and communicated to everybody involved in the
programme, without forgetting the local staff who work directly with the
population concerned.
- It is important to maintain the frequency of
surveillance in order to sustain interest and to follow the evolution and impact
of sanitation and water supply activities over
time.
This chapter is an introduction to vector control. It presents some methods of chemical control of the principle disease vectors. It should always be born in mind that a large-scale control programme necessarily demands specialist skills.
Since the introduction of DDT forty years ago, numerous chemical products have been invented for the destruction of disease vectors and agricultural insect pests.
Two major problems have appeared:
- Many insects vectors have developed a resistance to these
products.
- Their human toxicity has, at times, caused serious public health
problems.
In the context of the work of Medecins Sans Frontieres we are confronted by these problems in several ways:
- in the course of medical treatment after poisoning,
- as
users during a specific vector control programme,
- as trainers in public
health.
This chapter should, within the limited context of our actions, allow us to choose and to use suitably some selected insecticides, to know the precautions for their use and finally to be able to take emergency medical action in the case of poisoning.But it is also intended as a warning against the apparent ease of use and effectiveness of these products.
The use of pesticides is costly, is never without risk and is not always effective. In the context of a medical programme it may be conceived:
- either in an emergency phase (an epidemic due to a
vector),
- or when the control of vector breeding sites is a problem
(difficult to locate, far away, etc.).
Chemical control should always be planned alongside a programme of improvement of the site and/or of general living conditions and hygiene (the removal of stagnant water and refuse, scrub clearance, reduction of living density, water and sanitation services, etc.).
If no action is taken in this direction even the most active and powerful insecticide would have little impact in the long term.
The pesticides are frequently used in agriculture often, however, the users are not informed of the precautions to take during the transport and use of these products. The health problems which result may go unnoticed because the poisoning is chronic.
Here again, the remedy is prevention: information and education.
Mosquitoes
Lice
Flies
Fleas
Rodents
General introduction
Knowledge, however small, of the biology of each vector is a sine quae non of effective control measures.
It is useless to try to combat body lice by treating the hair, or to try to control Culex larvae by treating clean standing water. It is vital to know how, where and when to act.
Nevertheless, it is possible to identify some principles common to all vector control programmes:
- The aim should be to make the local environment unfavourable
for the development and survival of the vector (environmental hygiene).
-
Combat is generally more effective if * is focused on immature forms of the
vector.
- Complete eradication is frequently unattainable; the objective
should be to keep the vector population below a level at which it poses a too
great risk of an epidemic.
Mosquitoes
Mosquitoes form the largest group of vectors of medical importance, with more than 3,000 species. Their life cycle is closely linked with water.
Life cycle
There are four stages of development. The first three are aquatic (egg, larva, nymph), and generally last for two weeks.
The adult (or imago) feeds on plant sap. Its lifespan varies from one to several months. The maturation of eggs in the female needs a blood meal (except for the first laying in Culex species).
Larvae may thrive in any water body except for deep water such as large river, lake or sea.
Certain genera (Aedes) use sites where the water level is variable (dependent on rainfall), such as tree trunks or leaves. Others are more specific to stagnant and heavily polluted water (Culex).
The activity of the adult varies with species: the sphere of action, hours and places of activity, type and specificity of food, etc.
Thus, in order to carry out effective control it is important to find out what species is concerned and what are its specific features.
Control methods
ENVIRONMENTAL HYGIENE
The main aim is to alter the environment so as to make it unfavourable for the reproduction of the species concerned.
-Aedes aegypti
This species is often associated with human dwellings where it breeds in any open container of water. Control measures aim at getting rid of these types of sites, or at protecting them (with a cover, or mosquito netting with mesh <0.7 mm).
Large water containers should be frequently emptied (at least once per week).
- Culex
Control measures aim to eliminate bodies of stagnant water loaded with organic matter (e.g. in latrines), or if not, then to eliminate surface vegetation in stagnant water and ensure that these water bodies are at least 1.2 m deep.
- Anopheles
Control measures are identical to those for Culex, although Anopheles have a wider distribution. Land drainage and filling also has an impact but this is rarely possible.
However, it may be necessary to couple these environmental hygiene and improvement measures with chemical control of larvae and adults.
In this case the relevant government department should be called in, as the misuse of insecticides, particularly in the aquatic environment may cause irreparable ecological disturbance and favour the development of resistance, etc.
In the case of a viral epidemic (encephalitis, yellow fever, etc.), individual protection should be done by using:
- mosquito nets (mesh diameter less than 0 - 7 mm) on openings
of houses and over beds;
- repellent creams and lotions
CHEMICAL CONTROL
- Larvicides
· fuel oil: spread over the whole water surface (little
used).
· paraffin: 30 l/ha, 1 glass/latrine/week.
· malathion:
224 to 692 g active product/ha.
· temephos: 56 to 112 g active
product/ha.
· deltamethrin: 2.5 to 10 g active product/ha.
Chemicals formulated in granules or in emulsifiable concentrate.
- Adulticides
· Persistent treatment
- deltamethrin:0.05 g active product/m2
- malathion: 1 to 2 g
active product/m2
- permethrin: 0.5 g active product/m2
- propoxur: 1 to 2
g active product/m,
- pirimiphos-methyl: 1 to 2 g active product/m2
· Aerial application
Confined to specialists.
Lice
Only the body louse is a potential vector. It is found almost exclusively between the skin and clothes. Transmission of possible pathogens through the louse's excretions (e.g. typhus) or by the louse being crushed (e.g. recurrent fever).
The louse population may grow when personal hygiene is poor (lack of water, soap or clothes), where there is overcrowding and when it is cold. A situation of a risk of epidemic may be reached, demanding emergency measures, including the use of an insecticide.
Before any action is taken, a study of the resistance of the lice to insecticides should be done by a competent laboratory or by an experienced person in the field. In the absence of resistance (which is rare), DDT or malathion may be used. If in doubt, propoxur (or permethrin) is almost always a good choice.
Powder is used, as treatment of the body. The concentration depends on the product, but 30 g of powder per person is the standard dose. Powder is applied to the fully clothed subject at the neck, half at the front and half at the back, then spread by rubbing. Pay special attention to belts and socks if these are worn. Bedding, blankets and clothes may also be treated, in a plastic bag for example.
Every bout of fever or large drop in temperature (e.g. on death) promotes the movement of lice to a new host. Patients should therefore be disinfected before being admitted to a hospital structure.
Control measures include:
- Improvement of hygiene and reduction of overcrowding.
-
Preventive treatment of clothes, blankets etc distributed (by immersion,
spraying or powdering).
- Active treatment of every body by powdering
(treatments, 1 week apart).
- Treatment of clothes by damp heat (1 hour at
70d by dry heat (ironing).
Only this method ensures the elimination of lice, ticks, and bacteria (but it uses a lot of energy).
It must not be forgotten when treating that dust from clothing etc. is contaminating (excrete of lice).
- If possible, inform people of the danger of crushing lice between finger nails or teeth (risk of spread of borrelia).
Equipment
- Powder blower (hand or knapsack)
- Soupspoon: still the
cheapest and most practical (1 soupspoon = 15 g: use one at the front and one at
the back).
- Powdering tin or pierced bag.
- Bath, tub or simple knapsack
sprayer for liquid application.
Informing the population and training operators are two essential parts of a control programme.
Precautions:
- Powders: dust masks and gloves for teams of operators doing
treatment.
- Liquids: see Precautions for use.
When treating head lice, malathion is, the usual choice of insecticide (except if there is resistance). Prepare an aqueous solution of 4% active product, add a gentle detergent if possible (e.g. fabric detergent or shampoo, to aid the penetration into ticks) and apply about 15 ml to the head of each person. Leave to act for 24 hours before rinsing. Do not use on children of less than three years.
Deltamethrin may also be used, as a solution of 0.03% active product (2.5 ml of concentrated solution/litre or one sachet of 33 g/litre of water), or a 0.05% solution of permethrin. This treatment should be avoided if at all possible.
Flies
General points
This order is composed of a wide range of species which differ in their ecology, their behaviour and their medical importance.
The domestic fly has a life cycle of 10 to 30 days, depending on temperature.
The larvae develop in mammal and bird excrete, in waste waters, and in decomposing organic matter (medical and domestic refuse). The adult which lives for 2 to 8 weeks has a radius of activity of about three kilometres. It feeds on moist or liquid substances rich in sugars and proteins.
This species is closely linked to the human environment and frequently moves between contaminated areas (excrete, medical wastes, etc.), food and drink, thus playing a disease-carrying role.
Other species are of particular medical importance due to their specific biology: those attracted by lacrymal or nasal secretions, open wounds, domestic refuse, dead bodies, etc. They are important in the spread of conjunctivitis, plan (yaws), trachoma, dysentery, etc.
Glossinia (Tsetse fly, vector of trypanosomiasis) and glossinnia (black fly, vector of onchocerciasis) demand the implementation of a specific programme because of their medical importance and their biology; the complexity of such a programme is beyond the scope of this guide.
Control methods
Larval sites, i.e. the places where eggs are laid and where the larvae develop, are very often a product of human activity.
The basic principle of all control measures should be to reduce or remove these sites,or to prevent access by flies. Without these environmental hygiene measures, all control efforts are in vain.
In practical terms, these measures focus on:
- Animal excreta: cleaning of stockraising areas.
- Refuse:
organize collection and ensure disposal by burning or burial under at least 30
cm of soil. Make covered refuse containers available (in particular in kitchens,
laboratories and health centres).
- Spilled food: make smooth floors in
feeding centres (smoothed cement or plastic sheeting) to aid cleaning.
-
Wastewater: ensure good removal and disposal, particularly at washing areas for
clothes and cooking ustensils.
Recourse to chemical products should be avoided as much as possible, because of the rapidity of appearance of resistant strains which render this option costly and ineffective.
In practice:
- In the case of massive infestation by larvae of a defecation trench or latrines, used engine oil, diesel or kerosene is used to spread an impermeable layer which asphyxiates the larvae (but take care of the risks of polluting the water table). Ashes or earth may be added to latrines pits (after each defecation, or at least every morning and night), to reduce the contact between flies and excreta.
- In the case of an epidemic, when the presence of flies creates a risk of increased spread of the pathogen, and when an operating theatre or treatment room must be protected, the use of larvicides and alduticides may be considered, but always in tandem with environmental hygiene measures.
· Destruction of larvae
Spraying of larval sites with an emulsion or a suspension until the surface is completely wetted.
· Destruction of adults
Treatment with a residual effect should be done on the surfaces where flies land at night, as it is here that there is the longest contact time. These places may differ according to the species and the climate. In general they are external surfaces of building (in hot countries), trees, fences, dustbins, animal shelters, etc.
The insecticide is applied in an emulsion or a suspension.
Malathion (5% solution, 1 to of active or deltamethrin (see technical brief) are the most suitable.
To give a permanent protection to certain places (e.g. operating theatre, dispensary, kitchen), strips of gauze or cotton impregnated with insecticide may be used (1 m length/m2 of ground surface area). Renew the impregnation every two months. Where there is a concentration of flies in a limited area (e.g. in a feeding centre), poisoned baits may be used (though there is a risk of poisoning of children and poultry). These baits should always be placed outside (on the windowsill, door, etc). They may be:
- Dried food mixed with a toxic product (1 to 2%). The bait is
then spread at a rate of 6g/ 10 m2. or
- A 10% aqueous sugar solution mixed
with the toxic product (0.1 to 0.2%), which is spread with a watering can or
sprayer.
- Fly traps.
Fleas
Fleas are blood-feeding (haematophagic) insects with a close relationship with their host. Their developmental stages all occur on land.
The flea is usually a specific parasite but it is capable of changing its host (wild or domestic rodent, man, etc.) in certain circumstances.
Biology
The development cycle lasts about one month. The eggs are laid in dusty places in houses or in rodents nests.
The larvae are found in dark places (negative photo-trohism).
In the adult stages both sexes are blood feeders.
Contamination of the host may take place through a bite (plague) or excrete (typhus), so dust may be highly contaminating.
Control methods
Control is essentially by chemical methods, even if cleaning dwellings and burning dust gets rid of eggs and larvae.
It is essential to determine the sensitivity to any given insecticide because of the many problems of resistance.
Bedding and clothes are treated with an insecticide powder.
Disinfectant products (chlorine solution, 4% cresyl, etc.) are effective against eggs and larvae.
In the case of a risk of epidemic (plague) it is essential to destroy the population of fleas without harming the host species (e.g. rat) because of the risk of human infestation would be increased.
Control is done by putting insecticide powder on the rodent's trails or in their nests. Permethrin (0.5%), propoxur (1%) or any other effective insecticide is used. (Organochlorines are generally ineffective.). The powder is laid down in lines 50 cm long and 3 mm wide near to a non-poisonous bait, to attract the maximum number of rodents.
Rodents
General points
Rodents make up about half the mammal population and thus play an important role as reservoirs of pathogens in the transmission of diseases to other mammals.
Domestic rodents (and those of medical importance) are composed essentially of three species of the muride family: the black rat, the brown rat and the mouse.
Methods of transmission
Pathogenic agents are transmitted by:
- an ectoparasite of the rodent which thus plays only a
secondary role (e.g. plague);
- rodent excrete (e.g. salmonella,
leptospirosis);
- a bite.
Biology
- The black rat
The adult measures about 40 cm from head to tail and weighs 250 g.
The muzzle is pointed, the ears round and protruding from the fur, and the eyes protuberant. The animal may be dark grey or brown.
The nest is built generally on the ground, in vegetation or in trees (and exceptionally in a burrow or sewer).
In houses the nests are generally built under the roof and the territory is more "aerial" than terrestrial with a radius of about sixty meters.
Its diet is very varied (vegetable and animals). Sexual maturity is reached at two months (5 litters of 7 to 8 rats per month).
- The brown rat (or sewer rat)
The colour is generally brown. It is bigger than the black rat and may exceed 400 g. Its muzzle is rounded and the eyes and ears are smaller than those of the black rat.
This species is not well adapted to hot countries. Nests are built in burrows (entrance diameter: about 8 cm).
The diet is less varied than that of the black rat. The brown rat prefers refuse and human wastes. Its biology is identical to that of the black rat.
- The domestic mouse
This is a well known universal species. Its biology is similar to that of the rats. It can survive with the water enclosed in food (flour, etc.) whereas the rat needs "free" water (e.g. infusion liquids).
Its maximum weight is 20 g, and its length 20 cm. For two animals of the same size, the head and feet are larger in the young rat.
Nests are built in any place where there is an accumulation of material for making the small shelter which the mouse needs, making control difficult, specially as the adult's sphere of activity is never more than a few meters.
Control methods
ENVIRONMENTAL HYGIENE
As for any other vectors, this means making the environment unsuitable for rodents, working on two fronts:
- Food
· packaging of stored food
· disposal of refuse
- Reproduction: eliminatation of likely sites (refuse tips, waste packaging scrub).
PROTECTION AGAINST RODENTS
The aim is to prevent access by rodents to important or vulnerable areas (food stores, infusion liquids, etc.).
- Block or protect all openings greater than 6mm with cement or
metal netting
(1 mm wire, mesh less than 6 mm dia).
- Fit discs on cables
joining roofs.
- Paint a smooth band on walls at 1m from the ground to
prevent passage on rough vertical surfaces.
- Fix galvanized sheet (1mm) at
the bottom of doors and on the skirtings.
Stores are always places where people come in and out and where doors are often left open. It is therefore useful, in addition to the above mentioned measures, to organise stores according to the following points:
- Repair all broken packages;
- Leave a passage (1m) between
walls or pillars and stacks, to allow inspection;
- Stack bags with care,
leaving a sufficient space between the top of the stack and the roof;
- Clean
the store daily and never let a stack remain intact for more than a month.
-
Inspect the store at least once per week, looking for:
· insects,
· signs of damage on the bags (water,
mould, fermentation, etc.),
· the presence of rodents,
· empty
bags and refuse not thrown away.
TRAPPING
This method never achieves complete eradication by itself. It may be used to get rid of the last few survivors of a chemical control campaign or individuals of an isolated and small infestation.
Spring traps are the only efficient models. The key points to follow are:
- Many traps should be used.
- The traps should be placed
perpendicular to the rodents' trails.
- Rat traps should be left unset for
several days so that the rats become used to them (except for mouse traps). A
well placed trap does not need bait.
POISONING (POISONED BAIT)
Two classes of product are used:
- Single dose poisons
These are only effective if the animal ingests a lethal dose at the first feed, otherwise it will not go back to the bait.
These substances are extremely toxic and in addition they need special skills and experience in rodent control if their use is to be at all effective. For information, they are:
· Zinc phosphate (1 to 5%),
· fluorocetamide
(2%),
· sodium fluoroacetate (0.25%),
· certain anticoagulants.
- Multiple-dose poisons
These are anticoagulants with a cumulative effect used at low doses, which have two advantages:
· The slowness of their effect allows the animal to absorb
a lethal dose before the first effects are felt.
· Their mode of action
makes them less dangerous to man and other domestic animals, and there is an
effective antidote.
Products in use
See the table on the following page.
The bait is bought ready to use, or made with broken cereal grains which are soaked over night to moisten them to make a thick paste. Sugar may be added (5%) to make it more attractive, as it is important to persuade the animal away from its usual food and get it to stick to this new diet.
The poison is then mixed in, and the bait is laid on the rodents' trails in piles of 25g (mice) or 200g or more (rats).
These baits should be out of reach of other animals. They can be laid in particular ways (e.g. a slightly open plastic bag, a short piece of pipe, a small wooden box, etc.).
Effects should be seen in 3 weeks for the brown rat, 4 to 5 weeks for the black rat and the mouse.
The baits are always renewed, and left in excess. The dead bodies should be disposed of quickly and well: pick them up twice per day and put them in a plastic bag (with their fleas).
Chemical control will only be effective if it is complemented by environmental hygiene and if both efforts cover the whole area concerned.
Periodic inspection should allow renewed control measures before being faced with a new massive infestation.
Figure
Precautions to be taken by the operator
Before use, the operator must be sure of the nature of the product and familiar with the manufacturer's specifications. In case of any doubt about the origin of this product, its storage conditions, or if the label is missing, a concentrated insecticide should never be used.
Check the spraying equipment. Pressured equipment should always be operated first with water to trace any leaks (often a cause of poisoning).
For engine-driven sprayers, protect the insecticide feed pipe from the exhaust pipe.
The preparation stage (dilution, filling the tank) is the most dangerous, as concentrated products are handled.
During preparation and treatment the following rules should be respected and enforced:
- Do not smoke, drink or eat.
- Do not keep cigarettes on
you.
- Do not put anything to your mouth (to unscrew, blow, unblock,
etc.).
- Wear protective equipment corresponding to the toxicity of the
product being used:
· Powder: dust-mask and gloves.
· Liquid: canvas
overalls, wide-brimmed hat, boots and gloves resistant to hydrocarbons, side
protection glasses and mask. For the mask, the cartridge should correspond to
the product being used and should be changed regularly (every 60 hours, in the
open air). Check that it is airtight before starting work (take care of beards,
hair, etc.).
- Make sure that these safety precautions are feasible (heat,
etc.).
- Do not spray if it is windy.
- Establish a rotation of the team
to avoid too long exposure for each individual.
- Empty and clean the
equipment at the place of treatment. Do not throw remaining products in ditches,
ponds, water courses or any place which may involve pollution of the aquatic
environment.
- Ensure that the staff are well trained in taking the above
measures.
- Ensure that the medical services have been warned and that they
have the means to take the necessary action in case of poisoning.
-Always
have a shower system available (bucket of water and soap).
Criteria for selecting staff
Avoid people with the following risk conditions when selecting staff to make up a treatment team:
- Pregnancy,
- Alcoholism, chronic or otherwise,
- History
of liver or nerve disorders,
- Heavy smoking,
- Allergies or skin
diseases.
More subjective criteria are also important:
- professional integrity,
- meticulous work,
- neatness
and tidiness.
Before starting to make up and train a team, find out if suitable people are already available in the region (although a mosquito control team is not trained to manage a programme to control lice, or do aerial spraying).
Precautions to take during transport and storage
TRANSPORT
One of the most frequent risks of poisoning by insecticides is from leakages of concentrated toxic products during transport. International legislation forbids the transport of concentrated products with foodstuffs. Serious accidents have already occurred through not respecting this basic rule.
For land transport, always repack drums with leaks or with worn corners at the base. Put straw (or other absorbent material) in the bottom of the vehicle.
This should be burned on arrival. Load with care, pack the drums closely together and tie them down to avoid them jumping up and down.
The packaging of certain powdered products needs special protection against rain (craft paper bags).
Direct contact between the driver and the load should be avoided (separate cab), specially for powdered and granulated products.
STORAGE
Insecticides should be stored under lock and key. They should be out of reach of children, animals and thieves. The store should be separate and at a distance from food stores. The building should be cool, well ventilated and dry. Ideally, the store should not be deep, so that drums of concentrated products may be handled without having to go right into the store. Raise the containers off the ground if there is any risk of flooding.
Long-term storage should be in metal drums coated on the inside with a flexible varnish. Use anti-rust paint if there is any trace of oxidisation. The drums should be stored on their sides with the plugs (of the drain holes) towards the bottom, and recovered with liquid, in order to avoid the entry of air and humidity which would oxidise and denature the product.
Never store more insecticides than necessary, as disposal of the excess requires very special techniques.
Empty containers
There are several important precautions which must be taken when reusing metal containers:
- Empty the container well.
- Rinse several times with a
detergent solution.
- Rinse a final time with a mixture of water, detergent +
10% sodium bicarbonate.
Leave in the container for several hours, stirring
from time to time, then rinse with clear water.
All the water used in this process should be disposed in a hole in the ground.
It is preferable to avoid reusing? the drums for food or water. If, for a good reason, this rule cannot be respected, make sure that the above measures have been taken.
The type of equipment depends on the product being used and on the type of treatment (surface, spatial, etc.).
Powders
- Soup spoon: treatment of individuals.
- Powder blower (hand
or knapsack): treatment of the ground, bedding, people.
- Pierced tin, or
jute sack: treatment of floors, of vegetation.
Liquids
-Aerial application
Just for information.
-Atomisers
This equipment gives an immediate and temporary treatment by creating a fog (condensation of the solvent in the air into very fine droplets).It is an engine-driven machine portable or mounted on a vehicle.
- Sprayers
This equipment gives a persistent treatment by spreading the insecticide in visible drops on walls, floors, stretches of water, etc.
Four techniques are used:
· The liquid is pumped in a tank.
· The liquid is
expulsed in a watertight receptacle by the compression of its surface
air.
· The liquid is carried away by a gaseous current.
· The
liquid is expulsed by
centrifugation.
Classification of insecticides
Chemical methods for insect
control
Formulations
Propoxur
Permethrin
Deltamethrin
Malathion
Pyrimiphos-methyl
Temephos
Repellents
Impregnation
of mosquito nets
Classification of insecticides
A classification enables the grouping of chemically related compounds, to deduce their toxicity and precautions for use.
MINERAL COMPOUNDS
- Mineral oils: spreading on the water surface asphyxiates and poisons larvae which are there. (mosquitoes, etc.).
ORGANOCHLORINE COMPOUNDS (NEUROTROPIC POISON)
- DDT (Dichloro-diphenyl-trichloroethane): a compound of low toxicity to vertebrates. Effective against mosquitoes, ectoparasites (lice, fleas, etc.).
Contact insecticide. Large problems of resistance and big-accumulation, not very biodegradable.
- Methoxychlorine: same as for DDT. Partially
biodegradable.
- HCH (Hexachloroocyclohexane) ("Lindane", "Gamurexane"): more
toxic, less persistent than DDT, but less resistance and more
biodegradable.
- Chlordane: used only for controlling cockroaches and
grasshoppers.
- Dieldrin: very toxic, problems of resistance. To be avoided.
ORGANOPHOSPHOROUS COMPOUNDS (ACETYLCHOLINESTERASE INHIBITOR)
- Malathion: low toxicity, used against ectoparasites and
mosquitoes.
- Fenitrothion: low toxicity, used against mosquitoes (eggs and
larvae).
- Fenthion: used against mosquito larvae in urban areas and in stock
raising areas.
- Temephos: almost no toxicity, used against larvae in
drinking water. Problems of resistance.
- Chlopyripos: urban larvicide.
-
Dichlorvos: against domestic arthropods (high toxicity and vapour
pressure).
- Chlophoxim: mosquito larvicide.
- Pyrimiphos-methyl: skin
contact dangerous, used by spraying (aqueous dilution), widely used in public
health work
CARBAMATES (ANTICHOLINESTERASICS)
- Propoxur: domestic insecticide, low toxicity.
- Carbaryl:
problems of resistance.
PYRETHRIN-PYRETHRINOIDS
- Decamethrin (Deltamethrin) ("K-Othrine"): low toxicity,
irritant to mucosa.
Effective alduticide, almost universally used but
expensive.
- Permethrin: ditto.
Figure
Formulations
- Technical product
Active ingredient in its purest commercial form. Used almost exclusively for ultra low volume (ULV) application.
- Powder and granules
Active ingredient (0.5 to 10%) with inert carrier (talc, gypsum, etc.). Powder is used for the control of lice and fleas. Granules allow better penetration of dense vegetation.
- Wettable powder
Active ingredient (20 to 80%) + wetting agent + inert carrier. Used for preparation of aqueous solutions.
- Concentrated suspension
Active ingredient in a fine powder (10 to 50%) + wetting agent + water. Used for preparing aqueous suspensions.
- Solution
Active ingredient dissolved in a solvent. As most insecticides are insoluble in water, the solvent is most commonly gas oil, kerosene or even acetone or xylene.
- Emulsifiable concentrate
Active ingredient (25% or more) + solvent + emulsifying agent (oil). This formulation allows dilution in water later.
- Emulsion
Emulsifiable concentrate + water.
- Slow-release formulations
Slow-dissolving capsules, granules, briquettes, etc., which allow continuous release of larvicide in water.
The concentration may be expressed as weight per volume (for liquid formulations) as weight per weight (dry formulations).
INTERNATIONAL CODE OF DIFFERENT FORMULATIONS (EXTRACT)
AB: bait as a grain
AE: aerosol generator
AL: other
liquids to be used without dilution
BB: bait as a block
BR:
briquette
CB: concentrate for preparation of bait
CG: granulated in
capsules
CS: capsules suspended in a liquid, to be diluted in water before
use
DP: dusting powder
EC: liquid concentrate, to be diluted in water
before use
EO: emulsion with oil, ready to use
EW: emulsion with water,
ready to use
FG: fine granules (0.3 to 2.5 mm)
GB: granulated bait
GG:
large granules (2 to 6 mm)
GR: granules ready for use
LA: Lacquer
MG:
micro-granules (0.1 to 0.6 mm)
OF: concentrated suspension to be diluted in
oil
OL: liquid to be diluted in oil
PB: bait in bars
RB: bait, ready
for use
SL: liquid formulation to dilute in water
SP: powder to dilute in
water
SU: suspension, ready to use for ULV treatment
TC: product in its
most concentrated commercial form
UL: liquid, ready to use for ULV
treatment
WP: wettable powder, for dispersion in water
Propoxur (Carbamate)
Commercial names
- Baygon
- Blattanex
- Unden
Toxicity (per os for rats)
- LD50 = 95 mg/kg
Mode of action
- Contact or ingestion
Formulation
- Powder to dilute: 1%, 2%
- Wettable powder: 50 %, 70%
Method of use
- Dusting powder
Ready to use at the rate of 1 to 2g of active ingredient (100 or 200g of powder per m2)
- Wettable powder
Dilute in water for a final concentration of 0.5 to 1% of active ingredient (powder at 50% > 20 g/litre, - powder at 70% > 1kg/litre), spray at a rate of 100 ml/m2
For use against
- Body lice
- (mosquitoes, cockroaches, bugs, fleas).
Cost
- Powder: about $3 US/kg (25kg metal drum).
Quantity to allow
- For treating 1,000 people for body lice: 40kg + losses.
Precautions
- Avoid inhaling (dust masks for treatment team).
Permethrin (Pyrethrinoid)
Commercial names
- Ambush
- Coopex
- Stomoxin
Toxicity (rats)
- LD50 = 430mg/kg
Mode of action
- Contact, ingestion
Formulation
- Dusting powder: 0.5 and 1%
- Concentrated solution: 25% and
10%
Method of use
- Dusting powder
Ready to use
- Concentrated solution
Depending on vector
For use against
- Lice
- Impregnation of mosquito nets
Cost
- Powder: about $2 US/kg (25kg bag)
- Concentrated solution:
about 16 US $/litre
Quantity to allow
- For treating 1,000 people for body lice: 40kg + losses.
Precautions
- Avoid contact with mucosa (dust mask, goggles).
- Possible
skin allergies.
- Do not rinse with hot water.
Deltamethrin (Pyrethrinoid)
Commercial names
- K-Othrine
- Decamethrin
- NRDC 161
- Cistin
-
Decis
Toxicity (rats)
- LD50 = 135 mg/kg
Mode of action
- Contact and ingestion
Formulation
- Wettable powder: 2.5%
- Concentrated liquid: 25g/litre
Method of use
- Wettable powder
One sachet of 33g/6litres of water
- Concentrated liquid
1 litre/200 litres of water
- Spray at the rate of 1 litre/10 m2
For use against
- Flies, cockroaches (bait)
- (fleas, ants, mosquitoes,
etc.).
Cost
- Wettable powder: about $3 US per 33g sachet
Quantity to allow
-1 sachet per 60 m2
Precautions
- No specific precautions
Malathion (organophosphate)
Commercial name
- Malathion
Toxicity (rats)
- LD50 = 2.100 mg/kg
Mode of action
- Contact
Formulation
- Concentrated liquid; concentration varies with manufacturer.
Method of use
- Prepare a 1% Malathion shampoo with a detergent solution. Apply 15 to 20 ml per person. Do not rinse for 24 hours.
For use against
- Headlice
Cost
- About $6 US/litre
Quantity to allow
- Depends on concentration of initial solution
Precautions
- Use a deodorised product.
Pyrimiphos-methyl (organophosphate)
Commercial name
- Actellic
Toxicity (rats)
- LD50 = 2.018 mg/kg
Mode of action
- Contact
Formulation
- Emulsifiable concentrate
- Wettable powder
- Dusting
powder
Method of use
- Flies
· Actellic 50 EC: 1 litre in 40 litres of water
·
Actellic 25 PM: 1kg in 20 litres of water
· Powder at 2%: ready for use
- Bait
1 g/m2 of powder at 2%, mixed with sugar half and half)
For use against
- Adulticide with immediate or residual effect on flies, mosquitoes, lice, fleas, etc.
Cost
- Concentrate at 50%: about $14 US/litre
- Powder, 1%: about
$4 US/kg; powder, 2%: about $5 US/kg
Quantity to allow
- Depends on formulation used
Precautions
Temephos (organophosphate)
Commercial name
- Abate
Toxicity (rats)
- LD50 = 8.600mg/kg
Mode of action
- Contact
Formulation
- 2% solution
- Emulsifiable concentrate
- Granules
-
Briquettes
Method of use
- Reservoir of drinking water: 56 to 112g of active
ingredient/hectare for 2 to 4 weeks
- River: 1g/m3 of flowing water for 10
minutes
For use against
- Mosquito larvae in drinking water
- Simulium (blackfly)
larvae
Cost
- 2 % solution: about $7 US/kg
Quantity to allow
- Depends on the formulation and the area to be treated.
Example: 2% solution: 3 ml/3 m3 of drinking water.
Precautions
- No specific precautions
Repellents
Repellents are chemical products used on cloth or on the skin for protection against insects.
Products used
- DEET or diethyltoluamide
- Dibutyl phtalate
- Dimethyl
phtalate
Formulations
- Lotion
The active ingredient is dissolved in an organic solvent. This formulation may be used on the skin or on cloth. Only natural fibres or nylon have no risk of reaction with the solvent.
- Cream
The active ingredient is incorporated in a cream.
An attractive effect has sometimes been noted during the first minutes. For this reason, creams are not effective until after 30 minutes.
Dose
The normal dose is:
- 20g of active ingredient per m2 (cloth, mosquito net,
etc.).
- 7g of active ingredient per person.
Effectiveness
This varies according to the species concerned. It may be assumed that 100% protection lasts not more than two hours, whatever the product, and that it is about 80% after 5 hours.
Precautions
- These products conform to the standards of the cosmetics
industry and do not pose any particular risks for the skin.
- Only benzyl
benzoate and dibutyl phtalate have a repellent action in a very humid
atmosphere.
Other repellents should be applied on a dry surface; this
application should be renewed if the surface has got wet (rain, excessive
sweating, etc.).
Impregnation of mosquito nets
The use of mosquito nets impregnated with insecticide gives individual protection against nocturnal insects in houses (carriers of malaria), which is much more effective than using an untreated net.
Choice of insecticide
Deltamethrin 2.5% EC or WP
Or, if
not, permethrin, 20 or 10% EC
Dose
-Deltamethrin: 25 mg of active ingredient per m2 of cloth
(minimum 15 mg/m2)
- Permethrin: 200 to 500 mg/m2
Impregnation method
1. Determine the total area of the cloth
2. Determine the volume of water absorbable by the cloth: dip several identical mosquito nets in a known volume of water, then wring lightly; measure the reduction in the volume of water and divide this volume by the number of mosquito nets (the average is about 15 ml per m2).
3. Dilution
Determine the quantity of active ingredient per mosquito net: multiply the dosage of active ingredient per m2 by the area of the net; then determine the corresponding volume of concentrated solution and thus the factor of dilution (volume of water + volume of concentrated solution).
Example:
- area: 18.7 m2
- dose of active ingredient: 25 mg/m2
-
product: deltamethrin 2.5 mg/m2
- volume of concentrated solution: 467.5 x
100 / 2500 = 18.7 ml
- volume for impregnation of mosquito net: 280 ml
-
dilution = 280. 18.7, or 1/15
4. Impregnation
- One net:
Put the mosquito net in a water-tight plastic bag. Add the predetermined volumes of water and insecticide for that mosquito net.
Close the bag and knead well to ensure good impregnation, then take out the mosquito net and leave it to dry, preferably flat, to avoid dripping and the movement of the insecticide to the bottom of the cloth.
Replace the mosquito net in the bag for storage and distribution.
- Several nets:
After having determined the dilution factor, prepare a volume of insecticide solution sufficient for the number of mosquito nets to be treated. Dip the nets, then wring lightly and proceed as above.
These operations should be performed by staff trained in the use of insecticides.
Take care when disposing of excess solution to avoid damaging aquatic life and affecting water quality.
Choose a coloured cloth which dirties less easily and which is therefore washed less often.
Persistence depends on the product and the climate but mostly on washing; a persistence of six months is realistic in most cases if the net is not washed.
Glossary
English French Spanish Definition
A
Absorption |
Absorption |
Absorpci/TD> |
Incorporation of one substance by |
| | |
another (e.g.: of a gas by a liquid, of a |
| |
|
liquid by the soil). |
|
| | |
Accumulation rate |
Taux d'accumulation |
Tasa de acumulati/TD> |
Rate at which decomposed fl matter |
| |
|
builds up in a latrine pit, expressed in |
| |
|
m3 per person per year, and used for the |
| |
|
calculation of effective pit volume. |
| |
| |
Activated carbon |
Charbon actif |
Carbon activo |
Specially prepared powdered or |
| | |
granulated carbon, used in final |
| | |
treatment of drinking water by |
| | |
absorption, particularly for the removal |
| |
|
of dissolved organic pollutants which |
| |
|
impart taste and odours to water. |
| | | |
Adsorbent |
Adsorbent |
Adsorbente |
Solid particle (e.g.: activated carbon) of |
| |
|
very large surface with the property of |
| |
|
fixing dissolved solids and colloids in |
| |
|
water. |
| | | |
Alternating twin |
Latrine a fosse |
Letrina sobre |
Latrine with two pits used alternately |
pit latrine |
double |
dos fosas | |
| | | |
Apron |
Tablier |
Banqueta |
Concrete surface surrounding the head |
| |
|
of a well for protection and drainage. |
| |
| |
Available chlorine |
Chlore actif |
Chloro activo |
Pure chlorine content of a chlorine- |
| |
|
generating product, expressed as a |
| | |
percentage, or in chlorometric degrees |
| |
|
(e.g.: 70% for calcium hypochlorite). |
| |
| |
Aquifer |
Nappe phrique |
Capa freatica |
Saturated, permeable, underground rock |
(water table) |
| |
formation. |
| | | |
Autoclave |
Autoclave |
Autoclave |
Equipment for sterilization by saturated |
| |
|
water vapour (humid heat) during 20 |
| |
|
mins at 135°C (2 bars) or 30 mins at |
| |
|
121°C (1 bar). |
B
Bacteria |
Bactes |
Bacterias |
Microscopic unicellular organisms, |
| | |
certain of which are disease-causing |
| |
|
agents. |
| | | |
Bacteriological |
Analyse |
Analisis |
Identification of bacteria of the coliform |
analysis |
bactologique |
bacteriolo |
group and/or other micro-organisms |
| | |
indicating contamination of water by |
| |
|
fl material. |
|
| | |
Biodegradation |
Biodegradation |
Biodegradation |
Natural process of destruction of |
(decomposition) |
| |
organic material by microbiological |
| |
|
activity. |
| | | |
Burying |
Enfouissement |
Enterramiento |
Action of covering with earth (e.g. |
| |
|
refuse: see controlled tipping). |
C
Calcium |
Hypochlorite |
Hipoclorito |
Chlorine-generating product in a form hypochlorite |
|
de calcium |
de calcio |
containing 65 to 70% available chlorine, |
| |
|
made by reacting chlorine with calcium |
| |
|
hydroxide. |
| | | |
Candle filter |
Bougie |
Filtro de porcelana |
Ceramic filter element (pore size: 0.45µ). |
| |
| |
Catchment |
Captage |
Captati/TD> |
Part of a well below the static level of |
| |
|
the water table which allows water to |
| |
|
flow into the well, or the emergence |
| |
|
zone of a spring where water may be |
| |
|
collected. |
| | | |
Catchment ring |
Buse de captage |
Tubo de captaci/TD> |
Perforated or porous concrete cylinder |
| |
|
sunk into the water table, through |
| | |
which water passes. |
|
| | |
Chemical analysis |
Analyse chimique |
An lisis quimico |
Identification of undesirable or toxic |
| |
|
chemical substances whose maximum |
| | |
permissible concentrations determine |
| |
|
the potability of water. |
| | | |
Chlorinated lime |
Clorure de chaux |
Cloruro de calcio |
Chlorine generating product (CaO |
| | |
2CaOCl2) in powder form, containing |
| |
|
30% chlorine. Less stable than calcium |
| |
|
hypochlorite. |
|
| | |
Chlorine |
Chlore |
Cloro |
Reactive element (Cl) with strong |
| | |
oxidising powers, used for the |
| | |
disinfection of water (destruction of |
| |
|
organic material and biocidal action). |
| |
| |
Chlorine compound |
Produit grateur |
Derivado Product |
used for disinfecting water, |
|
de chlore |
del cloro |
containing a proportion of available |
| |
|
chlorine which is released or dissolving |
| |
|
in water. |
| | | |
Chlorine demand |
Demande |
Demanda |
Difference between amount of chlorine |
|
en chlore |
de cloro |
added to water and total residual |
| | |
chlorine level after 30 mins (= chlorine |
| |
|
consumed). |
| | | |
Combined residual |
Chlore rduel |
Cloro residual |
Fraction of chlorine added to water |
chlorine |
combine |
combinado |
which is not consumed, but combined |
| |
|
with certain substances (with some |
| | |
disinfectant power, but less than free |
| |
|
residual chlorine). |
|
| | |
Concrete ring |
Buse |
Tubo de concreto |
Short concrete cylinder for supporting |
| |
|
and lining the sides of a well to make |
| |
|
them impermeable. |
|
| | |
Contact time |
Temps de contact |
Tiempo de contacto |
Period necessary for the reaction of |
| |
|
chlorine with organic matter contained |
| |
|
in water (more or less 30 minutes). |
| |
| |
Contamination |
Contamination |
Contaminati/TD> |
Introduction of potentially pathogenic |
(pollution) |
| |
micro-organisms or chemical |
| | |
substances presenting health risks into |
| |
|
the environment. |
|
| | |
Controlled tipping |
Darge control |
Relleno sanitario |
Method of disposal of solid wastes by |
(sanitary landfill) |
| |
burial in successive layers in ground |
| |
|
exclusively reserved for this purpose. |
D
DPD1 |
DPD1 |
DPD1 |
Diethyl-p-phenyline diamine. Used in |
| |
|
tablet form with a colorimetric |
| | |
comparator to measure free residual |
| |
|
chlorine. |
| | | |
Defecation |
Dcation |
Defecaci/TD> |
Passage of waste matter from the |
| | |
bowels. |
| | | |
Detergent |
Drgent |
Detergente |
Compound used in cleaning (e.g. |
| | |
washing clothes), often found in |
| | |
polluting wastewater. |
| | | |
Disinfect |
Dnfecter |
Desinfectar |
To kill a large proportion of micro |
| |
|
organisms present in water or on a |
| | |
surface. |
| | | |
Distribution box |
Bo de distribution |
Caja distribuidora |
Construction for collecting effluent from |
| |
|
a septic tank and distributing it equally |
| |
|
among drains in a multiple trench |
| | |
infiltration system. |
|
| | |
Domestic refuse |
Dets mgers |
Basuras |
Putrescible or non-putrescible solid |
/waste | | |
waste material from household |
| | |
activities. |
|
| | |
Drain |
Drain |
Tubo de desague |
Underground pipe with pierced holes or |
| |
|
slots to a allow the passage and |
| | |
infiltration of water. |
| | | |
Drainage |
Drainage |
Drenaje |
Removal of water by ditches or pipes. |
E
Effective grain |
Granulometrie |
Granulomica |
Range and average of size of grains of |
size | | |
sand or other material used as a filter |
| |
|
material. |
| | | |
Effluent |
Effluent |
Effluente |
Partially or totally treated wastewater |
| |
|
coming from a treatment unit and going |
| |
|
to secondary treatment or disposal in. |
| |
| |
Emergence/eye |
Rrgence |
Resurgimiento |
Place where spring water appears at the |
| |
|
surface. |
| | | |
Evapotranspiration |
Evapotranspiration |
Evapotranspiraci/TD> |
Removal of water into the air by a |
| | |
combination of direct evaporation and |
| |
|
transpiration by plants. |
F
Faeco-oral |
Transmission |
Transmici/TD> |
Transmission of pathogens from fl |
transmission |
f-orale |
oro-fecal |
matter to the digestive system via the |
| |
|
mouth (fl contamination of water, |
| |
|
food, hands, etc). |
|
| | |
Ferrocement |
Ferrociment |
Ferrocemento |
Technique of constructing walls by |
| | |
applying layers of cement mortar to a |
| |
|
framework of wire/mesh. |
| | | |
Filtration |
Filtration |
Filtraci/TD> |
Passage of water through a porous layer |
| |
|
(filter) which traps suspended solid. |
| |
| |
Free residual |
Chlore rduel |
Cloro residual |
Fraction of available chlorine added to |
chlorine |
libre |
libre |
water which remains in excess and |
| | |
which still has disinfectant power after |
| |
|
30 minutes contact time (0.3 to 0.5mg/l). |
G
Grease trap |
Bac daisseur |
Trampa para grasa |
Construction for separating fatty |
| | |
material from wastewater before |
| | |
disposal in a soakaway pit or infiltration |
| |
|
field. |
| | | |
Groundwater |
Eau souterraine |
Agua subterr nea |
Infiltrated water contained in |
| | |
underground layers, forming a body of |
| |
|
water. |
H
Helminths |
Helminthes |
Helmintos |
Parasitic worms of man and other |
| | |
animals (e.g. ascaris). |
| | | |
Hot air sterilizer |
Poupinel |
Pupinel |
Equipment for sterilization by hot air |
| |
|
(dry heat) during 120 minutes at 160°C |
| |
|
or 90 minutes at 170°C. |
| | | |
Human wastes |
Dets humains |
Desechos humanos |
Faeces and urine (excreta). |
| | | |
Hygiene |
Hygi |
Higiene |
Practice related to keeping clean and |
| |
|
healthy. |
I
Incineration |
Incintion |
Incineraci/TD> |
Action of reducing refuse to ashes (e g. |
| |
|
incineration of medical refuse). |
| | | |
Infiltration |
Tranch |
Zanja de |
Structure for disposing of wastewater |
trench |
d'infiltration |
absorci/TD> |
by underground drainage, using |
| | |
trenches and drains. |
|
| | |
Irrigated garden |
Jardin irrigu/TD> |
Jardin irrigado |
Vegetable garden watered with |
| | |
wastewater recovered from water |
| | |
points (an alternative technique to |
| |
|
infiltration systems). |
L
Leachate |
Liquide de |
Liquido residual |
Liquid resulting from the |
|
fermentation |
de fermentaci/TD> |
decomposition of organic matter in a |
| |
|
refuse tip. |
|
| | |
Lysol |
Lysol |
Lysol |
Solution of cresol and soap (powerful |
| |
|
disinfectant used for floors and other |
| |
|
surfaces). |
M
Medical waste |
Dets mcaux |
Desechos mcos |
Refuse from the activities of a health |
| |
|
centre. Medical waste is potentially |
| |
|
contaminated (see Contamination). |
| | | |
Micro-organisms |
Micro-organismes |
Micro-organismos |
Microscopic animal or vegetable |
| | |
organisms. |
| | | |
Motorpump |
Motopompe |
Motobomba |
Pump powered by an electric motor or |
| |
|
combustion engine. |
N
Non-return valve |
Clapet anti-retour |
Valvula de |
Valve allowing water to flow in one |
|
retenci/TD> |
direction |
only, installed at the start of a |
| | |
delivery pipe from a motorpump to |
| | |
stop backflow when pumping stops. |
O
Oxidize |
Oxyder |
Oxidar |
To transform into the oxidised state by |
| |
|
combination with oxygen. |
| | | |
Organic matter |
Matieres organiques |
Materias organicas |
Residues and extracts of living |
| | |
organisms. |
P
Permeability |
Permilit/TD> |
Permeabilidad |
Ability of soil to allow water to |
| | |
infiltrate. |
|
| | |
Pit latrine |
Latrine a fosse |
Letrina |
Latrine with a single pit dug in the |
|
simple |
simple |
ground. |
| | | |
pH |
pH |
pH |
Expression of the degree of acidity or |
| |
|
alkalinity of a substance. The value of |
| |
|
7.35 is neutral; values above this are |
| |
|
alkaline, values below are acidic. |
| | | |
Phenol Red |
Rouge de phl |
Rojo de fenol |
Chemical compound used to measure |
| | |
pH by colorimetric comparison. May be |
| |
|
in tablet form. |
|
| | |
Pour-flush |
Latrine a siphon |
Letrina con |
Latrine in which the slab has a pan and |
latrine |
d'eaude |
sifon de ague |
water trap which is flushed manually. |
| |
| |
Protozoa |
Protozoaires |
Protozoares |
Group of unicellular microscopic |
| | |
animals, certain of which cause disease |
| |
|
(e.g amoeba). |
R
Rainwater |
Eaux pluviales |
Aguas pluviales |
Water from atmospheric precipitation |
| |
|
which may form a water source. |
| | | |
Resurgence |
Rrgence |
Resurgirmiento |
See Emergence. |
|
| | |
Retention time |
Rntion |
Retenci/TD> |
Time during which wastewater is held |
| |
|
in a tank to undergo treatment (e.g. 1 to |
| |
|
3 days for a septic tank). |
| | | |
Run-off |
Eaux de |
Aguas de |
Water flowing naturally on the ground |
|
ruissellement |
escurrimiento |
surface. |
S
Sanitary |
Inspection sanitaire |
Inspeccianitaria |
Field observation, using criteria to |
inspection | |
|
evaluate the environmental hygiene |
| | |
status of a settlement (e.g. refugee |
| |
|
camp). |
| | | |
Schmutzdecke |
Schmutzdecke |
Schmutzdecke |
Biological layer playing a purifying role, |
| |
|
at the surface of a slow sand filter. |
| |
| |
Sedimentation/ |
Smentation |
Sedimentaci/TD> |
Process of deposition of suspended |
settling | |
|
solids in water by gravity. |
| | | |
Septic tank |
Fosse septique |
Fosa sica |
Tank for collection and partial treatment |
| |
|
of household wastewater before |
| | |
disposal by sub-surface drainage. |
| | | |
Sewage |
Eaux vannes |
Aguas negras |
Wastewater from sanitation installations |
| |
|
(containing excrete). |
| | | |
Slow sand |
Filtration lente |
Filtraci/TD> |
Water treatment technique which |
filtration | |
lenta en arena |
combines mechanical filtration (sand) |
| |
|
with biological purification (see |
| | |
Schmutzdecke). |
|
| | |
Soakaway pit |
Puits perdu |
Pozo de |
Hole filled with stones, used for |
| |
absorci/TD> |
infiltration of wastewater. |
| | | |
Sodium |
Hypochlorite |
Hipoclorito |
Chlorine-generating product (NaOCl) |
hypochlorite |
de calcium |
de calcio |
with 5 to 15 % available chlorine, much |
| |
|
less stable than solid products. |
| | | |
Sodium |
Thiosulfate |
Tiosulfato |
Crystalline chemical substance used for |
thiosulphat |
de calcium |
de sodio |
dechlorinating drinking water. |
| | | |
Spring |
Source |
Manantial |
Ground water which flows naturally to |
| |
|
the surface. |
|
| | |
Standing |
Eaux satgnantes |
Aguas |
Water from rain or human activities |
stagnant water |
estancadas |
which stays on the ground surface. | |
| | | |
Sterile |
Stle |
Estl |
That which contains no germs or any |
| |
|
other form of life. |
|
| | |
Sterilization |
Stlisation |
Esterilizaci/TD> |
Elimination of all microorganisms from |
| |
|
water or from a surface: virus, bacteria |
| |
|
and microscopic fungi. |
| | | |
Stormwater |
Eaux pluviales |
Aquas pluviales |
Rainwater running on the ground |
(rein run-off) |
| |
surface (collected and disposed of |
| | |
separately from wastewater). |
| | | |
Stock solution |
Solution m |
Soluciadre |
Concentrated chlorine solution, |
| | |
generally 1%, used for chlorinating a |
| |
|
known volume of water. |
| | | |
Strainer |
Crne |
Pichancha |
Filter at the bottom of a motorpump |
| |
|
suction pipe to keep back large |
| | |
impurities. Often used with a non |
| | |
return foot valve. |
|
| | |
Submersible pump |
Pompe immerg |
Bomba submergida |
Pump with the pumping part under the |
| |
|
water (delivery only). |
| | | |
Subsurface |
Epandage |
Esparcimiento |
Treatment and elimination of drainage |
|
souterrain |
subterraneo |
wastewater by infiltration into the |
| |
|
subsoil. |
| | | |
Sullage/grey water |
Eaux mgs |
Aguas usadas |
Wastewater from kitchens and |
| | |
bathrooms. |
| | | |
Surface pump |
Pompe de surface |
Bomba de superficie |
Handpump or motorpump with the |
| | |
pumping part at the surface (suction |
| |
|
head limited to 7m). |
|
| | |
Surface water |
Eau de surface |
Agua superficial |
Water from precipitation, making |
| | |
streams, rivers, lakes, ponds, etc. |
| |
| |
Suspended |
Matis en |
Materias en |
Organic and mineral particles solids |
suspension |
suspenci/TD> |
suspended |
in water. |
T
Trench latrines |
Feuill |
Letrinas |
Shallow trenches used for defecation in |
| |
atrincheradas |
certain emergency situation. |
| | | |
Turbid water |
Eau turbide |
Aqua turbida |
Water containing fine particles in |
| | |
suspension which gives it a cloudy |
| | |
appearance (turbidity is expressed in |
| |
|
NTU units). |
V
Ventilated improved |
Latrine ventilee |
Letrina ventilada |
Pit latrine equipped with a ventilation pit |
(VIP) latrine |
amelior |
mejorada |
pipe to reduce flies and odour, with a fly |
| |
|
screen at the top. |
|
| | |
Virus |
Virus |
Virus |
Extremely small living organisms, |
| | |
which can only multiply inside living |
| |
|
cells which they parasitise. |
W
Washing aria |
Aire de lavage |
Lavadero |
Area or structure designed for washing |
| |
|
clothes and personal hygiene (washing |
| |
|
slab, wash tub etc). |
|
| | |
Wastewater |
Eaux us |
Aguas servidas |
Sewage and sullage. |
|
| | |
Well |
Puits |
Pozo |
Hole in the ground which enters an |
| | |
anderground body of water (water table) |
| |
|
to allow its abstraction. |
Conversion tables
Distances |
Surface |
1 km = 0.6214 miles |
1 km2 = 0.386 miles2 = 100 ha |
1 m = 1.0936 yards |
1 ha = 2.471 acres = 10000 m2 |
1 cm = 0.394 inches |
1 m2 = 1.196 yd = 10000 cm2 = 10.76 in2 |
1 mile = 1.609 km |
1 mile2 = 2.59 km2 = 240 acres = 259 ha |
1 yard = 0.914 m |
|
1 foot = 0.305 m |
1 acre = 0.405 ha = 4.840 yd2 |
1 foot = 30.48 cm |
1 yd2 = 0.836 m2 = 9 ft2 |
1 inch = 2.54 cm |
1 ft2 = 0.09 m2 = 144 inch2 = 930 cm2 |
1 inch2 = 6.54 cm2 |
|
Volume |
Capacity |
1 m3 = 1.307 yd3 = 1000 litres |
1 litre = 0.22UK Gal. |
1 m3 = 35.32 ft3 |
= 1.76 UK Pints |
1 cm3 = 0.061 in3 |
= 0.26US Gal |
1 yd3 = 0.765 m3 = 27 ft3 |
= 2.11US Pints |
1ft3 = 28.32 litres = 1728 in3 |
1ml = 0.0675 fluid ounces (fl.oz.) |
1in3 = 16.39 ml |
1 UK Gal. = 4.55 litres = 8 UK Pints = 1.20 US Gal. |
|
1 US Gal. = 3.791 litres = 8 US Pints = 0.83UK Gal. |
Weight |
|
1 tonne = 0.984 long (UK) tons |
1 UK Pint = 0568 litre = 20 fl. oz. |
= 1.102 short (US) tons |
1 US Pint = 0.473 litre = 16 fl. oz. |
= 2204 pounds (lb) |
1 fl. oz. = 28.41 ml |
1 kg = 2.205 lb |
|
= 35.27 oz |
Water weight (at 16.7°, so 62°F) |
1 g = 0.03oz 1litre = 1kg | |
1 UK ton = 1016 kg = 2240 lb |
1 UK Gal.= 10lb |
1 US ton = 907.1 kg = 2000 lb |
1 US Gal.= 8.33lb |
1 UK ton = 1.1 US ton | |
1 lb = 0.4 kg = 16 oz = 453.6g | |
1oz = 28.35g |
|
Temperatures
From Centigrade to Farenheit: multiply by 1.8 (9/5) and
substract 32.
From Farenheit to Centigrade: add 32 and multiply by 0.555
(5/9).
0°F =-17.8°C
32°F =0°C
50°F
=10°C
68°F =20°C
98.4°F=36.9°C
104°F
=40°C
Materials and work estimate
(From A Handbook of Gravity-Flow Water Systems [18])
EXCAVATIONS Per m3
Ordinary soil 0.55 man - days (m - d)
Gravelly soil 0.77 m -
d
Boulder mix 1.10 m - d
Medium rock cutting 1.60 m - d
Hard rock
cutting 2.50 m - d
WOOD WORKING Per m3 of finished wood
Skilled labour 18 men - day
Unskilled labour 18 men - day
STONB AGGREGATE PRODUCTlON Per m3 of crushed rock
Unskilled labour 14 men - day
CONCRETE Per m3: 1: 2 4 mix 1:1: 3 mix
Cement 0.25 m3 0.33 m3
Sand 0.50 m3 0.50 m3
Aggregate 1.00
m3 1.00 m3
Mason labour 1.1 man - days 1.1 man - days
Unskilled labour 4.0
man - days 4.0 man - days
PLASTER* Per m3:1:4 mix 1: 3 mix 1: 2 mix
Cement 0.0025 m3
0.0030 m3 0.0050 m3
Sand 0.01 m3 0.01 m3 0.01 m3
Mason labour 0.14 m - d
0.14 m - d 0.14 m - d
Unskilled labour 0.22 m - d 0.22 m - d 0.22 m - d
*
Each coat of plaster = 1 cm thick
BRICK MASONRY (1: 4 mortar) Per m3
Bricks 75%
Cement 0.063
m3
Sand 0.25 m3
Mason labour 1.4 m - d
UnskiUed labour 2.8 m - d
RUBPLE-STONE MASONRY (1: 4 mortar) Per m3
Cement 0.089
m3
Sand 0.35 m3
Mason labour 1.4 m - d
Unskilled labour 3.2 m - d
DRESSBD-STONB MASONRY (1: 4 mortar) Per m3
Cement 0.075
m3
Sand 0.30 m3
Mason labour 2.8 m - d
Unskilled labour 5.0 m - d
SPECIPIC WEIGHTS kg/m3
Portland cement: 1,440
Brick
masonry: 2,120
Stone masonry: 2,450
Concrete: 2,409
Seasoned wood:
650
Water: 1,000
Dry-stone masonry
2,000
1. ASSAR M.
Guide d'assainissement en cas de catastrophe
naturelle
OMS - Gen -1971
2. BURGEAP
La construction des puits en Afrique
tropicale
Minist de la Cooption et du Dloppement - Paris -1981
3.* CAIRNCROSS S., FEACHEM R
Small water supplies
Ross
Bulletin 10 - 1978
4.* CAIRNCROSS 57 FEACHEM R.
Environmental health engineering
in the tropics: an introduction text
John Willey - 1983
5.* CHLEQ J.L., DUPRIEZ H.
Eau et terres en
fuite
L'Harmattan - Enda - 1984
6. COMITE FRANCAIS D'EDUCATION POUR LA SANTE
Promotion de la
santdocument technique nes eaux us faciles
...
traiter
Minist de la Sant Paris - 1987
7. DIRECCION DE ENGENIERIA SANITARIA, SECRETARIA DE SALUBRIDAD Y
ASISTENCIA
Manual de saneamiento, agua, vivienda y desechos
Limusa -
Mco - 1984
8. FEACHEM R., BRADLEY D., GARELICK H., MARA D.
Sanitation
and disease: health aspects of exereta and wastewater management
John Willey
- 1983
9. FEACHEM R., MC GARRY M., MARA D.
Water, wastes and health
in hot climates
John Willey - 1977
10. GARANCHERJ.
L'assainissement automome individual et
collectif
Editions du moniteur - Paris - 1986
11. GAULENE M.C. PERRAULT A.M.
Lutte antivectorielle contre
la trypanosomiase humaine en Haute-Volta
Th de doctoral en mcine -
Toulouse - 1982
12. GENTILINI M., DUFLO B.
Mcine tropicale
Flammarion -
1986
13. GRET
Le point sur la construction de citernes, Recueil et
stockages des eaux de pluies
GRET - Paris - 1984
14. GRUNDFOS
La pompe en agriculture
Agri - Nathan - 1984
15.*HCR
Manuel des situations d'urgence. Premi partie:
Options sur le terrain
HCR - Gen - 1982
16. HELVETAS COOPERATION SUISSE AU DEVELOPPEMENT
Manuel
technique pour I'approvisionnement en eau des zones rurales
SKAT, ATOL - 1981
17.*HOWARD J.
Safe drinking water. An Oxfam Technical
guide
Oxfam - Oxford - 1978
18.*JORDAN T.D. Jr.
A handbook of gravity-flow water
systems
Intermediate Technology Publication - 1984
19. LANOI J.N., ROY M.L.
Manuel du technician
sanitaire
OMS - Gen - 1976
20. MARA D.
Sewage treatment in hot climates
John Willey -
1976
21.*MARA D.
The design of pour-flush latrines TAG - Technical
note nR>UNDP - World Bank - 1984
22. MARA D.
The design of pour-flush latrines TAG - Technical
note nR>UNDP - World Bank - 1985
23. MINISTERE DE LA COOPERATION
Memento de l'adjoint
technique des travaux ruraux
Minist de la Cooperation - Paris - 1977
24. OMS
Normes internationales pour I'eau de boisson - 3
tion
OMS - Gen - 1972
25. OMS
Directives de qualitour l'eau de boisson, Volumes
1 et 3
OMS - Gen - 1985
26. OMS
Techniques de base pour le laboratoire mcal
OMS
- Gen - 1980
27. OMS
Guide pratique pour l'eau potable et l'assainissement
rural et suburbain
OMS - Copenhague - 1984
28. OMS
Les leishmanioses
OMS - Gen - 1984
29.*OMS
Lutte antivectorielle en santnternationale
OMS-
Gen - 1973
30. OMS
La trypanosomiase africaine: dologie et
lutte
OMS - Gen - 1986
31.*RAJAGOPALAN S7 SHIFFMAN M.
Mesures simples contre les
maladies intestinales
OMS - Gen - 1975
32. RODHAIN F., PEREZ C.
Prs d'entomologie mcale et
vrinaire
Maloine Sa. Editeur - Paris - 1985
33. ROSS INSTITUTE
Control of domestic flies
Ross
Institute Bulletin - n1982
34. ROSS INSTITUTE
Insecticides
Ross Institute Bulletin -
n1981
35.*SIMMONDS S., VAUGHAN P., GUNN S.W.
Refugee community
health care
Oxford University Press - 1983
36. SOGREAH
Les pompes et les petites stations de
pompage
Minist de la Cooperation - Paris - 1978
37.*STERN P. et al.
Field engineering: an introduction to
development work and construction in rural areas
Intermediate Technologies -
London - 1983
38. TDRI
Food storage manual
TDRI, 2nd edition - England -
1983
39. THEUNYNCK S., HALTER A.
Filtre ... sable et ... charbon
de bois
Fiche n- GRET - Paris
40. TROPICAL HEALTH TECHNOLOGY
Medical laboratory manual for
tropical countries, Volume II
Monica Cheesbrough - 1984
41.*U.S.A.I.D.
Water for the world - Technical
notes
Agency for international development - Washington
42.*UNICEF
Aide aux situations d'urgence
UNICEF - Gen,
New York - 1986
43. WHO
Chemical methods for the control of arthropod vectors
and pests of public health importance
WHO - Gen - 1984
44. WHO
Equipment for vector control
WHO - Second Edition
- Gen - 1974
45.*WINBLAD U., KILAMA W.
Sanitation without
water
MACMILLAN - London -
1985